# Colossus (Memphis and Southaven): Announced vs Built | $SIS

> Colossus (Memphis and Southaven) in Memphis, Tennessee: 2 GW announced, 1 to 1.7 GW confirmed energized as of Jun 15, 2026. Announcements, evidence and sources.

Source: https://siscto.si/ledger/colossus-memphis/
Updated: 2026-11-11

1. [Home](https://siscto.si/)
2. [Gigawatt Ledger](https://siscto.si/ledger/)
3. Colossus

Gigawatt Ledger · Partly energized

# Colossus, announced against built

Colossus (Memphis and Southaven) is an SI compute project in Memphis, Tennessee, by SpaceXAI. The announced figure is almost 2 GW of training compute, from Elon Musk, reported by SiliconANGLE (Dec 30, 2025). Public evidence puts 1 to 1.7 GW in operation as of June 15, 2026, against 2 GW announced: 50% to 85%. The range covers every figure listed below. Its state today: partly energized.

Announced
:   2 GW

Energized
:   1 to 1.7 GW (Jun 15, 2026)

State
:   Partly energized

Source links
:   5

Announced

## What was said, and when

Each row is one public announcement about Colossus: who said it, the power or capacity it states in its own unit, the promised date, and the link. Company claims are quoted as claims.

**May 5, 2025**

Memphis Light, Gas and Water

### [xAI Update, May 5, 2025](https://www.mlgw.com/images/content/files/pdf/new/5-5-25%20xAI%20Update.pdf)

The city utility reports what xAI receives and has asked for at its first site on Paul Lowry Road, and the options discussed for the second site on Tulane Road.

> “xAI requested an additional 150MW at this location, for a total of 300MW.”

> “a range of grid power options from 260MW to 1.1GW has been discussed”

Power or capacity stated
:   300 MW requested at the first site; 260 MW to 1.1 GW discussed for the second

Promised
:   300 MW at the first site by no later than December 2025

**Dec 30, 2025**

Elon Musk, reported by SiliconANGLE

### [Elon Musk reveals plan to expand xAI's 'Colossus' data center to 2 gigawatts](https://siliconangle.com/2025/12/30/elon-musk-reveals-plan-expand-xais-colossus-data-center-2-gigawatts/)

SiliconANGLE quotes Elon Musk's post on X about a third building in Southaven, Mississippi. The figure is the company's own statement, so it is counted.

> “xAI has bought a third building called MACROHARDRR. Will take xAI training compute to almost 2GW.”

Power or capacity stated
:   Almost 2 GW of training compute for the whole complex

Promised
:   The third building becomes a data center during 2026

Built

## What public evidence confirms

What is on the ground today, from the Power Map data and from any statement or filing that states live power.

Public evidence puts 1 to 1.7 GW in operation as of June 15, 2026, against 2 GW announced: 50% to 85%. The range covers every figure listed below.

**Jun 15, 2026**

Epoch AI · Power Map

### Colossus 1 on the Power Map

Epoch AI counts 1 building operating at Colossus 1 and estimates 340 MW of IT power (425 MW for the whole facility) as of June 15, 2026.

> No major changes to the data center since February. Solar panels have been placed next to the facility.

IT power running
:   340 MW

Whole facility
:   425 MW

**Jun 15, 2026**

Epoch AI · Power Map

### Colossus 2 on the Power Map

Epoch AI counts 2 buildings operating at Colossus 2 and estimates 946 MW of IT power (1,276 MW for the whole facility) as of June 15, 2026.

> The site is estimated to have at least ~830 MW of GPU server power, with at least "at least 220,000 additional GB300 processors and over 400 additional megawatts of compute power", corresponding to the "next phase of expansion" found in the following [company S-1 filing, page 76](https://www.sec.gov/Archives/edgar/data/1181412/000162828026036936/spaceexplorationtechnologi.htm). This estimate is backed up by our cooling and turbine based power production calculations. The cooling calculations suggest there is enough infrastructure to support ~850MW of IT Power. Similarly the energy production calculations support ~900MW of available IT Power. This gives us confidence that the proposed expansion was achieved in time. The roof for building 3 is halfway complete.

IT power running
:   946 MW

Whole facility
:   1,276 MW

Epoch AI projects 1,531 MW of IT power by February 25, 2027. A projection, not a fact yet.

**May 5, 2025**

Memphis Light, Gas and Water

### [xAI Update, May 5, 2025](https://www.mlgw.com/images/content/files/pdf/new/5-5-25%20xAI%20Update.pdf)

The utility states the grid power it delivered to the first site on that date.

> “xAI is receiving 150MW of power at the Paul Lowry site.”

Power confirmed
:   150 MW

Used in the total
:   No, shown as history

**May 20, 2026**

Space Exploration Technologies Corp.

### [Form S-1 registration statement](https://www.sec.gov/Archives/edgar/data/1181412/000162828026036936/spaceexplorationtechnologi.htm)

The company's registration statement gives one figure for both facilities together.

