# Lake Mariner: Announced vs Built | Gigawatt Ledger

> Lake Mariner in Barker, New York: 440 MW announced, 268 MW confirmed energized as of Oct 31, 2026. Every announcement and the evidence, with sources.

Source: https://siscto.si/ledger/lake-mariner/
Updated: 2026-11-11

1. [Home](https://siscto.si/)
2. [Gigawatt Ledger](https://siscto.si/ledger/)
3. Lake Mariner

Gigawatt Ledger · Partly energized

# Lake Mariner, announced against built

Lake Mariner is an SI compute project in Barker, New York, by Fluidstack, TeraWulf, Core42 and Anthropic. The announced figure is 440 critical IT MW under lease (380 MW and 60 MW), from TeraWulf (Feb 26, 2026). Public evidence puts 268 MW in operation as of October 31, 2026, against 440 MW announced: 61%. The announcement states IT load, so it is set against the IT load running. Its state today: partly energized.

Announced
:   440 MW

Energized
:   268 MW (Oct 31, 2026)

State
:   Partly energized

Source links
:   4

Announced

## What was said, and when

Each row is one public announcement about Lake Mariner: who said it, the power or capacity it states in its own unit, the promised date, and the link. Company claims are quoted as claims.

**Nov 12, 2025**

Anthropic

### [Anthropic invests $50 billion in American AI infrastructure](https://www.anthropic.com/news/anthropic-invests-50-billion-in-american-ai-infrastructure)

Anthropic announces data centers with Fluidstack in Texas and New York. It names no site and states no power figure.

> “a $50 billion investment in American computing infrastructure”

> “with sites coming online throughout 2026”

Power or capacity stated
:   None stated

Promised
:   Sites online throughout 2026

**Feb 26, 2026**

TeraWulf

### [TeraWulf Reports Fourth Quarter and Full Year 2025 Results](https://investors.terawulf.com/news-events/press-releases/detail/132/terawulf-reports-fourth-quarter-and-full-year-2025-results)

TeraWulf lists its leases at the Lake Mariner campus (380 critical IT MW with Fluidstack, 60 with Core42) and the date each building is expected to be energized.

> “39 critical IT MW HPC capacity online”

> “more than 500 MW of near-term contracted campus capacity”

> “Energization expected Q3 2026”

> “Energization expected Q4 2026”

Power or capacity stated
:   440 critical IT MW under lease (380 MW Fluidstack, 60 MW Core42)

Promised
:   Buildings energized from March 2026 to the fourth quarter of 2026

Built

## What public evidence confirms

What is on the ground today, from the Power Map data and from any statement or filing that states live power.

Public evidence puts 268 MW in operation as of October 31, 2026, against 440 MW announced: 61%. The announcement states IT load, so it is set against the IT load running.

**Oct 31, 2026**

Epoch AI · Power Map

### Anthropic Lake Mariner on the Power Map

Epoch AI counts 2 buildings operating at Anthropic Lake Mariner and estimates 210 MW of IT power (245 MW for the whole facility) as of October 31, 2026.

> Building 2 (AKA CB4) is operational. On February 26, Terawulf [stated](https://investors.terawulf.com/news-events/press-releases/detail/132/terawulf-reports-fourth-quarter-and-full-year-2025-results) that CB4 was expected to be energized by Q3 2026.

IT power running
:   210 MW

Whole facility
:   245 MW

Epoch AI projects 378 MW of IT power by March 31, 2027. A projection, not a fact yet.

**Jul 23, 2026**

Epoch AI · Power Map

### Core42 Lake Mariner on the Power Map

Epoch AI counts 2 buildings operating at Core42 Lake Mariner and estimates 58 MW of IT power (58 MW for the whole facility) as of July 23, 2026.

> Both buildings still operational according to satellite imagery.

IT power running
:   58 MW

Whole facility
:   58 MW

Timeline

### Heat Watch

Over the last three summers NASA's MODIS read the ground here +1.2 °C against the land 5 to 10 km around it by day.

