 "name": "The Gigawatt Ledger",
 "url": "https://siscto.si/ledger/",
 "method": "https://siscto.si/ledger/method/",
 "as_of": "2026-11-11",
 "announcements_read": "2026-11-11",
 "built_by": "The $SIS community (siscto.si), built by Codeflex",
 "reuse": "Reuse with credit and a link to https://siscto.si/ledger/. Figures under epoch_ai are from Epoch AI, \"AI data centers\", CC BY 4.0 (https://epoch.ai/data/ai-data-centers), retrieved 2026-11-10.",
 "totals": {
  "projects": 24,
  "projects_with_stated_power": 18,
  "announced_mw": 14797,
  "confirmed_energized_low_mw": 3296.0,
  "confirmed_energized_high_mw": 4245.0,
  "share_confirmed": "22% to 29%",
  "upper_figures_not_counted_mw": 6540,
  "by_state": {
   "Announced": 0,
   "Under construction": 13,
   "Partly energized": 6,
   "Energized": 4,
   "Delayed": 1,
   "Cancelled": 0
  },
  "by_operator": [
   {
    "operator": "OpenAI",
    "projects": 6,
    "announced_mw": 7085,
    "confirmed_low_mw": 1154.0,
    "confirmed_high_mw": 1154.0
   },
   {
    "operator": "Meta",
    "projects": 2,
    "announced_mw": 3000,
    "confirmed_low_mw": 471.0,
    "confirmed_high_mw": 612.0
   },
   {
    "operator": "SpaceXAI",
    "projects": 1,
    "announced_mw": 2000,
    "confirmed_low_mw": 1000,
    "confirmed_high_mw": 1701.0
   },
   {
    "operator": "Microsoft",
    "projects": 1,
    "announced_mw": 900,
    "confirmed_low_mw": 0,
    "confirmed_high_mw": 0
   },
   {
    "operator": "CoreWeave",
    "projects": 4,
    "announced_mw": 860,
    "confirmed_low_mw": 328.0,
    "confirmed_high_mw": 435
   },
   {
    "operator": "Fluidstack",
    "projects": 2,
    "announced_mw": 647,
    "confirmed_low_mw": 268.0,
    "confirmed_high_mw": 268.0
   },
   {
    "operator": "Nscale",
    "projects": 1,
    "announced_mw": 230,
    "confirmed_low_mw": 0,
    "confirmed_high_mw": 0
   },
   {
    "operator": "Nebius",
    "projects": 1,
    "announced_mw": 75,
    "confirmed_low_mw": 75.0,
    "confirmed_high_mw": 75
   }
  ]
 },
 "states": {
  "Announced": "A public announcement exists and no public evidence of construction has been read.",
  "Under construction": "Work on the ground is confirmed and nothing is confirmed as running yet.",
  "Partly energized": "Part of the announced power is confirmed as running.",
  "Energized": "Public evidence puts the running power at 95% or more of the announced figure, or shows every building running where no figure was stated.",
  "Delayed": "Nothing is running, a promised date has passed, and a linked source shows it was not met.",
  "Cancelled": "A linked source says the project was dropped."
 },
 "projects": [
  {
   "slug": "colossus-memphis",
   "name": "Colossus (Memphis and Southaven)",
   "url": "https://siscto.si/ledger/colossus-memphis/",
   "operators": [
    "SpaceXAI"
   ],
   "filed_under": "SpaceXAI",
   "town": "Memphis",
   "region": "Tennessee",
   "country": "United States",
   "state": "Partly energized",
   "state_evidence": "Public evidence puts 1 to 1.7 GW in operation as of June 15, 2026, against 2 GW announced: 50% to 85%. The range covers every figure listed below.",
   "announced_mw": 2000,
   "announced_basis": "capacity, basis not stated",
   "announced_text": "almost 2 GW of training compute",
   "announced_source": "siliconangle-2025-12-30",
   "upper_figure_mw": null,
   "upper_figure_text": null,
   "confirmed_low_mw": 1000,
   "confirmed_high_mw": 1701.0,
   "counted_low_mw": 1000,
   "counted_high_mw": 1701.0,
   "evidence_as_of": "2026-06-15",
   "epoch_ai": {
    "it_mw": 1286.0,
    "facility_mw": 1701.0,
    "buildings_operating": 3,
    "sites": [
     {
      "name": "Colossus 1",
      "power_map": "https://siscto.si/power-map/colossus-1/",
      "it_mw": 340.0,
      "facility_mw": 425.0,
      "as_of": "2026-06-15",
      "status": "Operating"
     },
     {
      "name": "Colossus 2",
      "power_map": "https://siscto.si/power-map/colossus-2/",
      "it_mw": 946.0,
      "facility_mw": 1276.0,
      "as_of": "2026-06-15",
      "status": "Operating, expanding"
     }
    ]
   },
   "schedule_note": null,
   "announcements": [
    {
     "id": "mlgw-2025-05-05",
     "type": "announcement",
     "date": "2025-05-05",
     "undated_page": false,
     "who": "Memphis Light, Gas and Water",
     "kind": "Utility",
     "title": "xAI Update, May 5, 2025",
     "publisher": "MLGW",
     "url": "https://www.mlgw.com/images/content/files/pdf/new/5-5-25%20xAI%20Update.pdf",
     "summary": "The city utility reports what xAI receives and has asked for at its first site on Paul Lowry Road, and the options discussed for the second site on Tulane Road.",
     "quotes": [
      "xAI requested an additional 150MW at this location, for a total of 300MW.",
      "a range of grid power options from 260MW to 1.1GW has been discussed"
     ],
     "power_stated": "300 MW requested at the first site; 260 MW to 1.1 GW discussed for the second",
     "promised": "300 MW at the first site by no later than December 2025",
     "confirmed_mw": null,
     "used_in_total": null
    },
    {
     "id": "siliconangle-2025-12-30",
     "type": "announcement",
     "date": "2025-12-30",
     "undated_page": false,
     "who": "Elon Musk, reported by SiliconANGLE",
     "kind": "Company statement, quoted by the press",
     "title": "Elon Musk reveals plan to expand xAI's 'Colossus' data center to 2 gigawatts",
     "publisher": "SiliconANGLE",
     "url": "https://siliconangle.com/2025/12/30/elon-musk-reveals-plan-expand-xais-colossus-data-center-2-gigawatts/",
     "summary": "SiliconANGLE quotes Elon Musk's post on X about a third building in Southaven, Mississippi. The figure is the company's own statement, so it is counted.",
     "quotes": [
      "xAI has bought a third building called MACROHARDRR. Will take xAI training compute to almost 2GW."
     ],
     "power_stated": "Almost 2 GW of training compute for the whole complex",
     "promised": "The third building becomes a data center during 2026",
     "confirmed_mw": null,
     "used_in_total": null
    }
   ],
   "evidence": [
    {
     "id": "mlgw-2025-05-05-e",
     "type": "evidence",
     "date": "2025-05-05",
     "undated_page": false,
     "who": "Memphis Light, Gas and Water",
     "kind": "Utility",
     "title": "xAI Update, May 5, 2025",
     "publisher": "MLGW",
     "url": "https://www.mlgw.com/images/content/files/pdf/new/5-5-25%20xAI%20Update.pdf",
     "summary": "The utility states the grid power it delivered to the first site on that date.",
     "quotes": [
      "xAI is receiving 150MW of power at the Paul Lowry site."
