# Microsoft Fairwater Atlanta: Announced vs Built | $SIS

> Microsoft Fairwater Atlanta in Fayetteville, Georgia: no power figure stated; Epoch AI estimates 636 MW of IT power running as of Jun 14, 2026. Sourced.

Source: https://siscto.si/ledger/microsoft-fairwater-atlanta/
Updated: 2026-11-11

1. [Home](https://siscto.si/)
2. [Gigawatt Ledger](https://siscto.si/ledger/)
3. Microsoft Fairwater Atlanta

Gigawatt Ledger · Energized

# Microsoft Fairwater Atlanta, announced against built

Microsoft Fairwater Atlanta is an SI compute project in Fayetteville, Georgia, by Microsoft. No source states a power figure for this project alone, so it is not in the Ledger's total. No power figure was announced. Epoch AI estimates 636 MW of IT power in operation (859 MW for the whole facility) as of June 14, 2026. Its state today: energized.

Announced
:   Not stated

Energized
:   636 MW IT (Jun 14, 2026)

State
:   Energized

Source links
:   2

Announced

## What was said, and when

Each row is one public announcement about Microsoft Fairwater Atlanta: who said it, the power or capacity it states in its own unit, the promised date, and the link. Company claims are quoted as claims.

**Nov 12, 2025**

Microsoft

### [Infinite scale: The architecture behind the Azure AI superfactory](https://blogs.microsoft.com/blog/2025/11/12/infinite-scale-the-architecture-behind-the-azure-ai-superfactory/)

Microsoft unveils its Fairwater site in Atlanta, Georgia. It states no power figure for the site.

> “Today, we are unveiling the next Fairwater site of Azure AI datacenters in Atlanta, Georgia.”

Power or capacity stated
:   None stated

Promised
:   None stated

Built

## What public evidence confirms

What is on the ground today, from the Power Map data and from any statement or filing that states live power.

No power figure was announced. Epoch AI estimates 636 MW of IT power in operation (859 MW for the whole facility) as of June 14, 2026.

**Jun 14, 2026**

Epoch AI · Power Map

### Microsoft Fairwater Atlanta on the Power Map

Epoch AI counts 4 buildings operating at Microsoft Fairwater Atlanta and estimates 636 MW of IT power (859 MW for the whole facility) as of June 14, 2026.

> Building 3 and 4 are operational.

IT power running
:   636 MW

Whole facility
:   859 MW

Timeline

### Heat Watch

Over the last three summers NASA's MODIS read the ground here -0.2 °C against the land 5 to 10 km around it by day.

[Open Heat Watch](https://siscto.si/heat-watch/microsoft-fairwater-atlanta/)

## Announcements and evidence, by date

What was promised and what was seen, in the order it became public. The full dated record of each site is on its Power Map page.

**Oct 14, 2025**

Microsoft Fairwater Atlanta: 2 buildings operating, 321 MW of IT power. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/microsoft-fairwater-atlanta/))

**Nov 12, 2025**

Microsoft: no power figure stated. (Announcement · [The Official Microsoft Blog](https://blogs.microsoft.com/blog/2025/11/12/infinite-scale-the-architecture-behind-the-azure-ai-superfactory/))

**Feb 13, 2026**

Microsoft Fairwater Atlanta: 2 buildings operating, 321 MW of IT power. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/microsoft-fairwater-atlanta/))

**May 15, 2026**

Microsoft Fairwater Atlanta: 2 buildings operating, 321 MW of IT power. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/microsoft-fairwater-atlanta/))

**Jun 14, 2026**

Microsoft Fairwater Atlanta: 4 buildings operating, 636 MW of IT power. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/microsoft-fairwater-atlanta/))

Corrections

## See something wrong? File a correction

Sign in with your SI Passport and say what is wrong, with a link to a public source. The team reads the source before anything changes, and approved corrections stay on this page.

### File a correction

A correction needs a link. Nothing shows until the team approves it. If your Passport carries an Org check it shows here, and an organization correcting its own project is labeled as such.

Corrections on file · 0

Sources

## Every link behind this page

Read on November 11, 2026. An undated page carries the date it was read.

- [Infinite scale: The architecture behind the Azure AI superfactory](https://blogs.microsoft.com/blog/2025/11/12/infinite-scale-the-architecture-behind-the-azure-ai-superfactory/), The Official Microsoft Blog, Nov 12, 2025

- [Microsoft Fairwater Atlanta on the Power Map](https://siscto.si/power-map/microsoft-fairwater-atlanta/), from [Epoch AI](https://epoch.ai/data/ai-data-centers), "AI data centers" (CC BY 4.0), retrieved November 10, 2026

More projects

## Keep reading the Ledger

Three more projects, the same operator first.

[The whole Ledger](https://siscto.si/ledger/)

### Abilene campus for Microsoft

Abilene, Texas

900 MW announced · nothing confirmed

### Microsoft Fairwater Wisconsin

Mount Pleasant, Wisconsin

No power figure stated · 369 MW IT

### Colossus (Memphis and Southaven)

Memphis, Tennessee

2 GW announced · 1 to 1.7 GW