# Reality Check Q4 2026: SI Compute Announced vs Built | $SIS

> The Gigawatt Ledger summed up on November 11, 2026: 14.8 GW announced, 3.3 to 4.25 GW confirmed energized, by operator, with the gaps and the promises due.

Source: https://siscto.si/ledger/reality-check/2026-q4/
Updated: 2026-11-11

1. [Home](https://siscto.si/)
2. [Gigawatt Ledger](https://siscto.si/ledger/)
3. Reality Check Q4 2026

Gigawatt Ledger · Reality Check

# Reality Check, fourth quarter 2026

As of November 11, 2026, the 18 SI compute projects with a stated power figure add up to 14.8 GW announced. Public evidence confirms 3.3 to 4.25 GW energized, which is 22% to 29%. Of all 24 projects in the Ledger, 4 are energized, 6 partly energized, 13 under construction and 1 delayed. This page is generated from the Ledger's data, with nothing added by hand.

Announced
:   14.8 GW

Confirmed, min
:   3.3 GW

Confirmed, max
:   4.25 GW

Projects
:   24

The headline

## One pair of numbers

Announced power against confirmed energized power, for the projects with a stated figure, on November 11, 2026.

Announced

14.8 GW

against

Confirmed energized

3.3 to 4.25 GW

22% to 29% confirmed energized (18 projects with a stated power figure, as of November 11, 2026)

How this is counted

- Announced is the sum of one figure for each project: the power or capacity its operator, a partner, a regulator, a utility or a filing states for it.

- Not counted: "up to" and "can scale to" figures (6.54 GW more across 5 projects), figures shared between sites, and figures only the press reports.

- Confirmed energized is the power public evidence shows running at those same projects, never more than the project's own announced figure.

- Like for like: IT load is set against IT load and total power against the whole facility. Where an announcement does not say which it means, both ends are shown as a range.

[Read the full method](https://siscto.si/ledger/method/)

By operator

## Announced and confirmed, operator by operator

Projects are filed under the company the compute is built for, or the company that runs the campus.

- OpenAI · 6 projects · 7.08 GW · 1.15 GW · 16%

- Meta · 2 projects · 3 GW · 471 to 612 MW · 16% to 20%

- SpaceXAI · 1 project · 2 GW · 1 to 1.7 GW · 50% to 85%

- Microsoft · 1 project · 900 MW · None · 0%

- CoreWeave · 4 projects · 860 MW · 328 to 435 MW · 38% to 51%

- Fluidstack · 2 projects · 647 MW · 268 MW · 41%

- Nscale · 1 project · 230 MW · None · 0%

- Nebius · 1 project · 75 MW · 75 MW · 100%

The widest gaps

## Where the most is still to confirm

The six projects with the most announced power that public evidence does not yet show running, counted from the high end of the confirmed range.

- [Meta Hyperion](https://siscto.si/ledger/meta-hyperion/) · 2 GW · None · 2 GW · Under construction

- [Stargate Shackelford County (Frontier)](https://siscto.si/ledger/stargate-shackelford-county/) · 1.4 GW · None · 1.4 GW · Under construction

- [Stargate Michigan (Saline Township)](https://siscto.si/ledger/stargate-michigan/) · 1.38 GW · None · 1.38 GW · Under construction

- [Stargate Milam County](https://siscto.si/ledger/stargate-milam-county/) · 1.2 GW · None · 1.2 GW · Under construction

- [Stargate UAE](https://siscto.si/ledger/stargate-uae/) · 1 GW · None · 1 GW · Under construction

- [Stargate Wisconsin (Port Washington, Lighthouse)](https://siscto.si/ledger/stargate-port-washington/) · 902 MW · None · 902 MW · Under construction

Promises

## Dated promises, and where they stand

Every promise in the Ledger with a date through the end of 2026, next to the latest dated evidence. A promise is called not met only where a linked source shows it.

- [Colossus](https://siscto.si/ledger/colossus-memphis/) · 300 MW at the first site by December 2025 · [Memphis Light, Gas and Water](https://www.mlgw.com/images/content/files/pdf/new/5-5-25%20xAI%20Update.pdf), May 5, 2025 · Dec 31, 2025 · 1 to 1.7 GW running as of Jun 15, 2026

- [Microsoft Fairwater Wisconsin](https://siscto.si/ledger/microsoft-fairwater-wisconsin/) · Online in early 2026 · [Microsoft](https://blogs.microsoft.com/on-the-issues/2025/09/18/made-in-wisconsin-the-worlds-most-powerful-ai-datacenter/), Sep 18, 2025 · Mar 31, 2026 · 369 MW of IT power running as of May 15, 2026

- [Polaris Forge 1](https://siscto.si/ledger/polaris-forge-1/) · Second building ready for service in the middle of 2026 · [Applied Digital](https://ir.applieddigital.com/news-events/press-releases/detail/123/applied-digital-announces-250mw-ai-data-center-lease-with), Jun 2, 2025 · Jun 30, 2026 · 68 to 175 MW running as of Jun 30, 2026

- [Stargate Abilene](https://siscto.si/ledger/stargate-abilene/) · Six more buildings completed in mid-2026 · [Crusoe](https://www.crusoe.ai/resources/newsroom/crusoe-expands-ai-data-center-campus-in-abilene-to-1-2-gigawatts), Mar 18, 2025 · Jun 30, 2026 · 1.15 GW running as of Nov 1, 2026