     ],
     "power_stated": "",
     "promised": "",
     "confirmed_mw": 150,
     "used_in_total": false
    },
    {
     "id": "sec-s1-2026-05-20",
     "type": "evidence",
     "date": "2026-05-20",
     "undated_page": false,
     "who": "Space Exploration Technologies Corp.",
     "kind": "Public filing",
     "title": "Form S-1 registration statement",
     "publisher": "U.S. Securities and Exchange Commission",
     "url": "https://www.sec.gov/Archives/edgar/data/1181412/000162828026036936/spaceexplorationtechnologi.htm",
     "summary": "The company's registration statement gives one figure for both facilities together.",
     "quotes": [
      "Our AI compute facilities, COLOSSUS and COLOSSUS II, collectively provide approximately 1.0 gigawatt of compute power"
     ],
     "power_stated": "",
     "promised": "",
     "confirmed_mw": 1000,
     "used_in_total": true
    }
   ]
  },
  {
   "slug": "meta-hyperion",
   "name": "Meta Hyperion",
   "url": "https://siscto.si/ledger/meta-hyperion/",
   "operators": [
    "Meta"
   ],
   "filed_under": "Meta",
   "town": "Richland Parish",
   "region": "Louisiana",
   "country": "United States",
   "state": "Under construction",
   "state_evidence": "Epoch AI tracks the site as under construction, with no building operating as of April 19, 2026.",
   "announced_mw": 2000,
   "announced_basis": "capacity, basis not stated",
   "announced_text": "over two gigawatts of compute capacity",
   "announced_source": "meta-richland",
   "upper_figure_mw": 5000,
   "upper_figure_text": "scale up to 5 gigawatts",
   "confirmed_low_mw": 0,
   "confirmed_high_mw": 0,
   "counted_low_mw": 0,
   "counted_high_mw": 0,
   "evidence_as_of": "2026-04-19",
   "epoch_ai": {
    "it_mw": 0,
    "facility_mw": 0,
    "buildings_operating": 0,
    "sites": [
     {
      "name": "Meta Hyperion",
      "power_map": "https://siscto.si/power-map/meta-hyperion/",
      "it_mw": null,
      "facility_mw": null,
      "as_of": "2026-04-19",
      "status": "Under construction"
     }
    ]
   },
   "schedule_note": null,
   "announcements": [
    {
     "id": "techcrunch-2025-07-14-hyperion",
     "type": "announcement",
     "date": "2025-07-14",
     "undated_page": false,
     "who": "Mark Zuckerberg and Meta, reported by TechCrunch",
     "kind": "Company statement, quoted by the press",
     "title": "Mark Zuckerberg says Meta is building a 5GW AI data center",
     "publisher": "TechCrunch",
     "url": "https://techcrunch.com/2025/07/14/mark-zuckerberg-says-meta-is-building-a-5gw-ai-data-center",
     "summary": "TechCrunch reports Mark Zuckerberg's Threads post and a Meta spokesperson's dates for Hyperion.",
     "quotes": [
      "bring two gigawatts of data center capacity online by 2030",
      "would scale to five gigawatts in several years"
     ],
     "power_stated": "2 GW, scaling to 5 GW",
     "promised": "2 GW online by 2030",
     "confirmed_mw": null,
     "used_in_total": null
    },
    {
     "id": "meta-2025-09-29-hyperion",
     "type": "announcement",
     "date": "2025-09-29",
     "undated_page": false,
     "who": "Meta",
     "kind": "Company statement",
     "title": "Meta's Infrastructure Evolution and the Advent of AI",
     "publisher": "Engineering at Meta",
     "url": "https://engineering.fb.com/2025/09/29/data-infrastructure/metas-infrastructure-evolution-and-the-advent-of-ai/",
     "summary": "Meta's engineering blog describes Hyperion and when it starts to come online.",
     "quotes": [
      "will have the ability to scale up to a capacity of 5 gigawatts",
      "expected to come online beginning in 2028"
     ],
     "power_stated": "Ability to scale up to 5 GW",
     "promised": "Online beginning in 2028",
     "confirmed_mw": null,
     "used_in_total": null
    },
    {
     "id": "meta-richland",
     "type": "announcement",
     "date": "2026-11-11",
     "undated_page": true,
     "who": "Meta",
     "kind": "Company statement",
     "title": "The largest Meta data center yet brings big impact to Louisiana",
     "publisher": "Meta Data Centers",
     "url": "https://datacenters.atmeta.com/richland-parish-data-center/",
     "summary": "Meta's page for the Richland Parish data center, first announced in December 2024.",
     "quotes": [
      "The data center will deliver over two gigawatts of compute capacity to train future open-source large language models.",
      "delivering 5 gigawatts of compute capacity to house Hyperion, our largest multi-gigawatt AI cluster"
     ],
     "power_stated": "Over 2 GW of compute capacity; 5 GW for Hyperion",
     "promised": "",
     "confirmed_mw": null,
     "used_in_total": null
    }
   ],
   "evidence": []
  },
  {
   "slug": "stargate-shackelford-county",
   "name": "Stargate Shackelford County (Frontier)",
   "url": "https://siscto.si/ledger/stargate-shackelford-county/",
   "operators": [
    "OpenAI",
    "Oracle",
    "Vantage Data Centers"
   ],
   "filed_under": "OpenAI",
   "town": "Shackelford County",
   "region": "Texas",
   "country": "United States",
   "state": "Under construction",
   "state_evidence": "Epoch AI tracks the site as under construction, with no building operating as of September 4, 2026.",
   "announced_mw": 1400,
   "announced_basis": "IT load",
   "announced_text": "1.4 GW of critical IT capacity",
   "announced_source": "vantage-frontier",
   "upper_figure_mw": null,
   "upper_figure_text": null,
   "confirmed_low_mw": 0,
   "confirmed_high_mw": 0,
   "counted_low_mw": 0,
   "counted_high_mw": 0,
   "evidence_as_of": "2026-09-04",
   "epoch_ai": {
    "it_mw": 0,
    "facility_mw": 0,
    "buildings_operating": 0,
    "sites": [
     {
      "name": "OpenAI Stargate Shackelford",
      "power_map": "https://siscto.si/power-map/openai-stargate-shackelford/",
      "it_mw": null,
      "facility_mw": null,
      "as_of": "2026-09-04",
      "status": "Under construction"
     }
    ]
   },
   "schedule_note": null,
   "announcements": [
    {
     "id": "openai-2025-09-23-shackelford",
     "type": "announcement",
     "date": "2025-09-23",
     "undated_page": false,
     "who": "OpenAI, Oracle and SoftBank",
     "kind": "Company statement",
     "title": "OpenAI, Oracle, and SoftBank expand Stargate with five new AI data center sites",
     "publisher": "OpenAI",
     "url": "https://openai.com/index/five-new-stargate-sites/",
     "summary": "OpenAI names Shackelford County, Texas as one of three new sites built with Oracle. The power figure covers the three Oracle sites and an Abilene expansion together.",
     "quotes": [
      "can deliver over 5.5 gigawatts of capacity"
     ],
     "power_stated": "Over 5.5 GW for three Oracle sites and an Abilene expansion together",
     "promised": "",
     "confirmed_mw": null,
     "used_in_total": null
    },
    {
     "id": "vantage-frontier",
     "type": "announcement",
     "date": "2026-11-11",
     "undated_page": true,
     "who": "Vantage Data Centers",
     "kind": "Company statement",
     "title": "Shackelford County (Frontier)",
     "publisher": "Vantage Data Centers",
     "url": "https://vantage-dc.com/data-center-locations/north-america/shackelford-county-tx",
     "summary": "The developer's campus page states the capacity, the number of buildings and the date of the first one.",
     "quotes": [
      "deliver 1.4GW of critical IT capacity across 10 single-story data centers",
      "The first data center is scheduled for delivery in the second half of 2026."
     ],
     "power_stated": "1.4 GW of critical IT capacity across 10 data centers",
     "promised": "First data center delivered in the second half of 2026",
     "confirmed_mw": null,
     "used_in_total": null
    }
   ],
   "evidence": []
  },
  {
   "slug": "stargate-michigan",
   "name": "Stargate Michigan (Saline Township)",
   "url": "https://siscto.si/ledger/stargate-michigan/",
   "operators": [
    "OpenAI",
    "Oracle",
    "Related Digital"
   ],
   "filed_under": "OpenAI",
   "town": "Saline Township",
   "region": "Michigan",
   "country": "United States",
   "state": "Under construction",
   "state_evidence": "Epoch AI tracks the site as under construction, with no building operating as of March 12, 2026.",
   "announced_mw": 1383,
   "announced_basis": "total power",
   "announced_text": "1,383 MW data center",
   "announced_source": "mpsc-2025-12-18",
   "upper_figure_mw": null,
   "upper_figure_text": null,
   "confirmed_low_mw": 0,
   "confirmed_high_mw": 0,
   "counted_low_mw": 0,
   "counted_high_mw": 0,
   "evidence_as_of": "2026-03-12",
   "epoch_ai": {
    "it_mw": 0,
    "facility_mw": 0,
    "buildings_operating": 0,
    "sites": [
     {
      "name": "OpenAI Stargate Michigan",
      "power_map": "https://siscto.si/power-map/openai-stargate-michigan/",
      "it_mw": null,
      "facility_mw": null,
      "as_of": "2026-03-12",
      "status": "Under construction"
     }
    ]
   },
   "schedule_note": null,
   "announcements": [
    {
     "id": "mpsc-2025-12-18",
     "type": "announcement",
     "date": "2025-12-18",
     "undated_page": false,
     "who": "Michigan Public Service Commission",
     "kind": "Regulator",
     "title": "MPSC approves DTE Electric energy contracts for data center with conditions to strengthen protections for other customers",
     "publisher": "State of Michigan",
     "url": "https://www.michigan.gov/mpsc/commission/news-releases/2025/12/18/mpsc-approves-dte-electric-energy-contracts-for-data-center",
     "summary": "The state regulator approves DTE Electric's contracts for the data center and states its size. The customer is Green Chile Ventures LLC, a subsidiary of Oracle.",
     "quotes": [
      "the 1,383- megawatt (MW) data center in Saline Township",
      "develop 1,383 MW of energy storage facilities to match the data center's contracted demand"
     ],
     "power_stated": "1,383 MW data center (contracted demand)",
     "promised": "",
     "confirmed_mw": null,
     "used_in_total": null
    },
    {
     "id": "related-michigan",
     "type": "announcement",
     "date": "2026-11-11",
     "undated_page": true,
     "who": "Related Digital",
     "kind": "Company statement",
     "title": "Vertically integrated data center development",
     "publisher": "Related Digital",
     "url": "https://www.related-digital.com/michigan",
     "summary": "The developer's page for the Saline Township campus.",
     "quotes": [
      "will deliver over 1 GW of capacity"
     ],
     "power_stated": "Over 1 GW of capacity",
     "promised": "",
     "confirmed_mw": null,
     "used_in_total": null
    }
   ],
   "evidence": []
  },
  {
   "slug": "stargate-abilene",
   "name": "Stargate Abilene",
   "url": "https://siscto.si/ledger/stargate-abilene/",
   "operators": [
    "OpenAI",
    "Oracle",
    "Crusoe"
   ],
   "filed_under": "OpenAI",
   "town": "Abilene",
   "region": "Texas",
   "country": "United States",
   "state": "Energized",
   "state_evidence": "Public evidence puts 1.15 GW in operation as of November 1, 2026, against 1.2 GW announced: 96%. The announcement states total power, so it is set against the power of the whole facility.",
   "announced_mw": 1200,
   "announced_basis": "total power",
   "announced_text": "1.2 GW total power capacity",
   "announced_source": "crusoe-2025-03-18",
   "upper_figure_mw": null,
   "upper_figure_text": null,
   "confirmed_low_mw": 1154.0,
   "confirmed_high_mw": 1154.0,
   "counted_low_mw": 1154.0,
   "counted_high_mw": 1154.0,
   "evidence_as_of": "2026-11-01",
   "epoch_ai": {
    "it_mw": 824.0,
    "facility_mw": 1154.0,
    "buildings_operating": 8,
    "sites": [
     {
      "name": "OpenAI Stargate Abilene",
      "power_map": "https://siscto.si/power-map/openai-stargate-abilene/",
      "it_mw": 824.0,
      "facility_mw": 1154.0,
      "as_of": "2026-11-01",
      "status": "Operating"
     }
    ]
   },
   "schedule_note": "Crusoe first said the six buildings of the second phase were expected to be completed in mid-2026. Its March 27, 2026 release says the second phase is expected to reach completion by the end of 2026.",
