> SI compute announced against built: 14.8 GW announced, 3.3 to 4.25 GW confirmed energized across 18 projects. Every row has a source and a date.

Source: https://siscto.si/ledger/
Updated: 2026-11-11

1. [Home](https://siscto.si/)
2. Gigawatt Ledger

The Gigawatt Ledger · announced against built

# What was announced, and what is built

The Gigawatt Ledger sets what was announced for each SI compute project against what public evidence confirms as built. Today the 18 projects with a stated power figure add up to 14.8 GW announced, and 3.3 to 4.25 GW is confirmed energized: 22% to 29%. It follows 24 projects in 5 countries through 44 public announcements, each quoted in its own words with its date and its link.

Projects
:   24

Announced
:   14.8 GW

Confirmed, max
:   4.25 GW

Source links
:   37

The headline

## Announced against confirmed energized

One pair of numbers for the whole Ledger, with the method beside it. Both totals rest on stated power figures and dated public evidence, as of November 11, 2026.

Announced

14.8 GW

against

Confirmed energized

3.3 to 4.25 GW

22% to 29% confirmed energized (18 projects with a stated power figure, as of November 11, 2026)

How this is counted

- Announced is the sum of one figure for each project: the power or capacity its operator, a partner, a regulator, a utility or a filing states for it.

- Not counted: "up to" and "can scale to" figures (6.54 GW more across 5 projects), figures shared between sites, and figures only the press reports.

- Confirmed energized is the power public evidence shows running at those same projects, never more than the project's own announced figure.

- Like for like: IT load is set against IT load and total power against the whole facility. Where an announcement does not say which it means, both ends are shown as a range.

[Read the full method](https://siscto.si/ledger/method/)

By operator

## Who announced what, and what runs

Each bar is the announced power of one operator's projects in the Ledger. The green part is what public evidence confirms as energized.

OpenAI (6 projects)

7.08 GW · 1.15 GW

Meta (2 projects)

3 GW · 471 to 612 MW

SpaceXAI (1 project)

2 GW · 1 to 1.7 GW

Microsoft (1 project)

900 MW · none confirmed

CoreWeave (4 projects)

860 MW · 328 to 435 MW

Fluidstack (2 projects)

647 MW · 268 MW

Nscale (1 project)

230 MW · none confirmed

Nebius (1 project)

75 MW · 75 MW

Operators with a stated power figure. A project is filed under the company the compute is built for, or the company that runs the campus.

The Ledger

## All 24 projects

Filter by operator, by country or US state, and by state of the build. The totals follow what is shown. Open a project for its announcements, its evidence and its sources.

Projects shown
:   24

Announced
:   14.8 GW

Energized
:   3.3 to 4.25 GW

Share energized
:   22% to 29%

- [Colossus (Memphis and Southaven) (Memphis, Tennessee) · SpaceXAI · 2 GW (announced) · 1 to 1.7 GW (confirmed, Jun 15, 2026) · Partly energized](https://siscto.si/ledger/colossus-memphis/)

- [Meta Hyperion (Richland Parish, Louisiana) · Meta · 2 GW (announced) · Not confirmed (as of Apr 19, 2026) · Under construction](https://siscto.si/ledger/meta-hyperion/)

- [Stargate Shackelford County (Frontier) (Shackelford County, Texas) · OpenAI, Oracle, Vantage Data Centers · 1.4 GW (announced) · Not confirmed (as of Sep 4, 2026) · Under construction](https://siscto.si/ledger/stargate-shackelford-county/)

- [Stargate Michigan (Saline Township) (Saline Township, Michigan) · OpenAI, Oracle, Related Digital · 1.38 GW (announced) · Not confirmed (as of Mar 12, 2026) · Under construction](https://siscto.si/ledger/stargate-michigan/)

- [Stargate Abilene (Abilene, Texas) · OpenAI, Oracle, Crusoe · 1.2 GW (announced) · 1.15 GW (confirmed, Nov 1, 2026) · Energized](https://siscto.si/ledger/stargate-abilene/)

- [Stargate Milam County (Milam County, Texas) · OpenAI, SoftBank, SB Energy · 1.2 GW (announced) · Not confirmed (as of Mar 23, 2026) · Under construction](https://siscto.si/ledger/stargate-milam-county/)

- [Meta Prometheus (New Albany, Ohio) · Meta · 1 GW (announced) · 471 to 612 MW (confirmed, Aug 31, 2026) · Partly energized](https://siscto.si/ledger/meta-prometheus/)

- [Stargate UAE (Abu Dhabi, United Arab Emirates) · OpenAI, G42, Oracle · 1 GW (announced) · Not confirmed (as of Nov 16, 2025) · Under construction](https://siscto.si/ledger/stargate-uae/)

