# Power plants built for data centers

Onsite Power Watch lists the power plants built to run data centers directly, one by one from permits and filings: 12 so far, 9 gas plants and 3 nuclear agreements. The gas plants with a stated size add up to 13,663 MW (8 of 9 state one). 3 run today, 2 are being built, 5 are permitted and 2 are proposed.

Plants tracked
:   [12](https://siscto.si/onsite-power/#plants)

Running
:   [3](https://siscto.si/onsite-power/#plants)

Building
:   [2](https://siscto.si/onsite-power/#plants)

Permitted
:   [5](https://siscto.si/onsite-power/#plants)

Proposed
:   [2](https://siscto.si/onsite-power/#plants)

Gas capacity stated
:   [13,663 MW](https://siscto.si/onsite-power/#totals)

Plant by plant

## 12 plants, one page each

Running first, then building, permitted and proposed. Each card opens the plant: the site it serves, its permit or filing, its sources.

- [Susquehanna nuclear plant, Amazon agreement](https://siscto.si/onsite-power/susquehanna-amazon/): nuclear, 1,920 MW under the agreement, running as of Jun 11, 2025. Serves: Amazon's data center campus beside the Susquehanna plant, Pennsylvania.
- [Clinton Clean Energy Center, Meta agreement](https://siscto.si/onsite-power/clinton-meta/): nuclear, 1,121 MW under the agreement, running as of Jun 3, 2025. Serves: Meta, under a power purchase agreement (no single data center named).
- [Stargate Abilene onsite gas plant](https://siscto.si/onsite-power/stargate-abilene-onsite/): gas, 360 MW, running as of Jul 9, 2026. Serves: The OpenAI Stargate campus built by Crusoe in Abilene, Texas.
- [Crane Clean Energy Center, Microsoft agreement](https://siscto.si/onsite-power/crane-microsoft/): nuclear, 835 MW, building as of the plant page read Nov 23, 2026. Serves: Microsoft, under a power purchase agreement (no single data center named).
- [Socrates North and South](https://siscto.si/onsite-power/socrates/): gas, 400 MW (200 MW each), building as of May 5, 2026. Serves: A data center of Sidecat, LLC, an affiliate of Meta Platforms, in New Albany, Ohio.
- [Homer City Energy Campus](https://siscto.si/onsite-power/homer-city/): gas, up to 4,400 MW, permitted as of Nov 18, 2025. Serves: A planned data center campus at the former Homer City coal plant, Indiana County, Pennsylvania.
- [Franklin Farms 1 and 2 and Waterford 5](https://siscto.si/onsite-power/entergy-meta-hyperion/): gas, 2,262 MW, permitted as of August 2025. Serves: A Meta data center in north Louisiana (the Power Map's Meta Hyperion).
- [Apollo Power Generation Facility](https://siscto.si/onsite-power/apollo/): gas, 350 MW, plus about 120 MW of batteries, permitted as of Feb 3, 2026. Serves: The data center campus of Liames, LLC, beside the plant in Wood County, Ohio.
- [Colossus 1 gas turbines](https://siscto.si/onsite-power/colossus-1-turbines/): gas, up to 247 MW, permitted as of Jul 2, 2025. Serves: xAI's Colossus 1 data center, Memphis, Tennessee.
- [Southaven gas turbines for Colossus 2](https://siscto.si/onsite-power/southaven-turbines/): gas, not stated in the sources read (41 turbines), permitted as of Mar 10, 2026. Serves: xAI's Colossus 2 data center in Memphis, Tennessee, across the state line.
- [Richland Parish 1 to 4 and Pointe Coupee 1 to 3](https://siscto.si/onsite-power/entergy-evest/): gas, 5,278 MW of gas units, proposed as of Nov 2, 2026. Serves: A second Meta data center in north Louisiana, to be developed by Evest LLC.
- [Gas plant for Meta in El Paso](https://siscto.si/onsite-power/meta-el-paso-gas/): gas, 366 MW, proposed as of Jul 9, 2026. Serves: A Meta data center in El Paso, Texas.

Totals

## By fuel and by status

Counts are true by definition. Capacity is added only for the gas plants, and only where a source states it (8 of 9). Nuclear agreements are amounts under contract or a plant's size, two different things, so they are never added.

