# Muskogee: Announced vs Built | Gigawatt Ledger

> Muskogee in Muskogee, Oklahoma: 100 MW announced, nothing confirmed energized as of Jun 13, 2026. Every announcement and the evidence, with sources.

Source: https://siscto.si/ledger/muskogee/
Updated: 2026-11-11

1. [Home](https://siscto.si/)
2. [Gigawatt Ledger](https://siscto.si/ledger/)
3. Muskogee

Gigawatt Ledger · Under construction

# Muskogee, announced against built

Muskogee is an SI compute project in Muskogee, Oklahoma, by CoreWeave and Core Scientific. The announced figure is 100 MW facility (about 70 MW of critical IT load), from Core Scientific (Nov 18, 2024). Epoch AI tracks the site as under construction, with no building operating as of June 13, 2026. Its state today: under construction.

Announced
:   100 MW

Energized
:   None (Jun 13, 2026)

State
:   Under construction

Source links
:   2

Announced

## What was said, and when

Each row is one public announcement about Muskogee: who said it, the power or capacity it states in its own unit, the promised date, and the link. Company claims are quoted as claims.

**Nov 18, 2024**

Core Scientific

### [Core Scientific and Port Muskogee Break Ground on 100 MW HPC Data Center](https://investors.corescientific.com/news-events/press-releases/detail/99/core-scientific-and-port-muskogee-break-ground-on-100-mw-hpc-data-center)

Core Scientific breaks ground on a facility that will host CoreWeave.

> “The 100-megawatt facility will host CoreWeave's NVIDIA GPUs for an undisclosed client.”

> “will provide approximately 70 MW of critical IT load”

> “The site is expected to be operational in 2026.”

Power or capacity stated
:   100 MW facility; about 70 MW of critical IT load

Promised
:   Operational in 2026

Built

## What public evidence confirms

What is on the ground today, from the Power Map data and from any statement or filing that states live power.

Epoch AI tracks the site as under construction, with no building operating as of June 13, 2026.

**Jun 13, 2026**

Epoch AI · Power Map

### CoreWeave Muskogee OK on the Power Map

Epoch AI tracks CoreWeave Muskogee OK as under construction: no building is operating as of June 13, 2026.

> Based on satellite imagery, Building 1 has completed construction, with adjacent land cleared for what we're assuming will have power substations/generators. We can assume Building 1 is not operational from all the yard work directly surrounding it, and the lack of a parking lot. Building 2 (The one not leased to CoreWeave) is still in land clearing phase.

IT power running
:   None

Whole facility
:   None

Epoch AI projects 153 MW of IT power by December 31, 2027. A projection, not a fact yet.

Timeline

### Heat Watch

Over the last three summers NASA's MODIS read the ground here 0.0 °C against the land 5 to 10 km around it by day.

[Open Heat Watch](https://siscto.si/heat-watch/coreweave-muskogee-ok/)

## Announcements and evidence, by date

What was promised and what was seen, in the order it became public. The full dated record of each site is on its Power Map page.

**Nov 18, 2024**

Core Scientific: 100 MW facility; about 70 MW of critical IT load. Promised: operational in 2026. (Announcement · [Core Scientific](https://investors.corescientific.com/news-events/press-releases/detail/99/core-scientific-and-port-muskogee-break-ground-on-100-mw-hpc-data-center))

**Nov 18, 2024**

CoreWeave Muskogee OK: 0 buildings operating, no IT power yet. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/coreweave-muskogee-ok/))

**Apr 9, 2026**

CoreWeave Muskogee OK: 0 buildings operating, no IT power yet. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/coreweave-muskogee-ok/))

**Jun 13, 2026**

CoreWeave Muskogee OK: 0 buildings operating, no IT power yet. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/coreweave-muskogee-ok/))

Corrections

## See something wrong? File a correction

Sign in with your SI Passport and say what is wrong, with a link to a public source. The team reads the source before anything changes, and approved corrections stay on this page.

### File a correction

A correction needs a link. Nothing shows until the team approves it. If your Passport carries an Org check it shows here, and an organization correcting its own project is labeled as such.

Corrections on file · 0

Sources

## Every link behind this page

Read on November 11, 2026. An undated page carries the date it was read.

- [Core Scientific and Port Muskogee Break Ground on 100 MW HPC Data Center](https://investors.corescientific.com/news-events/press-releases/detail/99/core-scientific-and-port-muskogee-break-ground-on-100-mw-hpc-data-center), Core Scientific, Nov 18, 2024

- [CoreWeave Muskogee OK on the Power Map](https://siscto.si/power-map/coreweave-muskogee-ok/), from [Epoch AI](https://epoch.ai/data/ai-data-centers), "AI data centers" (CC BY 4.0), retrieved November 10, 2026

More projects

## Keep reading the Ledger

Three more projects, the same operator first.

[The whole Ledger](https://siscto.si/ledger/)

### Polaris Forge 1

Ellendale, North Dakota

400 MW announced · 68 to 175 MW

### Denton

Denton, Texas

260 MW announced · 262 MW

### Lancaster

Lancaster, Pennsylvania

100 MW announced · nothing confirmed