- [Stargate Wisconsin (Port Washington, Lighthouse) (Port Washington, Wisconsin) · OpenAI, Oracle, Vantage Data Centers · 902 MW (announced) · Not confirmed (as of Jul 24, 2026) · Under construction](https://siscto.si/ledger/stargate-port-washington/)

- [Abilene campus for Microsoft (Abilene, Texas) · Microsoft, Crusoe · 900 MW (announced) · Not confirmed (as of Jan 15, 2026) · Under construction](https://siscto.si/ledger/abilene-microsoft-campus/)

- [Lake Mariner (Barker, New York) · Fluidstack, TeraWulf, Core42, Anthropic · 440 MW (announced) · 268 MW (confirmed, Oct 31, 2026) · Partly energized](https://siscto.si/ledger/lake-mariner/)

- [Polaris Forge 1 (Ellendale, North Dakota) · CoreWeave, Applied Digital · 400 MW (announced) · 68 to 175 MW (confirmed, Jun 30, 2026) · Partly energized](https://siscto.si/ledger/polaris-forge-1/)

- [Denton (Denton, Texas) · CoreWeave, Core Scientific · 260 MW (announced) · 262 MW (confirmed, Sep 1, 2026) · Energized](https://siscto.si/ledger/denton/)

- [Stargate Norway (Narvik) (Narvik, Nordland, Norway) · Nscale, Aker, OpenAI, Microsoft · 230 MW (announced) · Not confirmed (as of Jul 5, 2026) · Under construction](https://siscto.si/ledger/stargate-norway-narvik/)

- [Barber Lake (Colorado City, Texas) · Fluidstack, Cipher Mining, Anthropic · 207 MW (announced) · Not confirmed (as of Jul 30, 2026) · Delayed](https://siscto.si/ledger/barber-lake/)

- [Lancaster (Lancaster, Pennsylvania) · CoreWeave, Chirisa Technology Parks, Machine Investment Group · 100 MW (announced) · Not confirmed (as of Jul 13, 2026) · Under construction](https://siscto.si/ledger/lancaster/)

- [Muskogee (Muskogee, Oklahoma) · CoreWeave, Core Scientific · 100 MW (announced) · Not confirmed (as of Jun 13, 2026) · Under construction](https://siscto.si/ledger/muskogee/)

- [Nebius Mäntsälä (Mäntsälä, Uusimaa, Finland) · Nebius · 75 MW (announced) · 75 to 90 MW (confirmed, Jun 29, 2026) · Energized](https://siscto.si/ledger/nebius-mantsala/)

- [Project Rainier, New Carlisle (New Carlisle, Indiana) · Amazon, Anthropic · Not stated (announced) · 1,037 MW IT (confirmed, Oct 19, 2026) · Partly energized](https://siscto.si/ledger/project-rainier-new-carlisle/)

- [Microsoft Fairwater Atlanta (Fayetteville, Georgia) · Microsoft · Not stated (announced) · 636 MW IT (confirmed, Jun 14, 2026) · Energized](https://siscto.si/ledger/microsoft-fairwater-atlanta/)

- [Microsoft Fairwater Wisconsin (Mount Pleasant, Wisconsin) · Microsoft · Not stated (announced) · 369 MW IT (confirmed, May 15, 2026) · Partly energized](https://siscto.si/ledger/microsoft-fairwater-wisconsin/)

- [EcoDataCenter 2, Borlänge (Borlänge, Dalarna County, Sweden) · Mistral AI, EcoDataCenter · Not stated (announced) · Not confirmed (as of Aug 17, 2026) · Under construction](https://siscto.si/ledger/ecodatacenter-2-borlange/)

- [Stargate Doña Ana County (Project Jupiter) (Doña Ana County, New Mexico) · OpenAI, Oracle, BorderPlex Digital Assets, STACK Infrastructure · Not stated (announced) · Not confirmed (as of Jun 22, 2026) · Under construction](https://siscto.si/ledger/stargate-dona-ana-county/)

- [Stargate Lordstown (Lordstown, Ohio) · OpenAI, SoftBank · Not stated (announced) · Not confirmed (as of Jul 30, 2026) · Under construction](https://siscto.si/ledger/stargate-lordstown/)

Built evidence: Epoch AI, "AI data centers" (CC BY 4.0), retrieved November 10, 2026, plus the linked statements and filings. Announcements read on November 11, 2026.

The states

## Six states, each with its evidence

Every project is in exactly one state, and its page says what evidence put it there.

A public announcement exists and no public evidence of construction has been read.

0 projects today

Work on the ground is confirmed and nothing is confirmed as running yet.

13 projects today

Part of the announced power is confirmed as running.

6 projects today

Public evidence puts the running power at 95% or more of the announced figure, or shows every building running where no figure was stated.

4 projects today

Nothing is running, a promised date has passed, and a linked source shows it was not met.

1 project today

A linked source says the project was dropped.

