# Franklin Farms 1 and 2 and Waterford 5: Onsite Power Watch

> Franklin Farms 1 and 2 and Waterford 5: 2,262 MW of gas power for a meta data center in north louisiana (the power map's meta hyperion), permitted.

Source: https://siscto.si/onsite-power/entergy-meta-hyperion/
Updated: 2026-11-26

1. [Home](https://siscto.si/)
2. [Onsite Power Watch](https://siscto.si/onsite-power/)
3. Franklin Farms 1 and 2 and Waterford 5

Onsite Power Watch · Gas

# Franklin Farms 1 and 2 and Waterford 5

Franklin Farms 1 and 2 and Waterford 5: three combined cycle gas units built by the utility, 2,262 MW. It serves a Meta data center in north Louisiana (the Power Map's Meta Hyperion). Status: permitted, as of August 2025. Louisiana Public Service Commission order of August 2025 accepting a settlement and certifying the units.

Size
:   [2,262 MW](https://siscto.si/onsite-power/entergy-meta-hyperion/#facts)

Fuel
:   [Gas](https://siscto.si/onsite-power/#totals)

Status
:   [Permitted](https://siscto.si/onsite-power/entergy-meta-hyperion/#filing)

As of
:   [August 2025](https://siscto.si/onsite-power/entergy-meta-hyperion/#sources)

The facts

## What the public record shows

Utility plants on the grid, certified to serve one customer. Each fact below names its source.

- Entergy Louisiana asked the LPSC in October 2024 to certify three combined cycle units totaling 2,262 MW to serve a new data center of a Meta subsidiary in north Louisiana; the LPSC accepted a settlement in August 2025 (Entergy, Form 10-K for 2025).

- Entergy expects Franklin Farms Units 1 and 2 in service in 2028 and Waterford 5 in 2029. These are utility plants on the grid, built for one customer.

- Epoch AI's record of Meta Hyperion ties the site to three gas units with 2,262 MW.

The filing

## The permit or filing behind it

The regulator's decision or the owner's filing that the status rests on.

Permitted · August 2025

Louisiana Public Service Commission order of August 2025 accepting a settlement and certifying the units.

[Open the filing](https://www.sec.gov/Archives/edgar/data/65984/000006598426000174/etr-20251231.htm)

The site

## The data center it serves

Linked to the Power Map only where a source ties the two.

[Meta Hyperion](https://siscto.si/power-map/meta-hyperion/) on the Power Map: Holly Ridge, Louisiana.

Sources

## Where every fact comes from

Each source was opened and read on November 23, 2026.

Feb 19, 2026, read Nov 23, 2026

### Entergy

Annual report for 2025 (SEC Form 10-K)

[Open the source](https://www.sec.gov/Archives/edgar/data/65984/000006598426000174/etr-20251231.htm)

retrieved Nov 10, 2026

### Epoch AI

The Power Map's site list, towns, status and power come from Epoch AI's open data set of data centers, licensed CC BY 4.0.

[Open the source](https://epoch.ai/data/ai-data-centers)

Keep going

## The grid around it

The same place, other records.

### The Queue: MISO

How much power data centers are asking MISO for.

### Onsite Power Watch

Every plant built to run a data center directly.

### Grid Watch

Live demand on the grids that host the most sites.

### Gigawatt Ledger

What was announced against what is confirmed energized.

Questions

## Franklin Farms 1 and 2 and Waterford 5, answered

The plant, its status and the sources.

### What is Franklin Farms 1 and 2 and Waterford 5?

Three combined cycle gas units built by the utility, 2,262 MW, built to serve A Meta data center in north Louisiana (the Power Map's Meta Hyperion). Utility plants on the grid, certified to serve one customer.

### What is its status?

Permitted, as of August 2025: Louisiana Public Service Commission order of August 2025 accepting a settlement and certifying the units.

### Where do the facts come from?

From the sources listed on this page, each opened and read on November 23, 2026. Entergy Louisiana asked the LPSC in October 2024 to certify three combined cycle units totaling 2,262 MW to serve a new data center of a Meta subsidiary in north Louisiana; the LPSC accepted a settlement in August 2025 (Entergy, Form 10-K for 2025).

Join the takeover

## Watch the plants with us

Found a newer permit or filing for this plant? Bring it to the $SIS Telegram with its link.

[Buy $SIS](https://pump.fun/coin/FdKdpz11GsTofLaNiddrhxrsE4APZYSSfLFqQ9YKpump)

[Join the Telegram](https://t.me/sisctotg)

[Follow on X](https://x.com/entersiscto)

[Swap on Jupiter](https://jup.ag/swap/SOL-FdKdpz11GsTofLaNiddrhxrsE4APZYSSfLFqQ9YKpump)
