# Richland Parish 1 to 4 and Pointe Coupee 1 to 3

> Richland Parish 1 to 4 and Pointe Coupee 1 to 3: 5,278 MW of gas units of gas power for a second meta data center in north louisiana, proposed. Sources linked.

Source: https://siscto.si/onsite-power/entergy-evest/
Updated: 2026-11-26

1. [Home](https://siscto.si/)
2. [Onsite Power Watch](https://siscto.si/onsite-power/)
3. Richland Parish 1 to 4 and Pointe Coupee 1 to 3

Onsite Power Watch · Gas

# Richland Parish 1 to 4 and Pointe Coupee 1 to 3

Richland Parish 1 to 4 and Pointe Coupee 1 to 3: seven combined cycle gas units and three battery systems, 5,278 MW of gas units. It serves a second Meta data center in north Louisiana, to be developed by Evest LLC. Status: proposed, as of November 2, 2026. Entergy Louisiana application to the LPSC of March 2026; a settlement recommends certification; LPSC decision expected in December 2026.

Size
:   [5,278 MW](https://siscto.si/onsite-power/entergy-evest/#facts)

Fuel
:   [Gas](https://siscto.si/onsite-power/#totals)

Status
:   [Proposed](https://siscto.si/onsite-power/entergy-evest/#filing)

As of
:   [Nov 2, 2026](https://siscto.si/onsite-power/entergy-evest/#sources)

The facts

## What the public record shows

Utility plants on the grid, certified to serve one customer. Each fact below names its source.

- In March 2026 Entergy Louisiana signed a service agreement with Evest LLC, a Meta subsidiary, and applied to build seven combined cycle units totaling 5,278 MW, four near the customer site in Richland Parish and three in Pointe Coupee Parish (Entergy, Form 10-Q, November 2, 2026).

- A settlement with the LPSC staff and one intervenor recommends certification. Entergy expects the decision in December 2026 and in service dates in 2030 and 2031.

The filing

## The permit or filing behind it

The regulator's decision or the owner's filing that the status rests on.

Proposed · Nov 2, 2026

Entergy Louisiana application to the LPSC of March 2026; a settlement recommends certification; LPSC decision expected in December 2026.

[Open the filing](https://www.sec.gov/Archives/edgar/data/65984/000006598426000325/etr-20260930.htm)

The site

## The data center it serves

Linked to the Power Map only where a source ties the two.

A second Meta data center in north Louisiana, to be developed by Evest LLC. Not on the Power Map.

Sources

## Where every fact comes from

Each source was opened and read on November 23, 2026.

Nov 2, 2026, read Nov 23, 2026

### Entergy

Quarterly report for the quarter ended September 30, 2026 (SEC Form 10-Q)

[Open the source](https://www.sec.gov/Archives/edgar/data/65984/000006598426000325/etr-20260930.htm)

Keep going

## The grid around it

The same place, other records.

### The Queue: MISO

How much power data centers are asking MISO for.

### Onsite Power Watch

Every plant built to run a data center directly.

### Grid Watch

Live demand on the grids that host the most sites.

### Gigawatt Ledger

What was announced against what is confirmed energized.

Questions

## Richland Parish 1 to 4 and Pointe Coupee 1 to 3, answered

The plant, its status and the sources.

### What is Richland Parish 1 to 4 and Pointe Coupee 1 to 3?

Seven combined cycle gas units and three battery systems, 5,278 MW of gas units, built to serve A second Meta data center in north Louisiana, to be developed by Evest LLC. Utility plants on the grid, certified to serve one customer.

### What is its status?

Proposed, as of November 2, 2026: Entergy Louisiana application to the LPSC of March 2026; a settlement recommends certification; LPSC decision expected in December 2026.

### Where do the facts come from?

From the sources listed on this page, each opened and read on November 23, 2026. In March 2026 Entergy Louisiana signed a service agreement with Evest LLC, a Meta subsidiary, and applied to build seven combined cycle units totaling 5,278 MW, four near the customer site in Richland Parish and three in Pointe Coupee Parish (Entergy, Form 10-Q, November 2, 2026).

Join the takeover

## Watch the plants with us

Found a newer permit or filing for this plant? Bring it to the $SIS Telegram with its link.

[Buy $SIS](https://pump.fun/coin/FdKdpz11GsTofLaNiddrhxrsE4APZYSSfLFqQ9YKpump)

[Join the Telegram](https://t.me/sisctotg)

[Follow on X](https://x.com/entersiscto)

[Swap on Jupiter](https://jup.ag/swap/SOL-FdKdpz11GsTofLaNiddrhxrsE4APZYSSfLFqQ9YKpump)