2 of the plants include batteries (Apollo Power Generation Facility, Richland Parish 1 to 4 and Pointe Coupee 1 to 3). Their battery size is on each plant's page where a source gives it.

Method

## How a plant gets on the list

From the public record only, with the date of every fact.

### The filing first

A plant is listed when a permit, a siting decision, a commission filing or the owner's own statement names it and the data center it serves. A report is used where it describes a public permit.

[Every plant](https://siscto.si/onsite-power/#plants)

### The site

Where a plant serves a site on the Power Map, the page links it, and only where a source or the site's own Epoch AI record ties the two.

[The Power Map](https://siscto.si/power-map/)

### The status

Proposed, permitted, building or running, as the newest source read says, with that source's date. Nothing is guessed from photos or maps.

[The totals](https://siscto.si/onsite-power/#totals)

### The recheck

Every month the list is read again: new permits, new filings, plants that change status. The list is below.

[The recheck list](https://siscto.si/onsite-power/#recheck)

Every month

## The monthly recheck list

What is read again each month, and what is still missing.

Texas

State air permits for data center plants (the Texas Tribune counted at least 15 planned gas plants), the GW Ranch permit in Pecos County and Meta El Paso.

[Where to look](https://www.tceq.texas.gov/permitting/air)

xAI

The capacity of the 41 Southaven turbines and any new Memphis permits.

[Where to look](https://www.shelbycountytn.gov/)

Ohio

Ohio Power Siting Board cases for behind the meter plants serving data centers.

[Where to look](https://opsb.ohio.gov/)

Louisiana

The LPSC decision on the Evest units, expected in December 2026.

[Where to look](https://lpsc.louisiana.gov/)

Nuclear

The Crane restart schedule and new nuclear agreements with data center owners.

[Where to look](https://www.nrc.gov/)

Global Energy Monitor

Whether its tracker data may be reused here (its license was not confirmed from its pages on November 23, 2026, so none of its project data is used).

[Where to look](https://globalenergymonitor.org/)

Public JSON, any origin, no key

Every plant
:   https://sicto.si/api/sis-onsite.php?a=list (Each plant with its size, fuel, status, site and filing, and the counts.)

One plant
:   https://sicto.si/api/sis-onsite.php?a=plant&p=socrates (The plant with its facts and sources.)

The whole set
:   https://siscto.si/assets/data/onsite-power.json (One file with every plant and source, as built into this release.)

Sources

## Where every fact comes from

Each source was opened and read on November 23, 2026. Global Energy Monitor's tracker data is not used: its license could not be confirmed from its pages.

Jun 3, 2025, read Nov 23, 2026

### Constellation

Constellation, Meta Sign 20-Year Deal for Clean, Reliable Nuclear Energy in Illinois

[Open the source](https://www.constellationenergy.com/newsroom/2025/constellation-meta-sign-20-year-deal-for-clean-reliable-nuclear-energy-in-illinois.html)

page read Nov 23, 2026, read Nov 23, 2026

### Constellation

Crane Clean Energy Center

[Open the source](https://www.constellationenergy.com/about/locations/crane-clean-energy-center.html)

Feb 19, 2026, read Nov 23, 2026

### Entergy

Annual report for 2025 (SEC Form 10-K)

[Open the source](https://www.sec.gov/Archives/edgar/data/65984/000006598426000174/etr-20251231.htm)

Nov 2, 2026, read Nov 23, 2026

### Entergy

Quarterly report for the quarter ended September 30, 2026 (SEC Form 10-Q)

[Open the source](https://www.sec.gov/Archives/edgar/data/65984/000006598426000325/etr-20260930.htm)

August 2026, read Nov 23, 2026

### Global Energy Monitor

U.S. gas power proposals tied to data centers nearly double in six months

[Open the source](https://globalenergymonitor.org/research/us-gas-power-proposals-tied-data-centers-nearly-double-six-months)

Nov 20, 2025, read Nov 23, 2026

### Homer City Generation

Homer City Generation Receives Air Quality Plan Approval from PA DEP

[Open the source](https://www.businesswire.com/news/home/20251120696816/en)

Mar 10, 2026, read Nov 23, 2026

### Mississippi Free Press

Mississippi permit board grants xAI's request for 41 Southaven gas turbines to power Memphis data center