   "announcements": [
    {
     "id": "openai-2025-01-21",
     "type": "announcement",
     "date": "2025-01-21",
     "undated_page": false,
     "who": "OpenAI",
     "kind": "Company statement",
     "title": "Announcing The Stargate Project",
     "publisher": "OpenAI",
     "url": "https://openai.com/index/announcing-the-stargate-project/",
     "summary": "OpenAI announces the Stargate Project with SoftBank, Oracle and MGX and says the buildout starts in Texas. No power figure is stated.",
     "quotes": [
      "intends to invest $500 billion over the next four years",
      "The buildout is currently underway, starting in Texas"
     ],
     "power_stated": "",
     "promised": "$500 billion invested over the next four years",
     "confirmed_mw": null,
     "used_in_total": null
    },
    {
     "id": "crusoe-2025-03-18",
     "type": "announcement",
     "date": "2025-03-18",
     "undated_page": false,
     "who": "Crusoe",
     "kind": "Company statement",
     "title": "Crusoe expands Abilene AI campus to 1.2 GW",
     "publisher": "Crusoe",
     "url": "https://www.crusoe.ai/resources/newsroom/crusoe-expands-ai-data-center-campus-in-abilene-to-1-2-gigawatts",
     "summary": "Crusoe says the Abilene campus grows to eight buildings and 1.2 GW of total power capacity.",
     "quotes": [
      "a total power capacity of 1.2 gigawatts (GW)",
      "The initial phase, comprising two buildings at 980,000 square feet and 200+ megawatts",
      "expected to be energized in the first half of 2025",
      "expected to be completed in mid-2026"
     ],
     "power_stated": "1.2 GW total power capacity (first phase: 200+ MW)",
     "promised": "First two buildings energized in the first half of 2025; six more buildings completed in mid-2026",
     "confirmed_mw": null,
     "used_in_total": null
    },
    {
     "id": "openai-2025-09-23-abilene",
     "type": "announcement",
     "date": "2025-09-23",
     "undated_page": false,
     "who": "OpenAI, Oracle and SoftBank",
     "kind": "Company statement",
     "title": "OpenAI, Oracle, and SoftBank expand Stargate with five new AI data center sites",
     "publisher": "OpenAI",
     "url": "https://openai.com/index/five-new-stargate-sites/",
     "summary": "OpenAI names five more Stargate sites and says a further 600 MW could be added near the Abilene flagship.",
     "quotes": [
      "brings Stargate to nearly 7 gigawatts of planned capacity",
      "an additional potential expansion of 600 megawatts near the flagship Stargate site"
     ],
     "power_stated": "Potential expansion of 600 MW near the flagship site",
     "promised": "",
     "confirmed_mw": null,
     "used_in_total": null
    },
    {
     "id": "crusoe-2026-03-27-abilene",
     "type": "announcement",
     "date": "2026-03-27",
     "undated_page": false,
     "who": "Crusoe",
     "kind": "Company statement",
     "title": "Crusoe builds 900 MW Abilene campus for Microsoft",
     "publisher": "Crusoe",
     "url": "https://www.crusoe.ai/resources/newsroom/crusoe-announces-new-900-mw-ai-factory-campus-in-abilene-texas-to-support-microsoft-ai-infrastructure",
     "summary": "In a release about a second Abilene campus, Crusoe restates the first campus at 1.2 GW and gives a new date for its second phase.",
     "quotes": [
      "to bring total campus capacity to 1.2 GW",
      "is expected to reach completion by the end of 2026"
     ],
     "power_stated": "1.2 GW total campus capacity",
     "promised": "Second phase complete by the end of 2026",
     "confirmed_mw": null,
     "used_in_total": null
    }
   ],
   "evidence": [
    {
     "id": "mortenson-abilene",
     "type": "evidence",
     "date": "2026-11-11",
     "undated_page": true,
     "who": "Mortenson",
     "kind": "Contractor statement",
     "title": "Abilene AI Data Center & Power Delivery",
     "publisher": "Mortenson",
     "url": "https://www.mortenson.com/projects/abilene-data-center-development",
     "summary": "The power contractor says the 1 GW, 345 kV substation for the second phase was fully energized by March 10, 2026.",
     "quotes": [
      "construction of a 12.5-acre, 1 GW, 345 kV greenfield substation",
      "fully energized by March 10, 2026"
     ],
     "power_stated": "",
     "promised": "",
     "confirmed_mw": null,
     "used_in_total": false
    }
   ]
  },
  {
   "slug": "stargate-milam-county",
   "name": "Stargate Milam County",
   "url": "https://siscto.si/ledger/stargate-milam-county/",
   "operators": [
    "OpenAI",
    "SoftBank",
    "SB Energy"
   ],
   "filed_under": "OpenAI",
   "town": "Milam County",
   "region": "Texas",
   "country": "United States",
   "state": "Under construction",
   "state_evidence": "Epoch AI tracks the site as under construction, with no building operating as of March 23, 2026.",
   "announced_mw": 1200,
   "announced_basis": "capacity, basis not stated",
   "announced_text": "1.2 GW data center site",
   "announced_source": "sbenergy-2026-03-19",
   "upper_figure_mw": null,
   "upper_figure_text": null,
   "confirmed_low_mw": 0,
   "confirmed_high_mw": 0,
   "counted_low_mw": 0,
   "counted_high_mw": 0,
   "evidence_as_of": "2026-03-23",
   "epoch_ai": {
    "it_mw": 0,
    "facility_mw": 0,
    "buildings_operating": 0,
    "sites": [
     {
      "name": "OpenAI Stargate Milam",
      "power_map": "https://siscto.si/power-map/openai-stargate-milam/",
      "it_mw": null,
      "facility_mw": null,
      "as_of": "2026-03-23",
      "status": "Under construction"
     }
    ]
   },
   "schedule_note": null,
   "announcements": [
    {
     "id": "openai-2025-09-23-milam",
     "type": "announcement",
     "date": "2025-09-23",
     "undated_page": false,
     "who": "OpenAI, Oracle and SoftBank",
     "kind": "Company statement",
     "title": "OpenAI, Oracle, and SoftBank expand Stargate with five new AI data center sites",
     "publisher": "OpenAI",
     "url": "https://openai.com/index/five-new-stargate-sites/",
     "summary": "OpenAI names Milam County, Texas as a site built with SB Energy, a SoftBank Group company.",
     "quotes": [
      "can scale to 1.5 gigawatts over the next 18 months"
     ],
     "power_stated": "1.5 GW for Lordstown and Milam County together, as a \"can scale to\" figure",
     "promised": "Over the next 18 months",
     "confirmed_mw": null,
     "used_in_total": null
    },
    {
     "id": "sbenergy-2026-03-19",
     "type": "announcement",
     "date": "2026-03-19",
     "undated_page": false,
     "who": "SB Energy",
     "kind": "Company statement",
     "title": "OpenAI and SoftBank Group Partner with SB Energy",
     "publisher": "SB Energy",
     "url": "https://sbenergy.com/openai-and-softbank-group-partner-with-sb-energy/",
     "summary": "SB Energy says OpenAI signed a 1.2 GW data center lease and chose SB Energy to build and operate the Milam County site.",
     "quotes": [
      "OpenAI signs 1.2 GW data center lease for initial data center buildout",
      "1.2 GW data center site in Milam County"
     ],
     "power_stated": "1.2 GW data center lease",
     "promised": "",
     "confirmed_mw": null,
     "used_in_total": null
    }
   ],
   "evidence": []
  },
  {
   "slug": "meta-prometheus",
   "name": "Meta Prometheus",
   "url": "https://siscto.si/ledger/meta-prometheus/",
   "operators": [
    "Meta"
   ],
   "filed_under": "Meta",
   "town": "New Albany",
   "region": "Ohio",
   "country": "United States",
   "state": "Partly energized",
   "state_evidence": "Public evidence puts 471 to 612 MW in operation as of August 31, 2026, against 1 GW announced: 47% to 61%. The low end is the IT load, the high end the whole facility, because the announcement does not say which it means.",
   "announced_mw": 1000,
   "announced_basis": "capacity, basis not stated",
   "announced_text": "1 gigawatt cluster",
   "announced_source": "meta-2025-09-29-prometheus",
   "upper_figure_mw": null,
   "upper_figure_text": null,
   "confirmed_low_mw": 471.0,
   "confirmed_high_mw": 612.0,
   "counted_low_mw": 471.0,
   "counted_high_mw": 612.0,
   "evidence_as_of": "2026-08-31",
   "epoch_ai": {
    "it_mw": 471.0,
    "facility_mw": 612.0,
    "buildings_operating": 10,
    "sites": [
     {
      "name": "Meta Prometheus",
      "power_map": "https://siscto.si/power-map/meta-prometheus/",
      "it_mw": 471.0,
      "facility_mw": 612.0,
      "as_of": "2026-08-31",
      "status": "Operating, expanding"
     }
    ]
   },
   "schedule_note": null,
   "announcements": [
    {
     "id": "techcrunch-2025-07-14-prometheus",
     "type": "announcement",
     "date": "2025-07-14",
     "undated_page": false,
     "who": "Mark Zuckerberg, reported by TechCrunch",
     "kind": "Company statement, quoted by the press",
     "title": "Mark Zuckerberg says Meta is building a 5GW AI data center",
     "publisher": "TechCrunch",
     "url": "https://techcrunch.com/2025/07/14/mark-zuckerberg-says-meta-is-building-a-5gw-ai-data-center",
     "summary": "TechCrunch reports Mark Zuckerberg's Threads post. A Meta spokesperson places Prometheus in New Albany, Ohio.",
     "quotes": [
      "bring a 1 GW super cluster, called Prometheus, online in 2026"
     ],
     "power_stated": "1 GW",
     "promised": "Online in 2026",
     "confirmed_mw": null,
     "used_in_total": null
    },
    {
     "id": "meta-2025-09-29-prometheus",
     "type": "announcement",
     "date": "2025-09-29",
     "undated_page": false,
     "who": "Meta",
     "kind": "Company statement",
     "title": "Meta's Infrastructure Evolution and the Advent of AI",
     "publisher": "Engineering at Meta",
     "url": "https://engineering.fb.com/2025/09/29/data-infrastructure/metas-infrastructure-evolution-and-the-advent-of-ai/",
     "summary": "Meta's engineering blog describes Prometheus as a cluster spread over several buildings, tents and colocation halls in one region.",
     "quotes": [
      "will be a 1-gigawatt cluster spanning across multiple data center buildings"
     ],
     "power_stated": "1 GW cluster",
     "promised": "",
     "confirmed_mw": null,
     "used_in_total": null
    }
   ],
   "evidence": []
  },
  {
   "slug": "stargate-uae",
   "name": "Stargate UAE",
   "url": "https://siscto.si/ledger/stargate-uae/",
   "operators": [
    "OpenAI",
    "G42",
    "Oracle"
   ],
   "filed_under": "OpenAI",
   "town": "Abu Dhabi",
   "region": "Abu Dhabi",
   "country": "United Arab Emirates",
   "state": "Under construction",
   "state_evidence": "Epoch AI tracks the site as under construction, with no building operating as of November 16, 2025.",
   "announced_mw": 1000,
   "announced_basis": "capacity, basis not stated",
   "announced_text": "1 GW cluster",
   "announced_source": "openai-stargate-uae",
   "upper_figure_mw": null,
   "upper_figure_text": null,
   "confirmed_low_mw": 0,
   "confirmed_high_mw": 0,
   "counted_low_mw": 0,
   "counted_high_mw": 0,
   "evidence_as_of": "2025-11-16",
   "epoch_ai": {
    "it_mw": 0,
    "facility_mw": 0,
    "buildings_operating": 0,
    "sites": [
     {
      "name": "OpenAI Stargate UAE",
      "power_map": "https://siscto.si/power-map/openai-stargate-uae/",
      "it_mw": null,
      "facility_mw": null,
      "as_of": "2025-11-16",
      "status": "Under construction"
     }
    ]
   },
   "schedule_note": null,
   "announcements": [
    {
     "id": "techcrunch-2025-05-22",
     "type": "announcement",
     "date": "2025-05-22",
     "undated_page": false,
     "who": "OpenAI, reported by TechCrunch",
     "kind": "Company statement, quoted by the press",
     "title": "OpenAI teams up with Cisco, Oracle to build UAE data center",
     "publisher": "TechCrunch",
     "url": "https://techcrunch.com/2025/05/22/openai-teams-up-with-cisco-oracle-to-build-uae-data-center",
     "summary": "TechCrunch reports the announcement on the day it was made, with G42, Oracle, Nvidia, Cisco and SoftBank as partners.",
     "quotes": [
      "which will bring a 1GW data center cluster to Abu Dhabi",
      "OpenAI expects 200MW will go live in 2026."
