# Polaris Forge 1: Announced vs Built | Gigawatt Ledger

> Polaris Forge 1 in Ellendale, North Dakota: 400 MW announced, 68 to 175 MW confirmed energized as of Jun 30, 2026. Announcements, evidence and sources.

Source: https://siscto.si/ledger/polaris-forge-1/
Updated: 2026-11-11

1. [Home](https://siscto.si/)
2. [Gigawatt Ledger](https://siscto.si/ledger/)
3. Polaris Forge 1

Gigawatt Ledger · Partly energized

# Polaris Forge 1, announced against built

Polaris Forge 1 is an SI compute project in Ellendale, North Dakota, by CoreWeave and Applied Digital. The announced figure is 400 MW of critical IT load under lease, from Applied Digital (Jul 1, 2026). Public evidence puts 68 to 175 MW in operation as of June 30, 2026, against 400 MW announced: 17% to 44%. The range covers every figure listed below. Its state today: partly energized.

Announced
:   400 MW

Energized
:   68 to 175 MW (Jun 30, 2026)

State
:   Partly energized

Source links
:   3

Announced

## What was said, and when

Each row is one public announcement about Polaris Forge 1: who said it, the power or capacity it states in its own unit, the promised date, and the link. Company claims are quoted as claims.

**Jun 2, 2025**

Applied Digital

### [Applied Digital Announces 250MW AI Data Center Lease With CoreWeave in North Dakota](https://ir.applieddigital.com/news-events/press-releases/detail/123/applied-digital-announces-250mw-ai-data-center-lease-with)

Applied Digital leases 250 MW of critical IT load to CoreWeave at its Ellendale campus, with an option on 150 MW more.

> “deliver 250 megawatts (MW) of critical IT load”

> “designed to host 400 MW of critical IT load”

> “designed to scale up to 1 gigawatt over time”

> “to be ready for service in the fourth quarter of calendar 2025”

> “is expected to be ready for service in the middle of 2026”

Power or capacity stated
:   250 MW of critical IT load, option on 150 MW more; campus designed for 400 MW

Promised
:   First 100 MW building in the fourth quarter of 2025; second building in the middle of 2026; third in 2027

**Jul 1, 2026**

Applied Digital

### [Applied Digital Delivers Second Building at Polaris Forge 1](https://ir.applieddigital.com/news-events/press-releases/detail/157/applied-digital-delivers-second-building-at-polaris-forge-1)

Applied Digital restates the full lease commitment at the campus.

> “contracted to deliver 400 MW of critical IT load”

Power or capacity stated
:   400 MW of critical IT load under lease

Promised
:   None stated

The larger figure, designed to scale up to 1 gigawatt over time (Applied Digital, Jun 2, 2025), is stated as an upper limit or an ambition. It is listed here and left out of the Ledger's total.

Built

## What public evidence confirms

What is on the ground today, from the Power Map data and from any statement or filing that states live power.

Public evidence puts 68 to 175 MW in operation as of June 30, 2026, against 400 MW announced: 17% to 44%. The range covers every figure listed below.

**Jun 30, 2026**

Epoch AI · Power Map

### CoreWeave Ellendale ND on the Power Map

Epoch AI counts 1 building operating at CoreWeave Ellendale ND and estimates 68 MW of IT power (88 MW for the whole facility) as of June 30, 2026.

> According to satellite imagery, Building 2 is fully roofed and shell complete, with rooftop chillers mostly installed. Building 3 construction is well underway, with about 1/4 of the roofing done and the foundation laid out.

IT power running
:   68 MW

Whole facility
:   88 MW

Epoch AI projects 400 MW of IT power by June 1, 2027. A projection, not a fact yet.

**Jul 1, 2026**

Applied Digital

### [Applied Digital Delivers Second Building at Polaris Forge 1](https://ir.applieddigital.com/news-events/press-releases/detail/157/applied-digital-delivers-second-building-at-polaris-forge-1)

The landlord says the first phase of the second building is ready for service and states the live capacity at the campus.

