Onsite Power Watch · Nuclear

# Crane Clean Energy Center, Microsoft agreement

Crane Clean Energy Center, Microsoft agreement: restart of the former Three Mile Island Unit 1, 835 MW. It serves Microsoft, under a power purchase agreement (no single data center named). Status: building, as of the plant page read Nov 23, 2026. Constellation's plant page: restart expected in 2027, subject to Nuclear Regulatory Commission approval.

Size
:   [835 MW](https://siscto.si/onsite-power/crane-microsoft/#facts)

Fuel
:   [Nuclear](https://siscto.si/onsite-power/#totals)

Status
:   [Building](https://siscto.si/onsite-power/crane-microsoft/#filing)

As of
:   [Nov 23, 2026](https://siscto.si/onsite-power/crane-microsoft/#sources)

The facts

## What the public record shows

An existing or restarting nuclear plant under an agreement. Each fact below names its source.

- Constellation is restoring the 835 MW unit for Microsoft under what it calls its largest power purchase agreement, with the plant expected online in 2027 (Constellation, plant page read November 23, 2026).

- The restart needs Nuclear Regulatory Commission approval and state and local permits.

The filing

## The permit or filing behind it

The regulator's decision or the owner's filing that the status rests on.

Building · the plant page read Nov 23, 2026

Constellation's plant page: restart expected in 2027, subject to Nuclear Regulatory Commission approval.

[Open the filing](https://www.constellationenergy.com/about/locations/crane-clean-energy-center.html)

The site

## The data center it serves

Linked to the Power Map only where a source ties the two.

Microsoft, under a power purchase agreement (no single data center named). Not on the Power Map.

Sources

## Where every fact comes from

Each source was opened and read on November 23, 2026.

page read Nov 23, 2026, read Nov 23, 2026

### Constellation

Crane Clean Energy Center

[Open the source](https://www.constellationenergy.com/about/locations/crane-clean-energy-center.html)

Keep going

## The grid around it

The same place, other records.

### The Queue: PJM

How much power data centers are asking PJM for.

### Onsite Power Watch

Every plant built to run a data center directly.

### Grid Watch

Live demand on the grids that host the most sites.

### Gigawatt Ledger

What was announced against what is confirmed energized.

Questions

## Crane Clean Energy Center, Microsoft agreement, answered

The plant, its status and the sources.

### What is Crane Clean Energy Center, Microsoft agreement?

Restart of the former Three Mile Island Unit 1, 835 MW, built to serve Microsoft, under a power purchase agreement (no single data center named). An existing or restarting nuclear plant under an agreement.

### What is its status?

Building, as of the plant page read Nov 23, 2026: Constellation's plant page: restart expected in 2027, subject to Nuclear Regulatory Commission approval.

### Where do the facts come from?

From the sources listed on this page, each opened and read on November 23, 2026. Constellation is restoring the 835 MW unit for Microsoft under what it calls its largest power purchase agreement, with the plant expected online in 2027 (Constellation, plant page read November 23, 2026).

Join the takeover

## Watch the plants with us

Found a newer permit or filing for this plant? Bring it to the $SIS Telegram with its link.

[Buy $SIS](https://pump.fun/coin/FdKdpz11GsTofLaNiddrhxrsE4APZYSSfLFqQ9YKpump)

[Join the Telegram](https://t.me/sisctotg)

[Follow on X](https://x.com/entersiscto)

[Swap on Jupiter](https://jup.ag/swap/SOL-FdKdpz11GsTofLaNiddrhxrsE4APZYSSfLFqQ9YKpump)