     ],
     "power_stated": "1 GW cluster; 200 MW first",
     "promised": "200 MW live in 2026",
     "confirmed_mw": null,
     "used_in_total": null
    },
    {
     "id": "khaleej-2025-10-16",
     "type": "announcement",
     "date": "2025-10-16",
     "undated_page": false,
     "who": "Khazna Data Centers, reported by Khaleej Times",
     "kind": "Company statement, quoted by the press",
     "title": "Watch: 3,500 people work on Stargate UAE as phase 1 set to be done in 2 years",
     "publisher": "Khaleej Times",
     "url": "https://www.khaleejtimes.com/uae/stargate-uae-phase-1-in-two-years",
     "summary": "Khazna executives describe construction on site and repeat the first delivery date.",
     "quotes": [
      "Stargate UAE is a 1-gigawatt compute cluster",
      "200MW of the 1GW project is scheduled to be delivered in 2026",
      "There's about 3,500 workforce on site already."
     ],
     "power_stated": "1 GW cluster; 200 MW first",
     "promised": "200 MW delivered in 2026",
     "confirmed_mw": null,
     "used_in_total": null
    },
    {
     "id": "openai-stargate-uae",
     "type": "announcement",
     "date": "2026-11-11",
     "undated_page": true,
     "who": "OpenAI",
     "kind": "Company statement",
     "title": "Introducing Stargate UAE",
     "publisher": "OpenAI",
     "url": "https://openai.com/index/introducing-stargate-uae",
     "summary": "OpenAI's own page for the project.",
     "quotes": [
      "A 1GW Stargate UAE cluster in Abu Dhabi",
      "200MW expected to go live in 2026"
     ],
     "power_stated": "1 GW cluster; 200 MW first",
     "promised": "200 MW live in 2026",
     "confirmed_mw": null,
     "used_in_total": null
    }
   ],
   "evidence": []
  },
  {
   "slug": "stargate-port-washington",
   "name": "Stargate Wisconsin (Port Washington, Lighthouse)",
   "url": "https://siscto.si/ledger/stargate-port-washington/",
   "operators": [
    "OpenAI",
    "Oracle",
    "Vantage Data Centers"
   ],
   "filed_under": "OpenAI",
   "town": "Port Washington",
   "region": "Wisconsin",
   "country": "United States",
   "state": "Under construction",
   "state_evidence": "Epoch AI tracks the site as under construction, with no building operating as of July 24, 2026.",
   "announced_mw": 902,
   "announced_basis": "IT load",
   "announced_text": "902 MW across four data centers",
   "announced_source": "vantage-lighthouse",
   "upper_figure_mw": null,
   "upper_figure_text": null,
   "confirmed_low_mw": 0,
   "confirmed_high_mw": 0,
   "counted_low_mw": 0,
   "counted_high_mw": 0,
   "evidence_as_of": "2026-07-24",
   "epoch_ai": {
    "it_mw": 0,
    "facility_mw": 0,
    "buildings_operating": 0,
    "sites": [
     {
      "name": "OpenAI Stargate Wisconsin",
      "power_map": "https://siscto.si/power-map/openai-stargate-wisconsin/",
      "it_mw": null,
      "facility_mw": null,
      "as_of": "2026-07-24",
      "status": "Under construction"
     }
    ]
   },
   "schedule_note": null,
   "announcements": [
    {
     "id": "openai-2025-09-23-midwest",
     "type": "announcement",
     "date": "2025-09-23",
     "undated_page": false,
     "who": "OpenAI, Oracle and SoftBank",
     "kind": "Company statement",
     "title": "OpenAI, Oracle, and SoftBank expand Stargate with five new AI data center sites",
     "publisher": "OpenAI",
     "url": "https://openai.com/index/five-new-stargate-sites/",
     "summary": "OpenAI announces a Midwest site with Oracle. An update on the same page dated October 22, 2025 places it in Wisconsin, developed with Vantage.",
     "quotes": [
      "can deliver over 5.5 gigawatts of capacity",
      "which we expect to announce soon"
     ],
     "power_stated": "Over 5.5 GW for three Oracle sites and an Abilene expansion together",
     "promised": "",
     "confirmed_mw": null,
     "used_in_total": null
    },
    {
     "id": "vantage-lighthouse",
     "type": "announcement",
     "date": "2026-11-11",
     "undated_page": true,
     "who": "Vantage Data Centers",
     "kind": "Company statement",
     "title": "Port Washington (Lighthouse) Data Center Campus",
     "publisher": "Vantage Data Centers",
     "url": "https://vantage-dc.com/data-center-locations/north-america/port-washington-wisconsin",
     "summary": "The developer's campus page states the capacity of the four data centers, labeled as critical IT load, and the completion year.",
     "quotes": [
      "totaling 902MW across 2.5 million square feet.",
      "is scheduled to be completed in 2028."
     ],
     "power_stated": "902 MW of critical IT load across four data centers",
     "promised": "Completed in 2028",
     "confirmed_mw": null,
     "used_in_total": null
    }
   ],
   "evidence": []
  },
  {
   "slug": "abilene-microsoft-campus",
   "name": "Abilene campus for Microsoft",
   "url": "https://siscto.si/ledger/abilene-microsoft-campus/",
   "operators": [
    "Microsoft",
    "Crusoe"
   ],
   "filed_under": "Microsoft",
   "town": "Abilene",
   "region": "Texas",
   "country": "United States",
   "state": "Under construction",
   "state_evidence": "Epoch AI tracks the site as under construction, with no building operating as of January 15, 2026.",
   "announced_mw": 900,
   "announced_basis": "total power",
   "announced_text": "900 MW site",
   "announced_source": "crusoe-2026-03-27",
   "upper_figure_mw": null,
   "upper_figure_text": null,
   "confirmed_low_mw": 0,
   "confirmed_high_mw": 0,
   "counted_low_mw": 0,
   "counted_high_mw": 0,
   "evidence_as_of": "2026-01-15",
   "epoch_ai": {
    "it_mw": 0,
    "facility_mw": 0,
    "buildings_operating": 0,
    "sites": [
     {
      "name": "Crusoe Abilene Expansion",
      "power_map": "https://siscto.si/power-map/crusoe-abilene-expansion/",
      "it_mw": null,
      "facility_mw": null,
      "as_of": "2026-01-15",
      "status": "Under construction"
     }
    ]
   },
   "schedule_note": null,
   "announcements": [
    {
     "id": "crusoe-2026-03-27",
     "type": "announcement",
     "date": "2026-03-27",
     "undated_page": false,
     "who": "Crusoe",
     "kind": "Company statement",
     "title": "Crusoe builds 900 MW Abilene campus for Microsoft",
     "publisher": "Crusoe",
     "url": "https://www.crusoe.ai/resources/newsroom/crusoe-announces-new-900-mw-ai-factory-campus-in-abilene-texas-to-support-microsoft-ai-infrastructure",
     "summary": "Crusoe announces a new 900 MW campus in Abilene for Microsoft: two buildings and an on-site power plant.",
     "quotes": [
      "the 900 MW site includes two new buildings and an onsite power plant to support grid resilience",
      "Each of the two new buildings is designed to deliver 336 MW of critical IT load",
      "the first building expected to be energized in mid-2027",
      "bringing the total projected capacity across the full Abilene site to 2.1 gigawatts (GW)"
     ],
     "power_stated": "900 MW site; 336 MW of critical IT load in each of two buildings",
     "promised": "First building energized in mid-2027",
     "confirmed_mw": null,
     "used_in_total": null
    }
   ],
   "evidence": []
  },
  {
   "slug": "lake-mariner",
   "name": "Lake Mariner",
   "url": "https://siscto.si/ledger/lake-mariner/",
   "operators": [
    "Fluidstack",
    "TeraWulf",
    "Core42",
    "Anthropic"
   ],
   "filed_under": "Fluidstack",
   "town": "Barker",
   "region": "New York",
   "country": "United States",
   "state": "Partly energized",
   "state_evidence": "Public evidence puts 268 MW in operation as of October 31, 2026, against 440 MW announced: 61%. The announcement states IT load, so it is set against the IT load running.",
   "announced_mw": 440,
   "announced_basis": "IT load",
   "announced_text": "440 critical IT MW under lease (380 MW and 60 MW)",
   "announced_source": "terawulf-2026-02-26",
   "upper_figure_mw": null,
   "upper_figure_text": null,
   "confirmed_low_mw": 268.0,
   "confirmed_high_mw": 268.0,
   "counted_low_mw": 268.0,
   "counted_high_mw": 268.0,
   "evidence_as_of": "2026-10-31",
   "epoch_ai": {
    "it_mw": 268.0,
    "facility_mw": 303.0,
    "buildings_operating": 4,
    "sites": [
     {
      "name": "Anthropic Lake Mariner",
      "power_map": "https://siscto.si/power-map/anthropic-lake-mariner/",
      "it_mw": 210.0,
      "facility_mw": 245.0,
      "as_of": "2026-10-31",
      "status": "Operating, expanding"
     },
     {
      "name": "Core42 Lake Mariner",
      "power_map": "https://siscto.si/power-map/core42-lake-mariner/",
      "it_mw": 58.0,
      "facility_mw": 58.0,
      "as_of": "2026-07-23",
      "status": "Operating"
     }
    ]
   },
   "schedule_note": null,
   "announcements": [
    {
     "id": "anthropic-2025-11-12-ny",
     "type": "announcement",
     "date": "2025-11-12",
     "undated_page": false,
     "who": "Anthropic",
     "kind": "Company statement",
     "title": "Anthropic invests $50 billion in American AI infrastructure",
     "publisher": "Anthropic",
     "url": "https://www.anthropic.com/news/anthropic-invests-50-billion-in-american-ai-infrastructure",
     "summary": "Anthropic announces data centers with Fluidstack in Texas and New York. It names no site and states no power figure.",
     "quotes": [
      "a $50 billion investment in American computing infrastructure",
      "with sites coming online throughout 2026"
     ],
     "power_stated": "",
     "promised": "Sites online throughout 2026",
     "confirmed_mw": null,
     "used_in_total": null
    },
    {
     "id": "terawulf-2026-02-26",