> “delivering 75 MW of operational AI capacity”

> “bringing total live capacity at the campus to 175 MW”

Power confirmed
:   175 MW

Used in the total
:   Yes

Timeline

### Heat Watch

Over the last three summers NASA's MODIS read the ground here +0.0 °C against the land 5 to 10 km around it by day.

[Open Heat Watch](https://siscto.si/heat-watch/coreweave-ellendale-nd/)

## Announcements and evidence, by date

What was promised and what was seen, in the order it became public. The full dated record of each site is on its Power Map page.

**Jun 2, 2025**

Applied Digital: 250 MW of critical IT load, option on 150 MW more; campus designed for 400 MW. Promised: first 100 MW building in the fourth quarter of 2025; second building in the middle of 2026; third in 2027. (Announcement · [Applied Digital](https://ir.applieddigital.com/news-events/press-releases/detail/123/applied-digital-announces-250mw-ai-data-center-lease-with))

**Oct 27, 2025**

CoreWeave Ellendale ND: 1 building operating, 50 MW of IT power. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/coreweave-ellendale-nd/))

**Nov 24, 2025**

CoreWeave Ellendale ND: 1 building operating, 68 MW of IT power. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/coreweave-ellendale-nd/))

**Mar 27, 2026**

CoreWeave Ellendale ND: 1 building operating, 68 MW of IT power. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/coreweave-ellendale-nd/))

**Jun 30, 2026**

CoreWeave Ellendale ND: 1 building operating, 68 MW of IT power. (Evidence · [Epoch AI, on the Power Map](https://siscto.si/power-map/coreweave-ellendale-nd/))

**Jul 1, 2026**

Applied Digital: 400 MW of critical IT load under lease. (Announcement · [Applied Digital](https://ir.applieddigital.com/news-events/press-releases/detail/157/applied-digital-delivers-second-building-at-polaris-forge-1))

**Jul 1, 2026**

The landlord says the first phase of the second building is ready for service and states the live capacity at the campus. (Evidence · [Applied Digital](https://ir.applieddigital.com/news-events/press-releases/detail/157/applied-digital-delivers-second-building-at-polaris-forge-1))

Corrections

## See something wrong? File a correction

Sign in with your SI Passport and say what is wrong, with a link to a public source. The team reads the source before anything changes, and approved corrections stay on this page.

### File a correction

A correction needs a link. Nothing shows until the team approves it. If your Passport carries an Org check it shows here, and an organization correcting its own project is labeled as such.

Corrections on file · 0

Sources

## Every link behind this page

Read on November 11, 2026. An undated page carries the date it was read.

- [Applied Digital Announces 250MW AI Data Center Lease With CoreWeave in North Dakota](https://ir.applieddigital.com/news-events/press-releases/detail/123/applied-digital-announces-250mw-ai-data-center-lease-with), Applied Digital, Jun 2, 2025

- [Applied Digital Delivers Second Building at Polaris Forge 1](https://ir.applieddigital.com/news-events/press-releases/detail/157/applied-digital-delivers-second-building-at-polaris-forge-1), Applied Digital, Jul 1, 2026

- [CoreWeave Ellendale ND on the Power Map](https://siscto.si/power-map/coreweave-ellendale-nd/), from [Epoch AI](https://epoch.ai/data/ai-data-centers), "AI data centers" (CC BY 4.0), retrieved November 10, 2026

More projects

## Keep reading the Ledger

Three more projects, the same operator first.

[The whole Ledger](https://siscto.si/ledger/)

### Denton

Denton, Texas

260 MW announced · 262 MW

### Lancaster

Lancaster, Pennsylvania

100 MW announced · nothing confirmed

### Muskogee

Muskogee, Oklahoma

100 MW announced · nothing confirmed