0 projects today

Use it

## Download, embed, cite

The Ledger is made to be quoted. Take the data, put the live headline in an article, or cite it with its date.

### The dataset

Every project, announcement and evidence row with its source link and date.

[JSON](https://siscto.si/assets/data/gigawatt-ledger.json)

[Projects CSV](https://siscto.si/assets/data/gigawatt-ledger-projects.csv)

[Rows CSV](https://siscto.si/assets/data/gigawatt-ledger-rows.csv)

Reuse with credit and a link to siscto.si/ledger/. Epoch AI's figures are theirs under CC BY 4.0.

### Embed for reporters

The headline and the chart in a frame that follows the data. Paste this where your article takes HTML.

[See the embed](https://siscto.si/ledger/embed/)

### Cite this

Give the date with the numbers: they move as buildings come on line.

[The dated method](https://siscto.si/ledger/method/)

Reality Check · fourth quarter 2026

### The quarter in one page

Each quarter the Ledger is summed up from its own data: the headline, the operators, the widest gaps and the promises that came due. The first one is dated November 11, 2026.

[Read the Reality Check](https://siscto.si/ledger/reality-check/2026-q4/)

See the sites

## On the map, and from orbit

The Ledger counts. The Power Map and Compute Watch show the same sites on the ground.

### The Power Map

Every SI data center that public data confirms, on one world map, with the dated timeline behind each Ledger figure.

### Compute Watch

The newest clear satellite pass over seven of the largest builds, read by SI MIND and sealed on Solana.

Questions

### Heat Watch

Every site's summer land heat from NASA's MODIS satellites against the land 5 to 10 km around it: +0.5 °C on average by day over the last three summers. One public signal, next to what is built.

[See the heat](https://siscto.si/heat-watch/)

### SI Next Door

Enter a ZIP code to see the SI data centers within reach, builds on the way, hearings, your state's home power price and sourced facts on what data center demand adds to costs.

[Look up your ZIP code](https://siscto.si/next-door/)

### Lights On

NASA's night-light imagery over all 96 sites, month by month since 2018, beside what is announced and what is built. In October 2026, 66 of 96 sites were brighter than a year before. Light is one public signal, never proof a site is running.

[See the lights](https://siscto.si/lights-on/)

## The Gigawatt Ledger, answered

What counts as announced, what counts as built and how to correct a row.

### What is the Gigawatt Ledger?

A public ledger of SI compute projects that sets what was announced against what can be verified as built. Each project lists its public announcements, each with who said it, the power or capacity stated, the promised date and a link, and next to them the public evidence of what is running today. It covers 24 projects from 5 countries, and every row has a source.

### Where do the announced figures come from?

From the announcement itself: a company page or release, a regulator, a utility or a public filing, quoted in its own words and its own unit. A figure counts toward the total only when the source states it as the project's planned or contracted power or capacity. Figures given as "up to", "potential" or "can scale to" are listed on the project page and left out of the total, and so are figures that only the press reports.

### What counts as confirmed energized?

Power that public evidence shows in operation. The main evidence is [Epoch AI](https://epoch.ai/data/ai-data-centers)'s public tracker, which dates each building that starts running from satellite images, permits and company statements, the same data the [Power Map](https://siscto.si/power-map/) draws. A company statement, a utility statement or a filing that states live power is used too, with its link. Where [Compute Watch](https://siscto.si/compute/) follows a site, its newest satellite pass is on the project page.

### Why is the confirmed figure a range?

Because announcements do not always say what their number measures. A campus announced at 1 GW may mean the power for the computers or the power for the whole site, cooling included. Where the announcement states IT load, the Ledger compares IT load, and where it states total power it compares the whole facility. Where it says neither, the low end is the IT load in operation and the high end is the whole facility, and both are shown.

### What do the six states mean?

Announced: no construction evidence has been read. Under construction: work is confirmed and nothing runs yet. Partly energized: part of the announced power runs. Energized: 95% or more runs. Delayed: nothing runs, a promised date has passed and a linked source shows it was not met. Cancelled: a linked source says the project was dropped. Each project page states the evidence for its state.

### Why are some projects not in the total?

A project joins the total only when a source states a power figure for it alone. A project announced with money and dates but no power, or with a figure shared between several sites, is on the Ledger with everything that is known and shows "not stated" where a number would be. Nothing is guessed to fill the gap.

### How do I correct a row?

Open the project page, sign in with your SI Passport and file a correction with a link to a public source. The team reads the source before anything changes, and approved corrections show on the page with their date. If your Passport carries an Org check, the page shows it, and an organization correcting its own project is labeled as such.

### Can I reuse the data?

Yes, with credit and a link to siscto.si/ledger/. The Ledger downloads as JSON and CSV, there is an embed for articles and a line to cite. The figures taken from Epoch AI are Epoch AI's, published under CC BY 4.0, so credit Epoch AI for those.