     "type": "announcement",
     "date": "2026-02-26",
     "undated_page": false,
     "who": "TeraWulf",
     "kind": "Company statement",
     "title": "TeraWulf Reports Fourth Quarter and Full Year 2025 Results",
     "publisher": "TeraWulf",
     "url": "https://investors.terawulf.com/news-events/press-releases/detail/132/terawulf-reports-fourth-quarter-and-full-year-2025-results",
     "summary": "TeraWulf lists its leases at the Lake Mariner campus (380 critical IT MW with Fluidstack, 60 with Core42) and the date each building is expected to be energized.",
     "quotes": [
      "39 critical IT MW HPC capacity online",
      "more than 500 MW of near-term contracted campus capacity",
      "Energization expected Q3 2026",
      "Energization expected Q4 2026"
     ],
     "power_stated": "440 critical IT MW under lease (380 MW Fluidstack, 60 MW Core42)",
     "promised": "Buildings energized from March 2026 to the fourth quarter of 2026",
     "confirmed_mw": null,
     "used_in_total": null
    }
   ],
   "evidence": []
  },
  {
   "slug": "polaris-forge-1",
   "name": "Polaris Forge 1",
   "url": "https://siscto.si/ledger/polaris-forge-1/",
   "operators": [
    "CoreWeave",
    "Applied Digital"
   ],
   "filed_under": "CoreWeave",
   "town": "Ellendale",
   "region": "North Dakota",
   "country": "United States",
   "state": "Partly energized",
   "state_evidence": "Public evidence puts 68 to 175 MW in operation as of June 30, 2026, against 400 MW announced: 17% to 44%. The range covers every figure listed below.",
   "announced_mw": 400,
   "announced_basis": "IT load",
   "announced_text": "400 MW of critical IT load under lease",
   "announced_source": "applied-2026-07-01-a",
   "upper_figure_mw": 1000,
   "upper_figure_text": "designed to scale up to 1 gigawatt over time",
   "confirmed_low_mw": 68.0,
   "confirmed_high_mw": 175,
   "counted_low_mw": 68.0,
   "counted_high_mw": 175,
   "evidence_as_of": "2026-06-30",
   "epoch_ai": {
    "it_mw": 68.0,
    "facility_mw": 88.0,
    "buildings_operating": 1,
    "sites": [
     {
      "name": "CoreWeave Ellendale ND",
      "power_map": "https://siscto.si/power-map/coreweave-ellendale-nd/",
      "it_mw": 68.0,
      "facility_mw": 88.0,
      "as_of": "2026-06-30",
      "status": "Operating, expanding"
     }
    ]
   },
   "schedule_note": null,
   "announcements": [
    {
     "id": "applied-2025-06-02",
     "type": "announcement",
     "date": "2025-06-02",
     "undated_page": false,
     "who": "Applied Digital",
     "kind": "Company statement",
     "title": "Applied Digital Announces 250MW AI Data Center Lease With CoreWeave in North Dakota",
     "publisher": "Applied Digital",
     "url": "https://ir.applieddigital.com/news-events/press-releases/detail/123/applied-digital-announces-250mw-ai-data-center-lease-with",
     "summary": "Applied Digital leases 250 MW of critical IT load to CoreWeave at its Ellendale campus, with an option on 150 MW more.",
     "quotes": [
      "deliver 250 megawatts (MW) of critical IT load",
      "designed to host 400 MW of critical IT load",
      "designed to scale up to 1 gigawatt over time",
      "to be ready for service in the fourth quarter of calendar 2025",
      "is expected to be ready for service in the middle of 2026"
     ],
     "power_stated": "250 MW of critical IT load, option on 150 MW more; campus designed for 400 MW",
     "promised": "First 100 MW building in the fourth quarter of 2025; second building in the middle of 2026; third in 2027",
     "confirmed_mw": null,
     "used_in_total": null
    },
    {
     "id": "applied-2026-07-01-a",
     "type": "announcement",
     "date": "2026-07-01",
     "undated_page": false,
     "who": "Applied Digital",
     "kind": "Company statement",
     "title": "Applied Digital Delivers Second Building at Polaris Forge 1",
     "publisher": "Applied Digital",
     "url": "https://ir.applieddigital.com/news-events/press-releases/detail/157/applied-digital-delivers-second-building-at-polaris-forge-1",
     "summary": "Applied Digital restates the full lease commitment at the campus.",
     "quotes": [
      "contracted to deliver 400 MW of critical IT load"
     ],
     "power_stated": "400 MW of critical IT load under lease",
     "promised": "",
     "confirmed_mw": null,
     "used_in_total": null
    }
   ],
   "evidence": [
    {
     "id": "applied-2026-07-01-e",
     "type": "evidence",
     "date": "2026-07-01",
     "undated_page": false,
     "who": "Applied Digital",
     "kind": "Company statement",
     "title": "Applied Digital Delivers Second Building at Polaris Forge 1",
     "publisher": "Applied Digital",
     "url": "https://ir.applieddigital.com/news-events/press-releases/detail/157/applied-digital-delivers-second-building-at-polaris-forge-1",
     "summary": "The landlord says the first phase of the second building is ready for service and states the live capacity at the campus.",
     "quotes": [
      "delivering 75 MW of operational AI capacity",
      "bringing total live capacity at the campus to 175 MW"
     ],
     "power_stated": "",
     "promised": "",
     "confirmed_mw": 175,
     "used_in_total": true
    }
   ]
  },
  {
   "slug": "denton",
   "name": "Denton",
   "url": "https://siscto.si/ledger/denton/",
   "operators": [
    "CoreWeave",
    "Core Scientific"
   ],
   "filed_under": "CoreWeave",
   "town": "Denton",
   "region": "Texas",
   "country": "United States",
   "state": "Energized",
   "state_evidence": "Public evidence puts 262 MW in operation as of September 1, 2026, against 260 MW announced: 100%. The announcement states IT load, so it is set against the IT load running.",
   "announced_mw": 260,
   "announced_basis": "IT load",
   "announced_text": "approximately 260 MW of critical IT load",
   "announced_source": "corescientific-2025-02-26",
   "upper_figure_mw": null,
   "upper_figure_text": null,
   "confirmed_low_mw": 262.0,
   "confirmed_high_mw": 262.0,
   "counted_low_mw": 260,
   "counted_high_mw": 260,
   "evidence_as_of": "2026-09-01",
   "epoch_ai": {
    "it_mw": 262.0,
    "facility_mw": 367.0,
    "buildings_operating": 7,
    "sites": [
     {
      "name": "CoreWeave Denton TX",
      "power_map": "https://siscto.si/power-map/coreweave-denton-tx/",
      "it_mw": 262.0,
      "facility_mw": 367.0,
      "as_of": "2026-09-01",
      "status": "Operating, expanding"
     }
    ]
   },
   "schedule_note": null,
   "announcements": [
    {
     "id": "corescientific-2025-02-26",
     "type": "announcement",
     "date": "2025-02-26",
     "undated_page": false,
     "who": "Core Scientific",
     "kind": "Company statement",
     "title": "Core Scientific and CoreWeave Announce $1.2 Billion Expansion at Denton, TX Site",
     "publisher": "Core Scientific",
     "url": "https://investors.corescientific.com/news-events/press-releases/detail/110/core-scientific-and-coreweave-announce-1-2-billion-expansion-at-denton-tx-site",
     "summary": "Core Scientific adds 70 MW for CoreWeave at its Denton site.",
     "quotes": [
      "increases the full critical IT load to approximately 260 MW",
      "The 70 MW of additional contracted power at the Denton site"
     ],
     "power_stated": "Approximately 260 MW of critical IT load",
     "promised": "",
     "confirmed_mw": null,
     "used_in_total": null
    }
   ],
   "evidence": []
  },
  {
   "slug": "stargate-norway-narvik",
   "name": "Stargate Norway (Narvik)",
   "url": "https://siscto.si/ledger/stargate-norway-narvik/",
   "operators": [
    "Nscale",
    "Aker",
    "OpenAI",
    "Microsoft"
   ],
   "filed_under": "Nscale",
   "town": "Narvik",
   "region": "Nordland",
   "country": "Norway",
   "state": "Under construction",
   "state_evidence": "Epoch AI tracks the site as under construction, with no building operating as of July 5, 2026.",
   "announced_mw": 230,
   "announced_basis": "capacity, basis not stated",
   "announced_text": "230 MW campus",
   "announced_source": "nscale-2026-04-14",
   "upper_figure_mw": 520,
   "upper_figure_text": "230 MW with ambitions for 290 MW more",
   "confirmed_low_mw": 0,
   "confirmed_high_mw": 0,
   "counted_low_mw": 0,
   "counted_high_mw": 0,
   "evidence_as_of": "2026-07-05",
   "epoch_ai": {
    "it_mw": 0,
    "facility_mw": 0,
    "buildings_operating": 0,
    "sites": [
     {
      "name": "Microsoft Narvik Norway",
      "power_map": "https://siscto.si/power-map/microsoft-narvik-norway/",
      "it_mw": null,
      "facility_mw": null,
      "as_of": "2026-07-05",
      "status": "Under construction"
     }
    ]
   },
   "schedule_note": null,
   "announcements": [
    {
     "id": "nscale-2025-08-14",
     "type": "announcement",
     "date": "2025-08-14",
     "undated_page": false,
     "who": "Nscale",
     "kind": "Company statement",
     "title": "Stargate Norway: Laying the foundation for the future of AI",
     "publisher": "Nscale",
     "url": "https://www.nscale.com/blog/stargate-norway-laying-the-foundation-for-the-future-of-ai",
     "summary": "Nscale describes Stargate Norway, a joint venture with Aker, with OpenAI as a partner.",
     "quotes": [
      "230MW of initial capacity powered by renewable hydropower",
      "ambitions to scale by an additional 290MW",
      "will target to deliver 100,000 NVIDIA GPUs"
     ],
     "power_stated": "230 MW initial capacity; ambition for 290 MW more",
     "promised": "",
     "confirmed_mw": null,
     "used_in_total": null
    },
    {
