# Barber Lake, announced against built

Barber Lake is an SI compute project in Colorado City, Texas, by Fluidstack, Cipher Mining and Anthropic. The announced figure is 207 MW of critical IT load (168 MW and 39 MW), from Cipher Mining (Nov 20, 2025). Cipher said it expected to deliver 168 MW of critical IT load by September 2026. Epoch AI's entry of July 30, 2026 reads "still under construction and not yet energized", and Epoch AI estimates the first phase for about December 2026, "about 3 months later than the disclosed target". Its state today: delayed.

Announced
:   207 MW

Energized
:   None (Jul 30, 2026)

State
:   Delayed

Source links
:   4

Announced

## What was said, and when

Each row is one public announcement about Barber Lake: who said it, the power or capacity it states in its own unit, the promised date, and the link. Company claims are quoted as claims.

**Sep 25, 2025**

Cipher Mining

### [Cipher Mining Signs 168 MW, 10-Year AI Hosting Agreement with Fluidstack](https://www.globenewswire.com/news-release/2025/09/25/3156107/0/en/Cipher-Mining-Signs-168-MW-10-Year-AI-Hosting-Agreement-with-Fluidstack.html)

Cipher signs a 10-year hosting agreement with Fluidstack, backed by Google, at its Barber Lake site.

> “Cipher will deliver 168 MW of critical IT load, supported by a maximum of 244 MW of gross capacity”

> “Expected Delivery of 168 MW of Critical IT Load by September of 2026”

Power or capacity stated
:   168 MW of critical IT load (244 MW gross)

Promised
:   Delivered by September 2026

**Nov 12, 2025**

Anthropic

### [Anthropic invests $50 billion in American AI infrastructure](https://www.anthropic.com/news/anthropic-invests-50-billion-in-american-ai-infrastructure)

Anthropic announces data centers with Fluidstack in Texas and New York. It names no site and states no power figure.

> “a $50 billion investment in American computing infrastructure”

> “with sites coming online throughout 2026”

Power or capacity stated
:   None stated

Promised
:   Sites online throughout 2026

**Nov 20, 2025**

Cipher Mining

### [Cipher Mining Signs Additional 56 MW, 10-Year AI Hosting Agreement with Fluidstack](https://www.globenewswire.com/news-release/2025/11/20/3191801/0/en/Cipher-Mining-Signs-Additional-56-MW-10-Year-AI-Hosting-Agreement-with-Fluidstack.html)

Fluidstack takes the rest of the site.

> “an additional 39 MW of critical IT load”

> “lease the entire 300 MW of capacity at Cipher's Barber Lake site”

> “Expected Delivery of Additional 39 MW of Critical IT Load at Barber Lake by January 2027”

Power or capacity stated
:   39 MW more critical IT load; the whole 300 MW site

Promised
:   Delivered by January 2027

Built

## What public evidence confirms

What is on the ground today, from the Power Map data and from any statement or filing that states live power.

Cipher said it expected to deliver 168 MW of critical IT load by September 2026. Epoch AI's entry of July 30, 2026 reads "still under construction and not yet energized", and Epoch AI estimates the first phase for about December 2026, "about 3 months later than the disclosed target".

**Jul 30, 2026**

Epoch AI · Power Map

### Anthropic Barber Lake on the Power Map

Epoch AI tracks Anthropic Barber Lake as under construction: no building is operating as of July 30, 2026.

> Building 1 shell is complete, with rooftop units installed, and most air-cooled chillers in place in a ground yard to the north. Most of the 120 backup diesel generators are also in place. Substantial progress since Nov 2025, still under construction and not yet energized.

IT power running
:   None

Whole facility
:   None

Epoch AI projects 207 MW of IT power by April 30, 2027. A projection, not a fact yet.

Timeline

### Heat Watch

Over the last three summers NASA's MODIS read the ground here +0.5 °C against the land 5 to 10 km around it by day.

[Open Heat Watch](https://siscto.si/heat-watch/anthropic-barber-lake/)

## Announcements and evidence, by date

What was promised and what was seen, in the order it became public. The full dated record of each site is on its Power Map page.

**Sep 18, 2025**

Anthropic Barber Lake: 0 buildings operating, no IT power yet. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/anthropic-barber-lake/))

**Sep 25, 2025**

Cipher Mining: 168 MW of critical IT load (244 MW gross). Promised: delivered by September 2026. (Announcement · [GlobeNewswire](https://www.globenewswire.com/news-release/2025/09/25/3156107/0/en/Cipher-Mining-Signs-168-MW-10-Year-AI-Hosting-Agreement-with-Fluidstack.html))

**Nov 12, 2025**

Anthropic: no power figure stated. Promised: sites online throughout 2026. (Announcement · [Anthropic](https://www.anthropic.com/news/anthropic-invests-50-billion-in-american-ai-infrastructure))

**Nov 20, 2025**

Cipher Mining: 39 MW more critical IT load; the whole 300 MW site. Promised: delivered by January 2027. (Announcement · [GlobeNewswire](https://www.globenewswire.com/news-release/2025/11/20/3191801/0/en/Cipher-Mining-Signs-Additional-56-MW-10-Year-AI-Hosting-Agreement-with-Fluidstack.html))

**Nov 29, 2025**

Anthropic Barber Lake: 0 buildings operating, no IT power yet. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/anthropic-barber-lake/))

**Jul 30, 2026**

Anthropic Barber Lake: 0 buildings operating, no IT power yet. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/anthropic-barber-lake/))

Corrections

## See something wrong? File a correction

Sign in with your SI Passport and say what is wrong, with a link to a public source. The team reads the source before anything changes, and approved corrections stay on this page.

### File a correction

A correction needs a link. Nothing shows until the team approves it. If your Passport carries an Org check it shows here, and an organization correcting its own project is labeled as such.

Corrections on file · 0

Sources

## Every link behind this page

Read on November 11, 2026. An undated page carries the date it was read.

- [Cipher Mining Signs 168 MW, 10-Year AI Hosting Agreement with Fluidstack](https://www.globenewswire.com/news-release/2025/09/25/3156107/0/en/Cipher-Mining-Signs-168-MW-10-Year-AI-Hosting-Agreement-with-Fluidstack.html), GlobeNewswire, Sep 25, 2025

- [Cipher Mining Signs Additional 56 MW, 10-Year AI Hosting Agreement with Fluidstack](https://www.globenewswire.com/news-release/2025/11/20/3191801/0/en/Cipher-Mining-Signs-Additional-56-MW-10-Year-AI-Hosting-Agreement-with-Fluidstack.html), GlobeNewswire, Nov 20, 2025

- [Anthropic invests $50 billion in American AI infrastructure](https://www.anthropic.com/news/anthropic-invests-50-billion-in-american-ai-infrastructure), Anthropic, Nov 12, 2025

- [Anthropic Barber Lake on the Power Map](https://siscto.si/power-map/anthropic-barber-lake/), from [Epoch AI](https://epoch.ai/data/ai-data-centers), "AI data centers" (CC BY 4.0), retrieved November 10, 2026

More projects

## Keep reading the Ledger

Three more projects, the same operator first.

[The whole Ledger](https://siscto.si/ledger/)

### Lake Mariner

Barker, New York

440 MW announced · 268 MW

### Colossus (Memphis and Southaven)

Memphis, Tennessee

2 GW announced · 1 to 1.7 GW

### Meta Hyperion

Richland Parish, Louisiana

2 GW announced · nothing confirmed