[Open Heat Watch](https://siscto.si/heat-watch/anthropic-lake-mariner/)

### Heat Watch

Over the last three summers NASA's MODIS read the ground here +1.3 °C against the land 5 to 10 km around it by day.

[Open Heat Watch](https://siscto.si/heat-watch/core42-lake-mariner/)

## Announcements and evidence, by date

What was promised and what was seen, in the order it became public. The full dated record of each site is on its Power Map page.

**Oct 1, 2025**

Core42 Lake Mariner: 1 building operating, 16 MW of IT power. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/core42-lake-mariner/))

**Nov 12, 2025**

Anthropic: no power figure stated. Promised: sites online throughout 2026. (Announcement · [Anthropic](https://www.anthropic.com/news/anthropic-invests-50-billion-in-american-ai-infrastructure))

**Feb 26, 2026**

TeraWulf: 440 critical IT MW under lease (380 MW Fluidstack, 60 MW Core42). Promised: buildings energized from March 2026 to the fourth quarter of 2026. (Announcement · [TeraWulf](https://investors.terawulf.com/news-events/press-releases/detail/132/terawulf-reports-fourth-quarter-and-full-year-2025-results))

**Mar 2, 2026**

Anthropic Lake Mariner: 0 buildings operating, no IT power yet. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/anthropic-lake-mariner/))

**Mar 2, 2026**

Core42 Lake Mariner: 1 building operating, 16 MW of IT power. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/core42-lake-mariner/))

**Mar 31, 2026**

Core42 Lake Mariner: 2 buildings operating, 58 MW of IT power. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/core42-lake-mariner/))

**May 31, 2026**

Anthropic Lake Mariner: 1 building operating, 42 MW of IT power. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/anthropic-lake-mariner/))

**Jul 23, 2026**

Anthropic Lake Mariner: 1 building operating, 42 MW of IT power. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/anthropic-lake-mariner/))

**Jul 23, 2026**

Core42 Lake Mariner: 2 buildings operating, 58 MW of IT power. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/core42-lake-mariner/))

**Oct 31, 2026**

Anthropic Lake Mariner: 2 buildings operating, 210 MW of IT power. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/anthropic-lake-mariner/))

Corrections

## See something wrong? File a correction

Sign in with your SI Passport and say what is wrong, with a link to a public source. The team reads the source before anything changes, and approved corrections stay on this page.

### File a correction

A correction needs a link. Nothing shows until the team approves it. If your Passport carries an Org check it shows here, and an organization correcting its own project is labeled as such.

Corrections on file · 0

Sources

## Every link behind this page

Read on November 11, 2026. An undated page carries the date it was read.

- [Anthropic invests $50 billion in American AI infrastructure](https://www.anthropic.com/news/anthropic-invests-50-billion-in-american-ai-infrastructure), Anthropic, Nov 12, 2025

- [TeraWulf Reports Fourth Quarter and Full Year 2025 Results](https://investors.terawulf.com/news-events/press-releases/detail/132/terawulf-reports-fourth-quarter-and-full-year-2025-results), TeraWulf, Feb 26, 2026

- [Anthropic Lake Mariner on the Power Map](https://siscto.si/power-map/anthropic-lake-mariner/), from [Epoch AI](https://epoch.ai/data/ai-data-centers), "AI data centers" (CC BY 4.0), retrieved November 10, 2026

- [Core42 Lake Mariner on the Power Map](https://siscto.si/power-map/core42-lake-mariner/), from [Epoch AI](https://epoch.ai/data/ai-data-centers), "AI data centers" (CC BY 4.0), retrieved November 10, 2026

More projects

## Keep reading the Ledger

Three more projects, the same operator first.

[The whole Ledger](https://siscto.si/ledger/)

### Barber Lake

Colorado City, Texas

207 MW announced · nothing confirmed

### Colossus (Memphis and Southaven)

Memphis, Tennessee

2 GW announced · 1 to 1.7 GW

### Meta Hyperion

Richland Parish, Louisiana

2 GW announced · nothing confirmed