     "id": "nscale-2026-04-14",
     "type": "announcement",
     "date": "2026-04-14",
     "undated_page": false,
     "who": "Nscale",
     "kind": "Company statement",
     "title": "Nscale announces expanded deal with Microsoft in Norway",
     "publisher": "Nscale",
     "url": "https://www.nscale.com/press-releases/nscale-microsoft-norway",
     "summary": "Nscale expands its Microsoft deal at the Narvik campus and says it will manage the campus alone.",
     "quotes": [
      "230 MW Nscale Narvik campus",
      "will add more than 30,000 NVIDIA Rubin GPUs in deployment",
      "deliver even more high-performance AI compute capacity in Norway in 2027"
     ],
     "power_stated": "230 MW campus",
     "promised": "More capacity in 2027",
     "confirmed_mw": null,
     "used_in_total": null
    }
   ],
   "evidence": []
  },
  {
   "slug": "barber-lake",
   "name": "Barber Lake",
   "url": "https://siscto.si/ledger/barber-lake/",
   "operators": [
    "Fluidstack",
    "Cipher Mining",
    "Anthropic"
   ],
   "filed_under": "Fluidstack",
   "town": "Colorado City",
   "region": "Texas",
   "country": "United States",
   "state": "Delayed",
   "state_evidence": "Cipher said it expected to deliver 168 MW of critical IT load by September 2026. Epoch AI's entry of July 30, 2026 reads \"still under construction and not yet energized\", and Epoch AI estimates the first phase for about December 2026, \"about 3 months later than the disclosed target\".",
   "announced_mw": 207,
   "announced_basis": "IT load",
   "announced_text": "207 MW of critical IT load (168 MW and 39 MW)",
   "announced_source": "cipher-2025-11-20",
   "upper_figure_mw": null,
   "upper_figure_text": null,
   "confirmed_low_mw": 0,
   "confirmed_high_mw": 0,
   "counted_low_mw": 0,
   "counted_high_mw": 0,
   "evidence_as_of": "2026-07-30",
   "epoch_ai": {
    "it_mw": 0,
    "facility_mw": 0,
    "buildings_operating": 0,
    "sites": [
     {
      "name": "Anthropic Barber Lake",
      "power_map": "https://siscto.si/power-map/anthropic-barber-lake/",
      "it_mw": null,
      "facility_mw": null,
      "as_of": "2026-07-30",
      "status": "Under construction"
     }
    ]
   },
   "schedule_note": "Cipher said it expected to deliver 168 MW of critical IT load by September 2026. Epoch AI's entry of July 30, 2026 reads \"still under construction and not yet energized\", and Epoch AI estimates the first phase for about December 2026, \"about 3 months later than the disclosed target\".",
   "announcements": [
    {
     "id": "cipher-2025-09-25",
     "type": "announcement",
     "date": "2025-09-25",
     "undated_page": false,
     "who": "Cipher Mining",
     "kind": "Company statement",
     "title": "Cipher Mining Signs 168 MW, 10-Year AI Hosting Agreement with Fluidstack",
     "publisher": "GlobeNewswire",
     "url": "https://www.globenewswire.com/news-release/2025/09/25/3156107/0/en/Cipher-Mining-Signs-168-MW-10-Year-AI-Hosting-Agreement-with-Fluidstack.html",
     "summary": "Cipher signs a 10-year hosting agreement with Fluidstack, backed by Google, at its Barber Lake site.",
     "quotes": [
      "Cipher will deliver 168 MW of critical IT load, supported by a maximum of 244 MW of gross capacity",
      "Expected Delivery of 168 MW of Critical IT Load by September of 2026"
     ],
     "power_stated": "168 MW of critical IT load (244 MW gross)",
     "promised": "Delivered by September 2026",
     "confirmed_mw": null,
     "used_in_total": null
    },
    {
     "id": "anthropic-2025-11-12-texas",
     "type": "announcement",
     "date": "2025-11-12",
     "undated_page": false,
     "who": "Anthropic",
     "kind": "Company statement",
     "title": "Anthropic invests $50 billion in American AI infrastructure",
     "publisher": "Anthropic",
     "url": "https://www.anthropic.com/news/anthropic-invests-50-billion-in-american-ai-infrastructure",
     "summary": "Anthropic announces data centers with Fluidstack in Texas and New York. It names no site and states no power figure.",
     "quotes": [
      "a $50 billion investment in American computing infrastructure",
      "with sites coming online throughout 2026"
     ],
     "power_stated": "",
     "promised": "Sites online throughout 2026",
     "confirmed_mw": null,
     "used_in_total": null
    },
    {
     "id": "cipher-2025-11-20",
     "type": "announcement",
     "date": "2025-11-20",
     "undated_page": false,
     "who": "Cipher Mining",
     "kind": "Company statement",
     "title": "Cipher Mining Signs Additional 56 MW, 10-Year AI Hosting Agreement with Fluidstack",
     "publisher": "GlobeNewswire",
     "url": "https://www.globenewswire.com/news-release/2025/11/20/3191801/0/en/Cipher-Mining-Signs-Additional-56-MW-10-Year-AI-Hosting-Agreement-with-Fluidstack.html",
     "summary": "Fluidstack takes the rest of the site.",
     "quotes": [
      "an additional 39 MW of critical IT load",
      "lease the entire 300 MW of capacity at Cipher's Barber Lake site",
      "Expected Delivery of Additional 39 MW of Critical IT Load at Barber Lake by January 2027"
     ],
     "power_stated": "39 MW more critical IT load; the whole 300 MW site",
     "promised": "Delivered by January 2027",
     "confirmed_mw": null,
     "used_in_total": null
    }
   ],
   "evidence": []
  },
  {
   "slug": "lancaster",
   "name": "Lancaster",
   "url": "https://siscto.si/ledger/lancaster/",
   "operators": [
    "CoreWeave",
    "Chirisa Technology Parks",
    "Machine Investment Group"
   ],
   "filed_under": "CoreWeave",
   "town": "Lancaster",
   "region": "Pennsylvania",
   "country": "United States",
   "state": "Under construction",
   "state_evidence": "Epoch AI tracks the site as under construction, with no building operating as of July 13, 2026.",
   "announced_mw": 100,
   "announced_basis": "capacity, basis not stated",
   "announced_text": "initial 100 MW data center",
   "announced_source": "coreweave-2025-07-15",
   "upper_figure_mw": 300,
   "upper_figure_text": "potential to expand to 300 MW",
   "confirmed_low_mw": 0,
   "confirmed_high_mw": 0,
   "counted_low_mw": 0,
   "counted_high_mw": 0,
   "evidence_as_of": "2026-07-13",
   "epoch_ai": {
    "it_mw": 0,
    "facility_mw": 0,
    "buildings_operating": 0,
    "sites": [
     {
      "name": "CoreWeave Lancaster Greenfield site",
      "power_map": "https://siscto.si/power-map/coreweave-lancaster-greenfield-site/",
      "it_mw": null,
      "facility_mw": null,
      "as_of": "2026-07-13",
      "status": "Under construction"
     }
    ]
   },
   "schedule_note": null,
   "announcements": [
    {
     "id": "coreweave-2025-07-15",
     "type": "announcement",
     "date": "2025-07-15",
     "undated_page": false,
     "who": "CoreWeave",
     "kind": "Company statement",
     "title": "CoreWeave Announces Multi-Billion Dollar Commitment to AI Infrastructure in Pennsylvania",
     "publisher": "CoreWeave",
     "url": "https://investors.coreweave.com/news/news-details/2025/CoreWeave-Announces-Multi-Billion-Dollar-Commitment-to-AI-Infrastructure-in-Pennsylvania/default.aspx",
     "summary": "CoreWeave says it intends to commit up to $6 billion to a new data center in Lancaster.",
     "quotes": [
      "The initial 100 megawatt (MW) data center",
      "with potential to expand to 300 MW"
     ],
     "power_stated": "Initial 100 MW; potential to expand to 300 MW",
     "promised": "",
     "confirmed_mw": null,
     "used_in_total": null
    }
   ],
   "evidence": []
  },
  {
   "slug": "muskogee",
   "name": "Muskogee",
   "url": "https://siscto.si/ledger/muskogee/",
   "operators": [
    "CoreWeave",
    "Core Scientific"
   ],
   "filed_under": "CoreWeave",
   "town": "Muskogee",
   "region": "Oklahoma",
   "country": "United States",
   "state": "Under construction",
   "state_evidence": "Epoch AI tracks the site as under construction, with no building operating as of June 13, 2026.",
   "announced_mw": 100,
   "announced_basis": "total power",
   "announced_text": "100 MW facility (about 70 MW of critical IT load)",
   "announced_source": "corescientific-2024-11-18",
   "upper_figure_mw": null,
   "upper_figure_text": null,
   "confirmed_low_mw": 0,
   "confirmed_high_mw": 0,
   "counted_low_mw": 0,
   "counted_high_mw": 0,
   "evidence_as_of": "2026-06-13",
   "epoch_ai": {
    "it_mw": 0,
    "facility_mw": 0,
    "buildings_operating": 0,
    "sites": [
     {
      "name": "CoreWeave Muskogee OK",
      "power_map": "https://siscto.si/power-map/coreweave-muskogee-ok/",
      "it_mw": null,
      "facility_mw": null,
      "as_of": "2026-06-13",
      "status": "Under construction"
     }
    ]
   },
   "schedule_note": null,
   "announcements": [
    {
     "id": "corescientific-2024-11-18",
     "type": "announcement",
     "date": "2024-11-18",
     "undated_page": false,
     "who": "Core Scientific",
     "kind": "Company statement",
     "title": "Core Scientific and Port Muskogee Break Ground on 100 MW HPC Data Center",
     "publisher": "Core Scientific",
     "url": "https://investors.corescientific.com/news-events/press-releases/detail/99/core-scientific-and-port-muskogee-break-ground-on-100-mw-hpc-data-center",
     "summary": "Core Scientific breaks ground on a facility that will host CoreWeave.",
     "quotes": [
      "The 100-megawatt facility will host CoreWeave's NVIDIA GPUs for an undisclosed client.",
      "will provide approximately 70 MW of critical IT load",
      "The site is expected to be operational in 2026."
