Gigawatt Ledger · Under construction

# EcoDataCenter 2, Borlänge, announced against built

EcoDataCenter 2, Borlänge is an SI compute project in Borlänge, Dalarna County, Sweden, by Mistral AI and EcoDataCenter. No source states a power figure for this project alone, so it is not in the Ledger's total. Epoch AI tracks the site as under construction, with no building operating as of August 17, 2026. Its state today: under construction.

Announced
:   Not stated

Energized
:   None (Aug 17, 2026)

State
:   Under construction

Source links
:   2

Announced

## What was said, and when

Each row is one public announcement about EcoDataCenter 2, Borlänge: who said it, the power or capacity it states in its own unit, the promised date, and the link. Company claims are quoted as claims.

**Feb 11, 2026**

EcoDataCenter and Mistral AI

### [Mistral AI and EcoDataCenter Partner to Build AI-focused Data Center in Sweden](https://ecodatacenter.tech/press/mistral-ai-and-ecodatacenter-partner-to-build-ai-focused-data-center-in-sweden-3431886)

The two companies announce a data center at EcoDataCenter's Borlänge site. They state money and an opening year, and no power figure.

> “a strategic, long-term investment of €1.2 billion in Sweden’s digital infrastructure”

> “Scheduled to open in 2027”

Power or capacity stated
:   None stated

Promised
:   Opens in 2027

Built

## What public evidence confirms

What is on the ground today, from the Power Map data and from any statement or filing that states live power.

Epoch AI tracks the site as under construction, with no building operating as of August 17, 2026.

**Aug 17, 2026**

Epoch AI · Power Map

### EcoDataCenter 2 on the Power Map

Epoch AI tracks EcoDataCenter 2 as under construction: no building is operating as of August 17, 2026.

> Buildings 1 and 2 look fully roofed, with active construction showing cooling and power equipment still being installed. Buildings 3-4 look like their foundations have been laid out and are early in construction.

IT power running
:   None

Whole facility
:   None

Epoch AI projects 48 MW of IT power by June 30, 2028. A projection, not a fact yet.

Timeline

### Heat Watch

Over the last three summers NASA's MODIS read the ground here +0.1 °C against the land 5 to 10 km around it by day.

[Open Heat Watch](https://siscto.si/heat-watch/ecodatacenter-2/)

## Announcements and evidence, by date

What was promised and what was seen, in the order it became public. The full dated record of each site is on its Power Map page.

**Sep 1, 2025**

EcoDataCenter 2: 0 buildings operating, no IT power yet. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/ecodatacenter-2/))

**Feb 11, 2026**

EcoDataCenter and Mistral AI: no power figure stated. Promised: opens in 2027. (Announcement · [EcoDataCenter](https://ecodatacenter.tech/press/mistral-ai-and-ecodatacenter-partner-to-build-ai-focused-data-center-in-sweden-3431886))

**May 9, 2026**

EcoDataCenter 2: 0 buildings operating, no IT power yet. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/ecodatacenter-2/))

**Aug 17, 2026**

EcoDataCenter 2: 0 buildings operating, no IT power yet. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/ecodatacenter-2/))

Corrections

## See something wrong? File a correction

Sign in with your SI Passport and say what is wrong, with a link to a public source. The team reads the source before anything changes, and approved corrections stay on this page.

### File a correction

A correction needs a link. Nothing shows until the team approves it. If your Passport carries an Org check it shows here, and an organization correcting its own project is labeled as such.

Corrections on file · 0

Sources

## Every link behind this page

Read on November 11, 2026. An undated page carries the date it was read.

- [Mistral AI and EcoDataCenter Partner to Build AI-focused Data Center in Sweden](https://ecodatacenter.tech/press/mistral-ai-and-ecodatacenter-partner-to-build-ai-focused-data-center-in-sweden-3431886), EcoDataCenter, Feb 11, 2026

- [EcoDataCenter 2 on the Power Map](https://siscto.si/power-map/ecodatacenter-2/), from [Epoch AI](https://epoch.ai/data/ai-data-centers), "AI data centers" (CC BY 4.0), retrieved November 10, 2026

More projects

## Keep reading the Ledger

Three more projects, the same operator first.

[The whole Ledger](https://siscto.si/ledger/)

### Colossus (Memphis and Southaven)

Memphis, Tennessee

2 GW announced · 1 to 1.7 GW

### Meta Hyperion

Richland Parish, Louisiana

2 GW announced · nothing confirmed

### Stargate Shackelford County (Frontier)

Shackelford County, Texas

1.4 GW announced · nothing confirmed