> Colossus 1 gas turbines: up to 247 MW of gas power for xAI's Colossus 1 data center, permitted. The permit or filing behind it, dated and linked.

Source: https://siscto.si/onsite-power/colossus-1-turbines/
Updated: 2026-11-26

1. [Home](https://siscto.si/)
2. [Onsite Power Watch](https://siscto.si/onsite-power/)
3. Colossus 1 gas turbines

Onsite Power Watch · Gas

# Colossus 1 gas turbines

Colossus 1 gas turbines: 15 Solar SMT-130 gas turbines, up to 247 MW. It serves xAI's Colossus 1 data center, Memphis, Tennessee. Status: permitted, as of July 2, 2025. Air permit from the Shelby County Health Department, issued July 2, 2025, for 15 turbines.

Size
:   [up to 247 MW](https://siscto.si/onsite-power/colossus-1-turbines/#facts)

Fuel
:   [Gas](https://siscto.si/onsite-power/#totals)

Status
:   [Permitted](https://siscto.si/onsite-power/colossus-1-turbines/#filing)

As of
:   [Jul 2, 2025](https://siscto.si/onsite-power/colossus-1-turbines/#sources)

The facts

## What the public record shows

On site, behind the meter or beside the campus. Each fact below names its source.

- The Shelby County Health Department issued the permit on July 2, 2025, for 15 Solar SMT-130 turbines with up to 247 MW (TechCrunch, July 3, 2025).

- Epoch AI's record of the site, which the Power Map uses, lists the July 2025 turbine permit among its sources.

The filing

## The permit or filing behind it

The regulator's decision or the owner's filing that the status rests on.

Permitted · Jul 2, 2025

Air permit from the Shelby County Health Department, issued July 2, 2025, for 15 turbines.

[Open the filing](https://techcrunch.com/2025/07/03/xai-gets-permits-for-15-natural-gas-generators-at-memphis-data-center)

The site

## The data center it serves

Linked to the Power Map only where a source ties the two.

[Colossus 1](https://siscto.si/power-map/colossus-1/) on the Power Map: Memphis, Tennessee.

Sources

## Where every fact comes from

Each source was opened and read on November 23, 2026.

Jul 3, 2025, read Nov 23, 2026

### TechCrunch

xAI gets permits for 15 natural gas generators at Memphis data center

[Open the source](https://techcrunch.com/2025/07/03/xai-gets-permits-for-15-natural-gas-generators-at-memphis-data-center)

retrieved Nov 10, 2026

### Epoch AI

The Power Map's site list, towns, status and power come from Epoch AI's open data set of data centers, licensed CC BY 4.0.

[Open the source](https://epoch.ai/data/ai-data-centers)

Keep going

## The grid around it

The same place, other records.

### The Queue: Southeast

How much power data centers are asking Southeast for.

### Onsite Power Watch

Every plant built to run a data center directly.

### Grid Watch

Live demand on the grids that host the most sites.

### Gigawatt Ledger

What was announced against what is confirmed energized.

Questions

## Colossus 1 gas turbines, answered

The plant, its status and the sources.

### What is Colossus 1 gas turbines?

15 Solar SMT-130 gas turbines, up to 247 MW, built to serve xAI's Colossus 1 data center, Memphis, Tennessee. On site, behind the meter or beside the campus.

### What is its status?

Permitted, as of July 2, 2025: Air permit from the Shelby County Health Department, issued July 2, 2025, for 15 turbines.

### Where do the facts come from?

From the sources listed on this page, each opened and read on November 23, 2026. The Shelby County Health Department issued the permit on July 2, 2025, for 15 Solar SMT-130 turbines with up to 247 MW (TechCrunch, July 3, 2025).

Join the takeover

## Watch the plants with us

Found a newer permit or filing for this plant? Bring it to the $SIS Telegram with its link.

[Buy $SIS](https://pump.fun/coin/FdKdpz11GsTofLaNiddrhxrsE4APZYSSfLFqQ9YKpump)

[Join the Telegram](https://t.me/sisctotg)

[Follow on X](https://x.com/entersiscto)

[Swap on Jupiter](https://jup.ag/swap/SOL-FdKdpz11GsTofLaNiddrhxrsE4APZYSSfLFqQ9YKpump)