     ],
     "power_stated": "100 MW facility; about 70 MW of critical IT load",
     "promised": "Operational in 2026",
     "confirmed_mw": null,
     "used_in_total": null
    }
   ],
   "evidence": []
  },
  {
   "slug": "nebius-mantsala",
   "name": "Nebius Mäntsälä",
   "url": "https://siscto.si/ledger/nebius-mantsala/",
   "operators": [
    "Nebius"
   ],
   "filed_under": "Nebius",
   "town": "Mäntsälä",
   "region": "Uusimaa",
   "country": "Finland",
   "state": "Energized",
   "state_evidence": "Public evidence puts 75 to 90 MW in operation as of June 29, 2026, against 75 MW announced: 100%. The low end is the IT load, the high end the whole facility, because the announcement does not say which it means.",
   "announced_mw": 75,
   "announced_basis": "capacity, basis not stated",
   "announced_text": "75 MW",
   "announced_source": "nebius-2024-10-08",
   "upper_figure_mw": null,
   "upper_figure_text": null,
   "confirmed_low_mw": 75.0,
   "confirmed_high_mw": 90.0,
   "counted_low_mw": 75.0,
   "counted_high_mw": 75,
   "evidence_as_of": "2026-06-29",
   "epoch_ai": {
    "it_mw": 75.0,
    "facility_mw": 90.0,
    "buildings_operating": 3,
    "sites": [
     {
      "name": "Nebius Mantsala",
      "power_map": "https://siscto.si/power-map/nebius-mantsala/",
      "it_mw": 75.0,
      "facility_mw": 90.0,
      "as_of": "2026-06-29",
      "status": "Operating, expanding"
     }
    ]
   },
   "schedule_note": null,
   "announcements": [
    {
     "id": "nebius-2024-10-08",
     "type": "announcement",
     "date": "2024-10-08",
     "undated_page": false,
     "who": "Nebius",
     "kind": "Company statement",
     "title": "Nebius to triple capacity at Finland data center to 75 MW",
     "publisher": "Nebius",
     "url": "https://nebius.com/newsroom/nebius-to-triple-capacity-at-finland-data-center-to-75-mw",
     "summary": "Nebius says it will triple its Mäntsälä data center.",
     "quotes": [
      "Nebius to triple capacity at Finland data center to 75 MW",
      "place up to 60,000 GPUs at the Mäntsälä location alone"
     ],
     "power_stated": "75 MW",
     "promised": "",
     "confirmed_mw": null,
     "used_in_total": null
    }
   ],
   "evidence": []
  },
  {
   "slug": "project-rainier-new-carlisle",
   "name": "Project Rainier, New Carlisle",
   "url": "https://siscto.si/ledger/project-rainier-new-carlisle/",
   "operators": [
    "Amazon",
    "Anthropic"
   ],
   "filed_under": "Amazon",
   "town": "New Carlisle",
   "region": "Indiana",
   "country": "United States",
   "state": "Partly energized",
   "state_evidence": "No power figure was announced. Epoch AI estimates 1,037 MW of IT power in operation (1,244 MW for the whole facility) as of October 19, 2026, with more capacity on its timeline.",
   "announced_mw": null,
   "announced_basis": null,
   "announced_text": null,
   "announced_source": null,
   "upper_figure_mw": null,
   "upper_figure_text": null,
   "confirmed_low_mw": 1037.0,
   "confirmed_high_mw": 1244.0,
   "counted_low_mw": null,
   "counted_high_mw": null,
   "evidence_as_of": "2026-10-19",
   "epoch_ai": {
    "it_mw": 1037.0,
    "facility_mw": 1244.0,
    "buildings_operating": 18,
    "sites": [
     {
      "name": "Anthropic-Amazon New Carlisle",
      "power_map": "https://siscto.si/power-map/anthropic-amazon-new-carlisle/",
      "it_mw": 1037.0,
      "facility_mw": 1244.0,
      "as_of": "2026-10-19",
      "status": "Operating, expanding"
     }
    ]
   },
   "schedule_note": null,
   "announcements": [
    {
     "id": "amazon-2025-06-24",
     "type": "announcement",
     "date": "2025-06-24",
     "undated_page": false,
     "who": "Amazon",
     "kind": "Company statement",
     "title": "AWS's Project Rainier: the world's most powerful computer for training AI",
     "publisher": "About Amazon",
     "url": "https://www.aboutamazon.com/news/aws/aws-project-rainier-ai-trainium-chips-compute-cluster",
     "summary": "Amazon describes Project Rainier and its site in St. Joseph County, Indiana, used by Anthropic. It counts chips and states no power figure.",
     "quotes": [
      "nearly half a million Trainium2 chips",
      "Claude is expected to be on more than 1 million Trainium2 chips"
     ],
     "power_stated": "",
     "promised": "More than 1 million Trainium2 chips by the end of the year",
     "confirmed_mw": null,
     "used_in_total": null
    },
    {
     "id": "register-2025-07-04",
     "type": "announcement",
     "date": "2025-07-04",
     "undated_page": false,
     "who": "The New York Times, reported by The Register",
     "kind": "Press report",
     "title": "Amazon Project Rainier: AI supercomputer for Anthropic",
     "publisher": "The Register",
     "url": "https://www.theregister.com/2025/07/04/project_rainier_deep_dive/",
     "summary": "The Register cites a New York Times report for the campus power and an Amazon director for the number of buildings. A press figure is listed, never counted.",
     "quotes": [
      "consume upwards of 2.2 gigawatts of power",
      "will span thirty datacenters at 200,000 square feet apiece"
     ],
     "power_stated": "Upwards of 2.2 GW (press report)",
     "promised": "",
     "confirmed_mw": null,
     "used_in_total": null
    }
   ],
   "evidence": []
  },
  {
   "slug": "microsoft-fairwater-atlanta",
   "name": "Microsoft Fairwater Atlanta",
   "url": "https://siscto.si/ledger/microsoft-fairwater-atlanta/",
   "operators": [
    "Microsoft"
   ],
   "filed_under": "Microsoft",
   "town": "Fayetteville",
   "region": "Georgia",
   "country": "United States",
   "state": "Energized",
   "state_evidence": "No power figure was announced. Epoch AI estimates 636 MW of IT power in operation (859 MW for the whole facility) as of June 14, 2026.",
   "announced_mw": null,
   "announced_basis": null,
   "announced_text": null,
   "announced_source": null,
   "upper_figure_mw": null,
   "upper_figure_text": null,
   "confirmed_low_mw": 636.0,
   "confirmed_high_mw": 859.0,
   "counted_low_mw": null,
   "counted_high_mw": null,
   "evidence_as_of": "2026-06-14",
   "epoch_ai": {
    "it_mw": 636.0,
    "facility_mw": 859.0,
    "buildings_operating": 4,
    "sites": [
     {
      "name": "Microsoft Fairwater Atlanta",
      "power_map": "https://siscto.si/power-map/microsoft-fairwater-atlanta/",
      "it_mw": 636.0,
      "facility_mw": 859.0,
      "as_of": "2026-06-14",
      "status": "Operating"
     }
    ]
   },
   "schedule_note": null,
   "announcements": [
    {
     "id": "microsoft-2025-11-12",
     "type": "announcement",
     "date": "2025-11-12",
     "undated_page": false,
     "who": "Microsoft",
     "kind": "Company statement",
     "title": "Infinite scale: The architecture behind the Azure AI superfactory",
     "publisher": "The Official Microsoft Blog",
     "url": "https://blogs.microsoft.com/blog/2025/11/12/infinite-scale-the-architecture-behind-the-azure-ai-superfactory/",
     "summary": "Microsoft unveils its Fairwater site in Atlanta, Georgia. It states no power figure for the site.",
     "quotes": [
      "Today, we are unveiling the next Fairwater site of Azure AI datacenters in Atlanta, Georgia."
