# Abilene campus for Microsoft: Announced vs Built | $SIS

> Abilene campus for Microsoft in Abilene, Texas: 900 MW announced, nothing confirmed energized as of Jan 15, 2026. Announcements, evidence and sources.

Source: https://siscto.si/ledger/abilene-microsoft-campus/
Updated: 2026-11-11

1. [Home](https://siscto.si/)
2. [Gigawatt Ledger](https://siscto.si/ledger/)
3. Abilene campus for Microsoft

Gigawatt Ledger · Under construction

# Abilene campus for Microsoft, announced against built

Abilene campus for Microsoft is an SI compute project in Abilene, Texas, by Microsoft and Crusoe. The announced figure is 900 MW site, from Crusoe (Mar 27, 2026). Epoch AI tracks the site as under construction, with no building operating as of January 15, 2026. Its state today: under construction.

Announced
:   900 MW

Energized
:   None (Jan 15, 2026)

State
:   Under construction

Source links
:   2

Announced

## What was said, and when

Each row is one public announcement about Abilene campus for Microsoft: who said it, the power or capacity it states in its own unit, the promised date, and the link. Company claims are quoted as claims.

**Mar 27, 2026**

Crusoe

### [Crusoe builds 900 MW Abilene campus for Microsoft](https://www.crusoe.ai/resources/newsroom/crusoe-announces-new-900-mw-ai-factory-campus-in-abilene-texas-to-support-microsoft-ai-infrastructure)

Crusoe announces a new 900 MW campus in Abilene for Microsoft: two buildings and an on-site power plant.

> “the 900 MW site includes two new buildings and an onsite power plant to support grid resilience”

> “Each of the two new buildings is designed to deliver 336 MW of critical IT load”

> “the first building expected to be energized in mid-2027”

> “bringing the total projected capacity across the full Abilene site to 2.1 gigawatts (GW)”

Power or capacity stated
:   900 MW site; 336 MW of critical IT load in each of two buildings

Promised
:   First building energized in mid-2027

Built

## What public evidence confirms

What is on the ground today, from the Power Map data and from any statement or filing that states live power.

Epoch AI tracks the site as under construction, with no building operating as of January 15, 2026.

**Jan 15, 2026**

Epoch AI · Power Map

### Crusoe Abilene Expansion on the Power Map

Epoch AI tracks Crusoe Abilene Expansion as under construction: no building is operating as of January 15, 2026.

> Land clearing continues.

IT power running
:   None

Whole facility
:   None

Epoch AI projects 672 MW of IT power by November 11, 2027. A projection, not a fact yet.

Timeline

### Heat Watch

Over the last three summers NASA's MODIS read the ground here -0.4 °C against the land 5 to 10 km around it by day.

[Open Heat Watch](https://siscto.si/heat-watch/crusoe-abilene-expansion/)

## Announcements and evidence, by date

What was promised and what was seen, in the order it became public. The full dated record of each site is on its Power Map page.

**Nov 2, 2025**

Crusoe Abilene Expansion: 0 buildings operating, no IT power yet. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/crusoe-abilene-expansion/))

**Jan 15, 2026**

Crusoe Abilene Expansion: 0 buildings operating, no IT power yet. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/crusoe-abilene-expansion/))

**Mar 27, 2026**

Crusoe: 900 MW site; 336 MW of critical IT load in each of two buildings. Promised: first building energized in mid-2027. (Announcement · [Crusoe](https://www.crusoe.ai/resources/newsroom/crusoe-announces-new-900-mw-ai-factory-campus-in-abilene-texas-to-support-microsoft-ai-infrastructure))

Corrections

## See something wrong? File a correction

Sign in with your SI Passport and say what is wrong, with a link to a public source. The team reads the source before anything changes, and approved corrections stay on this page.

### File a correction

A correction needs a link. Nothing shows until the team approves it. If your Passport carries an Org check it shows here, and an organization correcting its own project is labeled as such.

Corrections on file · 0

Sources

## Every link behind this page

Read on November 11, 2026. An undated page carries the date it was read.

- [Crusoe builds 900 MW Abilene campus for Microsoft](https://www.crusoe.ai/resources/newsroom/crusoe-announces-new-900-mw-ai-factory-campus-in-abilene-texas-to-support-microsoft-ai-infrastructure), Crusoe, Mar 27, 2026

- [Crusoe Abilene Expansion on the Power Map](https://siscto.si/power-map/crusoe-abilene-expansion/), from [Epoch AI](https://epoch.ai/data/ai-data-centers), "AI data centers" (CC BY 4.0), retrieved November 10, 2026

More projects

## Keep reading the Ledger

Three more projects, the same operator first.

[The whole Ledger](https://siscto.si/ledger/)

### Microsoft Fairwater Atlanta

Fayetteville, Georgia

No power figure stated · 636 MW IT

### Microsoft Fairwater Wisconsin

Mount Pleasant, Wisconsin

No power figure stated · 369 MW IT

### Colossus (Memphis and Southaven)

Memphis, Tennessee

2 GW announced · 1 to 1.7 GW