# Denton, announced against built

Denton is an SI compute project in Denton, Texas, by CoreWeave and Core Scientific. The announced figure is approximately 260 MW of critical IT load, from Core Scientific (Feb 26, 2025). Public evidence puts 262 MW in operation as of September 1, 2026, against 260 MW announced: 100%. The announcement states IT load, so it is set against the IT load running. Its state today: energized.

Announced
:   260 MW

Energized
:   262 MW (Sep 1, 2026)

State
:   Energized

Source links
:   2

Announced

## What was said, and when

Each row is one public announcement about Denton: who said it, the power or capacity it states in its own unit, the promised date, and the link. Company claims are quoted as claims.

**Feb 26, 2025**

Core Scientific

### [Core Scientific and CoreWeave Announce $1.2 Billion Expansion at Denton, TX Site](https://investors.corescientific.com/news-events/press-releases/detail/110/core-scientific-and-coreweave-announce-1-2-billion-expansion-at-denton-tx-site)

Core Scientific adds 70 MW for CoreWeave at its Denton site.

> “increases the full critical IT load to approximately 260 MW”

> “The 70 MW of additional contracted power at the Denton site”

Power or capacity stated
:   Approximately 260 MW of critical IT load

Promised
:   None stated

Built

## What public evidence confirms

What is on the ground today, from the Power Map data and from any statement or filing that states live power.

Public evidence puts 262 MW in operation as of September 1, 2026, against 260 MW announced: 100%. The announcement states IT load, so it is set against the IT load running.

**Sep 1, 2026**

Epoch AI · Power Map

### CoreWeave Denton TX on the Power Map

Epoch AI counts 7 buildings operating at CoreWeave Denton TX and estimates 262 MW of IT power (367 MW for the whole facility) as of September 1, 2026.

> Building 8 interior fit-out scheduled to begin. [TDLR project TABS2026028247](https://www.tdlr.texas.gov/TABS/Projects/TABS2026028247) schedules a $110M interior fit-out of the existing 27,678.22 sq ft Building A as a data hall beginning September 1, 2026.

IT power running
:   262 MW

Whole facility
:   367 MW

Epoch AI projects 282 MW of IT power by May 31, 2027. A projection, not a fact yet.

Timeline

### Heat Watch

Over the last three summers NASA's MODIS read the ground here -0.7 °C against the land 5 to 10 km around it by day, a change of +0.3 °C since before work on this build began.

[Open Heat Watch](https://siscto.si/heat-watch/coreweave-denton-tx/)

## Announcements and evidence, by date

What was promised and what was seen, in the order it became public. The full dated record of each site is on its Power Map page.

**Feb 26, 2025**

Core Scientific: Approximately 260 MW of critical IT load. (Announcement · [Core Scientific](https://investors.corescientific.com/news-events/press-releases/detail/110/core-scientific-and-coreweave-announce-1-2-billion-expansion-at-denton-tx-site))

**Feb 23, 2026**

CoreWeave Denton TX: 4 buildings operating, 131 MW of IT power. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/coreweave-denton-tx/))

**Mar 2, 2026**

CoreWeave Denton TX: 4 buildings operating, 131 MW of IT power. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/coreweave-denton-tx/))

**Jul 3, 2026**

CoreWeave Denton TX: 7 buildings operating, 262 MW of IT power. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/coreweave-denton-tx/))

**Sep 1, 2026**

CoreWeave Denton TX: 7 buildings operating, 262 MW of IT power. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/coreweave-denton-tx/))

Corrections

## See something wrong? File a correction

Sign in with your SI Passport and say what is wrong, with a link to a public source. The team reads the source before anything changes, and approved corrections stay on this page.

### File a correction

A correction needs a link. Nothing shows until the team approves it. If your Passport carries an Org check it shows here, and an organization correcting its own project is labeled as such.

Corrections on file · 0

Sources

## Every link behind this page

Read on November 11, 2026. An undated page carries the date it was read.

- [Core Scientific and CoreWeave Announce $1.2 Billion Expansion at Denton, TX Site](https://investors.corescientific.com/news-events/press-releases/detail/110/core-scientific-and-coreweave-announce-1-2-billion-expansion-at-denton-tx-site), Core Scientific, Feb 26, 2025

- [CoreWeave Denton TX on the Power Map](https://siscto.si/power-map/coreweave-denton-tx/), from [Epoch AI](https://epoch.ai/data/ai-data-centers), "AI data centers" (CC BY 4.0), retrieved November 10, 2026

More projects

## Keep reading the Ledger

Three more projects, the same operator first.

[The whole Ledger](https://siscto.si/ledger/)

### Polaris Forge 1

Ellendale, North Dakota

400 MW announced · 68 to 175 MW

### Lancaster

Lancaster, Pennsylvania

100 MW announced · nothing confirmed

### Muskogee

Muskogee, Oklahoma

100 MW announced · nothing confirmed