     ],
     "power_stated": "",
     "promised": "",
     "confirmed_mw": null,
     "used_in_total": null
    }
   ],
   "evidence": []
  },
  {
   "slug": "microsoft-fairwater-wisconsin",
   "name": "Microsoft Fairwater Wisconsin",
   "url": "https://siscto.si/ledger/microsoft-fairwater-wisconsin/",
   "operators": [
    "Microsoft"
   ],
   "filed_under": "Microsoft",
   "town": "Mount Pleasant",
   "region": "Wisconsin",
   "country": "United States",
   "state": "Partly energized",
   "state_evidence": "No power figure was announced. Epoch AI estimates 369 MW of IT power in operation (442 MW for the whole facility) as of May 15, 2026, with more capacity on its timeline.",
   "announced_mw": null,
   "announced_basis": null,
   "announced_text": null,
   "announced_source": null,
   "upper_figure_mw": null,
   "upper_figure_text": null,
   "confirmed_low_mw": 369.0,
   "confirmed_high_mw": 442.0,
   "counted_low_mw": null,
   "counted_high_mw": null,
   "evidence_as_of": "2026-05-15",
   "epoch_ai": {
    "it_mw": 369.0,
    "facility_mw": 442.0,
    "buildings_operating": 1,
    "sites": [
     {
      "name": "Microsoft Fairwater Wisconsin",
      "power_map": "https://siscto.si/power-map/microsoft-fairwater-wisconsin/",
      "it_mw": 369.0,
      "facility_mw": 442.0,
      "as_of": "2026-05-15",
      "status": "Operating, expanding"
     }
    ]
   },
   "schedule_note": null,
   "announcements": [
    {
     "id": "microsoft-2025-09-18",
     "type": "announcement",
     "date": "2025-09-18",
     "undated_page": false,
     "who": "Microsoft",
     "kind": "Company statement",
     "title": "Made in Wisconsin: The world's most powerful AI datacenter",
     "publisher": "Microsoft On the Issues",
     "url": "https://blogs.microsoft.com/on-the-issues/2025/09/18/made-in-wisconsin-the-worlds-most-powerful-ai-datacenter/",
     "summary": "Microsoft announces the Fairwater datacenter in Mount Pleasant and a second one. It states money and a date, and no power figure.",
     "quotes": [
      "bring this AI datacenter online in early 2026",
      "an additional $4 billion to be spent in the next three years"
     ],
     "power_stated": "",
     "promised": "Online in early 2026; a second datacenter within three years",
     "confirmed_mw": null,
     "used_in_total": null
    }
   ],
   "evidence": []
  },
  {
   "slug": "ecodatacenter-2-borlange",
   "name": "EcoDataCenter 2, Borlänge",
   "url": "https://siscto.si/ledger/ecodatacenter-2-borlange/",
   "operators": [
    "Mistral AI",
    "EcoDataCenter"
   ],
   "filed_under": "Mistral AI",
   "town": "Borlänge",
   "region": "Dalarna County",
   "country": "Sweden",
   "state": "Under construction",
   "state_evidence": "Epoch AI tracks the site as under construction, with no building operating as of August 17, 2026.",
   "announced_mw": null,
   "announced_basis": null,
   "announced_text": null,
   "announced_source": null,
   "upper_figure_mw": null,
   "upper_figure_text": null,
   "confirmed_low_mw": 0,
   "confirmed_high_mw": 0,
   "counted_low_mw": null,
   "counted_high_mw": null,
   "evidence_as_of": "2026-08-17",
   "epoch_ai": {
    "it_mw": 0,
    "facility_mw": 0,
    "buildings_operating": 0,
    "sites": [
     {
      "name": "EcoDataCenter 2",
      "power_map": "https://siscto.si/power-map/ecodatacenter-2/",
      "it_mw": null,
      "facility_mw": null,
      "as_of": "2026-08-17",
      "status": "Under construction"
     }
    ]
   },
   "schedule_note": null,
   "announcements": [
    {
     "id": "ecodc-2026-02-11",
     "type": "announcement",
     "date": "2026-02-11",
     "undated_page": false,
     "who": "EcoDataCenter and Mistral AI",
     "kind": "Company statement",
     "title": "Mistral AI and EcoDataCenter Partner to Build AI-focused Data Center in Sweden",
     "publisher": "EcoDataCenter",
     "url": "https://ecodatacenter.tech/press/mistral-ai-and-ecodatacenter-partner-to-build-ai-focused-data-center-in-sweden-3431886",
     "summary": "The two companies announce a data center at EcoDataCenter's Borlänge site. They state money and an opening year, and no power figure.",
     "quotes": [
      "a strategic, long-term investment of €1.2 billion in Sweden’s digital infrastructure",
      "Scheduled to open in 2027"
     ],
     "power_stated": "",
     "promised": "Opens in 2027",
     "confirmed_mw": null,
     "used_in_total": null
    }
   ],
   "evidence": []
  },
  {
   "slug": "stargate-dona-ana-county",
   "name": "Stargate Doña Ana County (Project Jupiter)",
   "url": "https://siscto.si/ledger/stargate-dona-ana-county/",
   "operators": [
    "OpenAI",
    "Oracle",
    "BorderPlex Digital Assets",
    "STACK Infrastructure"
   ],
   "filed_under": "OpenAI",
   "town": "Doña Ana County",
   "region": "New Mexico",
   "country": "United States",
   "state": "Under construction",
   "state_evidence": "Epoch AI tracks the site as under construction, with no building operating as of June 22, 2026.",
   "announced_mw": null,
   "announced_basis": null,
   "announced_text": null,
   "announced_source": null,
   "upper_figure_mw": 2450,
   "upper_figure_text": "up to 2.45 GW of installed fuel cell capacity",
   "confirmed_low_mw": 0,
   "confirmed_high_mw": 0,
   "counted_low_mw": null,
   "counted_high_mw": null,
   "evidence_as_of": "2026-06-22",
   "epoch_ai": {
    "it_mw": 0,
    "facility_mw": 0,
    "buildings_operating": 0,
    "sites": [
     {
      "name": "OpenAI Stargate New Mexico",
      "power_map": "https://siscto.si/power-map/openai-stargate-new-mexico/",
      "it_mw": null,
      "facility_mw": null,
      "as_of": "2026-06-22",
      "status": "Under construction"
     }
    ]
   },
   "schedule_note": null,
   "announcements": [
    {
     "id": "openai-2025-09-23-donaana",
     "type": "announcement",
     "date": "2025-09-23",
     "undated_page": false,
     "who": "OpenAI, Oracle and SoftBank",
     "kind": "Company statement",
     "title": "OpenAI, Oracle, and SoftBank expand Stargate with five new AI data center sites",
     "publisher": "OpenAI",
     "url": "https://openai.com/index/five-new-stargate-sites/",
     "summary": "OpenAI names Doña Ana County, New Mexico as one of three new sites built with Oracle. No figure is given for this site alone.",
     "quotes": [
      "can deliver over 5.5 gigawatts of capacity"
     ],
     "power_stated": "Over 5.5 GW for three Oracle sites and an Abilene expansion together",
     "promised": "",
     "confirmed_mw": null,
     "used_in_total": null
    },
    {
     "id": "oracle-2026-04-27",
     "type": "announcement",
     "date": "2026-04-27",
     "undated_page": false,
     "who": "Oracle",
     "kind": "Company statement",
     "title": "Oracle, BorderPlex, and Bloom Energy to Power Project Jupiter with Cleaner, Water-Efficient Fuel Cell Technology",
     "publisher": "Oracle",
     "url": "https://www.oracle.com/news/announcement/oracle-borderplex-and-bloom-energy-to-power-project-jupiter-with-fuel-cell-technology-2026-04-27/",
     "summary": "Oracle says the campus will be powered by Bloom fuel cells. The figure is the on-site power supply, stated as an upper limit.",
     "quotes": [
      "up to 2.45 GW of installed Bloom fuel cell capacity",
      "Construction continues to move forward on schedule."
     ],
     "power_stated": "Up to 2.45 GW of installed fuel cell capacity (on-site power supply)",
     "promised": "",
     "confirmed_mw": null,
     "used_in_total": null
    }
   ],
   "evidence": []
  },
  {
   "slug": "stargate-lordstown",
   "name": "Stargate Lordstown",
   "url": "https://siscto.si/ledger/stargate-lordstown/",
   "operators": [
    "OpenAI",
    "SoftBank"
   ],
   "filed_under": "OpenAI",
   "town": "Lordstown",
   "region": "Ohio",
   "country": "United States",
   "state": "Under construction",
   "state_evidence": "Epoch AI tracks the site as under construction, with no building operating as of July 30, 2026.",
   "announced_mw": null,
   "announced_basis": null,
   "announced_text": null,
   "announced_source": null,
   "upper_figure_mw": null,
   "upper_figure_text": null,
   "confirmed_low_mw": 0,
   "confirmed_high_mw": 0,
   "counted_low_mw": null,
   "counted_high_mw": null,
   "evidence_as_of": "2026-07-30",
   "epoch_ai": {
    "it_mw": 0,
    "facility_mw": 0,
    "buildings_operating": 0,
    "sites": [
     {
      "name": "OpenAI Stargate Lordstown",
      "power_map": "https://siscto.si/power-map/openai-stargate-lordstown/",
      "it_mw": null,
      "facility_mw": null,
      "as_of": "2026-07-30",
      "status": "Under construction"
     }
    ]
   },
   "schedule_note": null,
   "announcements": [
    {
     "id": "openai-2025-09-23-lordstown",
     "type": "announcement",
     "date": "2025-09-23",
     "undated_page": false,
     "who": "OpenAI, Oracle and SoftBank",
     "kind": "Company statement",
     "title": "OpenAI, Oracle, and SoftBank expand Stargate with five new AI data center sites",
     "publisher": "OpenAI",
     "url": "https://openai.com/index/five-new-stargate-sites/",
     "summary": "OpenAI names Lordstown, Ohio as a SoftBank site. The power figure covers Lordstown and Milam County together, so no figure is counted for Lordstown alone.",
     "quotes": [
      "can scale to 1.5 gigawatts over the next 18 months",
      "on track to be operational next year"
     ],
     "power_stated": "1.5 GW for Lordstown and Milam County together, as a \"can scale to\" figure",
     "promised": "Operational in 2026",
     "confirmed_mw": null,
     "used_in_total": null
    }
   ],
   "evidence": []
  }
 ]
}