- [Barber Lake](https://siscto.si/ledger/barber-lake/) · 168 MW of critical IT load delivered by September 2026 · [Cipher Mining](https://www.globenewswire.com/news-release/2025/09/25/3156107/0/en/Cipher-Mining-Signs-168-MW-10-Year-AI-Hosting-Agreement-with-Fluidstack.html), Sep 25, 2025 · Sep 30, 2026 · Not met: delayed, per the linked evidence

- [Lake Mariner](https://siscto.si/ledger/lake-mariner/) · Buildings energized through the fourth quarter of 2026 · [TeraWulf](https://investors.terawulf.com/news-events/press-releases/detail/132/terawulf-reports-fourth-quarter-and-full-year-2025-results), Feb 26, 2026 · Dec 31, 2026 · 268 MW running as of Oct 31, 2026

- [Meta Prometheus](https://siscto.si/ledger/meta-prometheus/) · 1 GW online in 2026 · [Mark Zuckerberg, reported by TechCrunch](https://techcrunch.com/2025/07/14/mark-zuckerberg-says-meta-is-building-a-5gw-ai-data-center), Jul 14, 2025 · Dec 31, 2026 · 471 to 612 MW running as of Aug 31, 2026

- [Muskogee](https://siscto.si/ledger/muskogee/) · Operational in 2026 · [Core Scientific](https://investors.corescientific.com/news-events/press-releases/detail/99/core-scientific-and-port-muskogee-break-ground-on-100-mw-hpc-data-center), Nov 18, 2024 · Dec 31, 2026 · Nothing confirmed as running as of Jun 13, 2026, and the date has not passed

- [Stargate Abilene](https://siscto.si/ledger/stargate-abilene/) · Second phase complete by the end of 2026 · [Crusoe](https://www.crusoe.ai/resources/newsroom/crusoe-announces-new-900-mw-ai-factory-campus-in-abilene-texas-to-support-microsoft-ai-infrastructure), Mar 27, 2026 · Dec 31, 2026 · 1.15 GW running as of Nov 1, 2026

- [Stargate Lordstown](https://siscto.si/ledger/stargate-lordstown/) · Operational in 2026 · [OpenAI, Oracle and SoftBank](https://openai.com/index/five-new-stargate-sites/), Sep 23, 2025 · Dec 31, 2026 · Nothing confirmed as running as of Jul 30, 2026, and the date has not passed

- [Stargate Shackelford County](https://siscto.si/ledger/stargate-shackelford-county/) · First data center delivered in the second half of 2026 · [Vantage Data Centers](https://vantage-dc.com/data-center-locations/north-america/shackelford-county-tx), Nov 11, 2026 · Dec 31, 2026 · Nothing confirmed as running as of Sep 4, 2026, and the date has not passed

- [Stargate UAE](https://siscto.si/ledger/stargate-uae/) · 200 MW live in 2026 · [OpenAI](https://openai.com/index/introducing-stargate-uae), Nov 11, 2026 · Dec 31, 2026 · Nothing confirmed as running as of Nov 16, 2025, and the date has not passed

Dates that moved

## Schedules the record shows changing

Only changes that two linked sources show, in their own words.

- [Stargate Abilene](https://siscto.si/ledger/stargate-abilene/): Crusoe first said the six buildings of the second phase were expected to be completed in mid-2026. Its March 27, 2026 release says the second phase is expected to reach completion by the end of 2026.

- [Barber Lake](https://siscto.si/ledger/barber-lake/): Cipher said it expected to deliver 168 MW of critical IT load by September 2026. Epoch AI's entry of July 30, 2026 reads "still under construction and not yet energized", and Epoch AI estimates the first phase for about December 2026, "about 3 months later than the disclosed target".

Not in the total

## Projects with no stated power figure

On the Ledger with everything that is known, and outside the headline.

- [Project Rainier, New Carlisle](https://siscto.si/ledger/project-rainier-new-carlisle/): No power figure was announced. Epoch AI estimates 1,037 MW of IT power in operation (1,244 MW for the whole facility) as of October 19, 2026, with more capacity on its timeline.

- [Microsoft Fairwater Atlanta](https://siscto.si/ledger/microsoft-fairwater-atlanta/): No power figure was announced. Epoch AI estimates 636 MW of IT power in operation (859 MW for the whole facility) as of June 14, 2026.

- [Microsoft Fairwater Wisconsin](https://siscto.si/ledger/microsoft-fairwater-wisconsin/): No power figure was announced. Epoch AI estimates 369 MW of IT power in operation (442 MW for the whole facility) as of May 15, 2026, with more capacity on its timeline.

- [EcoDataCenter 2, Borlänge](https://siscto.si/ledger/ecodatacenter-2-borlange/): Epoch AI tracks the site as under construction, with no building operating as of August 17, 2026.

- [Stargate Doña Ana County (Project Jupiter)](https://siscto.si/ledger/stargate-dona-ana-county/): Epoch AI tracks the site as under construction, with no building operating as of June 22, 2026.

- [Stargate Lordstown](https://siscto.si/ledger/stargate-lordstown/): Epoch AI tracks the site as under construction, with no building operating as of July 30, 2026.

The Gigawatt Ledger

### Every project, every source

Open the Ledger for the full list, the filters, the dataset and the method behind these numbers.

[Open the Ledger](https://siscto.si/ledger/)

[Read the method](https://siscto.si/ledger/method/)