> “Our AI compute facilities, COLOSSUS and COLOSSUS II, collectively provide approximately 1.0 gigawatt of compute power”

Power confirmed
:   1,000 MW

Used in the total
:   Yes

Seen from orbit · Compute Watch

### The newest clear pass over the site

The image loads from NASA's public imagery: true color at 30 m per pixel, about 5 km across, north up.

[Open Compute Watch](https://siscto.si/compute/)

Timeline

### Heat Watch

Over the last three summers NASA's MODIS read the ground here -0.4 °C against the land 5 to 10 km around it by day, a change of -0.0 °C since before work on this build began.

[Open Heat Watch](https://siscto.si/heat-watch/colossus-1/)

### Heat Watch

Over the last three summers NASA's MODIS read the ground here +1.3 °C against the land 5 to 10 km around it by day.

[Open Heat Watch](https://siscto.si/heat-watch/colossus-2/)

## Announcements and evidence, by date

What was promised and what was seen, in the order it became public. The full dated record of each site is on its Power Map page.

**May 5, 2025**

Memphis Light, Gas and Water: 300 MW requested at the first site; 260 MW to 1.1 GW discussed for the second. Promised: 300 MW at the first site by no later than December 2025. (Announcement · [MLGW](https://www.mlgw.com/images/content/files/pdf/new/5-5-25%20xAI%20Update.pdf))

**May 5, 2025**

The utility states the grid power it delivered to the first site on that date. (Evidence · [MLGW](https://www.mlgw.com/images/content/files/pdf/new/5-5-25%20xAI%20Update.pdf))

**Oct 19, 2025**

Colossus 2: 1 building operating, 239 MW of IT power. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/colossus-2/))

**Dec 30, 2025**

Elon Musk, reported by SiliconANGLE: Almost 2 GW of training compute for the whole complex. Promised: the third building becomes a data center during 2026. (Announcement · [SiliconANGLE](https://siliconangle.com/2025/12/30/elon-musk-reveals-plan-expand-xais-colossus-data-center-2-gigawatts/))

**Jan 13, 2026**

Colossus 2: 1 building operating, 239 MW of IT power. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/colossus-2/))

**Feb 11, 2026**

Colossus 1: 1 building operating, 340 MW of IT power. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/colossus-1/))

**Apr 6, 2026**

Colossus 2: 1 building operating, 490 MW of IT power. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/colossus-2/))

**May 6, 2026**

Colossus 1: 1 building operating, 340 MW of IT power. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/colossus-1/))

**May 20, 2026**

The company's registration statement gives one figure for both facilities together. (Evidence · [U.S. Securities and Exchange Commission](https://www.sec.gov/Archives/edgar/data/1181412/000162828026036936/spaceexplorationtechnologi.htm))

**Jun 1, 2026**

Colossus 1: 1 building operating, 340 MW of IT power. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/colossus-1/))

**Jun 15, 2026**

Colossus 1: 1 building operating, 340 MW of IT power. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/colossus-1/))

**Jun 15, 2026**

Colossus 2: 2 buildings operating, 946 MW of IT power. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/colossus-2/))

Corrections

## See something wrong? File a correction

Sign in with your SI Passport and say what is wrong, with a link to a public source. The team reads the source before anything changes, and approved corrections stay on this page.

### File a correction

A correction needs a link. Nothing shows until the team approves it. If your Passport carries an Org check it shows here, and an organization correcting its own project is labeled as such.

Corrections on file · 0

Sources

## Every link behind this page

Read on November 11, 2026. An undated page carries the date it was read.

- [xAI Update, May 5, 2025](https://www.mlgw.com/images/content/files/pdf/new/5-5-25%20xAI%20Update.pdf), MLGW, May 5, 2025

- [Elon Musk reveals plan to expand xAI's 'Colossus' data center to 2 gigawatts](https://siliconangle.com/2025/12/30/elon-musk-reveals-plan-expand-xais-colossus-data-center-2-gigawatts/), SiliconANGLE, Dec 30, 2025

- [Form S-1 registration statement](https://www.sec.gov/Archives/edgar/data/1181412/000162828026036936/spaceexplorationtechnologi.htm), U.S. Securities and Exchange Commission, May 20, 2026

- [Colossus 1 on the Power Map](https://siscto.si/power-map/colossus-1/), from [Epoch AI](https://epoch.ai/data/ai-data-centers), "AI data centers" (CC BY 4.0), retrieved November 10, 2026

- [Colossus 2 on the Power Map](https://siscto.si/power-map/colossus-2/), from [Epoch AI](https://epoch.ai/data/ai-data-centers), "AI data centers" (CC BY 4.0), retrieved November 10, 2026

More projects

## Keep reading the Ledger

Three more projects, the same operator first.

[The whole Ledger](https://siscto.si/ledger/)

### Meta Hyperion

Richland Parish, Louisiana

2 GW announced · nothing confirmed

### Stargate Shackelford County (Frontier)

Shackelford County, Texas

1.4 GW announced · nothing confirmed

### Stargate Michigan (Saline Township)

Saline Township, Michigan

1.38 GW announced · nothing confirmed