[Open the source](https://www.mississippifreepress.org/mississippi-permit-board-grants-xais-request-for-41-southaven-gas-turbines-to-power-memphis-data-center/)

Jun 9, 2025, read Nov 23, 2026

### Ohio Power Siting Board

OPSB approves construction of Licking County natural gas-fired power plant

[Open the source](https://content.govdelivery.com/accounts/OHPUC/bulletins/3e43bed)

Feb 3, 2026, read Nov 23, 2026

### Ohio Power Siting Board

OPSB authorizes construction of Wood County power plant

[Open the source](https://content.govdelivery.com/accounts/OHPUC/bulletins/4077fa5)

Nov 12, 2026, read Nov 23, 2026

### Pennsylvania DEP

Homer City Generation Site Redevelopment

[Open the source](https://pa.gov/agencies/dep/dep-regions/northwest-regional-office/homer-city-generation-redevelopment)

Jun 11, 2025, read Nov 23, 2026

### Talen Energy

Talen Energy Expands Nuclear Energy Relationship with Amazon

[Open the source](https://www.globenewswire.com/news-release/2025/06/11/3097385/0/en/Talen-Energy-Expands-Nuclear-Energy-Relationship-with-Amazon.html)

Jul 3, 2025, read Nov 23, 2026

### TechCrunch

xAI gets permits for 15 natural gas generators at Memphis data center

[Open the source](https://techcrunch.com/2025/07/03/xai-gets-permits-for-15-natural-gas-generators-at-memphis-data-center)

Jul 9, 2026, read Nov 23, 2026

### The Texas Tribune and Floodlight

Planned Texas data centers could emit more greenhouse gases than many countries

[Open the source](https://www.texastribune.org/2026/07/09/texas-data-centers-ai-power-plants-pollution-state-permits/)

August 2025, read Nov 23, 2026

### Williams

Socrates North and South fact sheet

[Open the source](https://www.williams.com/wp-content/uploads/sites/8/2025/08/1355-Socrates-North-Fact-Sheet_v6.pdf)

May 5, 2026, read Nov 23, 2026

### Williams

Q1 earnings recap: data centers accelerate new growth paths for Williams

[Open the source](https://www.williams.com/2026/05/05/q1-earnings-recap-data-centers-accelerate-new-growth-paths-for-williams/)

retrieved Nov 10, 2026

### Epoch AI

The Power Map's site list, towns, status and power come from Epoch AI's open data set of data centers, licensed CC BY 4.0.

[Open the source](https://epoch.ai/data/ai-data-centers)

The set

## Other ways to check the build

Each reads a different public record of the same sites and grids.

### Power Map

Every SI data center public data can confirm, with its power.

### Gigawatt Ledger

What was announced against what is confirmed energized.

### The Queue

How much power data centers are asking each grid for.

### Grid Watch

Live demand on the grids that host the most sites.

### Bill Watch

Home power prices in every state with a site.

Questions

## Onsite Power Watch, answered

The plants, the statuses and the limits.

### What is Onsite Power Watch?

A free list of the power plants built to run data centers directly: gas turbines and engines on the campus, batteries, utility plants certified to serve one data center, and nuclear plants under agreements with data center owners. Each plant shows the site it serves, its size, its fuel, its status and the permit or filing behind it, with links and dates.

### Why are data centers building their own power plants?

To get power sooner than the grid can deliver it. Global Energy Monitor reported in August 2026 that about 77 GW of the gas capacity in development in Texas is planned to power data centers directly. Onsite Power Watch lists the plants one by one, from permits and filings.

### What do the statuses mean?

Proposed: a plan or an application, not yet approved. Permitted: a regulator approved it (an air permit, a siting certificate or a commission order). Building: the developer or a filing says construction is under way. Running: the plant runs. For a nuclear agreement, the status is the plant's own; the agreement's start date is on its page.

### Why are some sizes missing?

A size appears only where a permit, a filing or a report read for the page states it. The 41 turbines permitted in Southaven, Mississippi have no capacity in the sources read, so the page says so instead of guessing.

### Does it say these plants are good or bad?

No. It lists what the public record shows: the plant, the permit and the dates. It does not judge a plant, a company or a permit, and it makes no forecast.

### Can I reuse the data?

Yes. Every plant is a set of facts from public documents, linked to them. The whole set is a free download at [/assets/data/onsite-power.json](https://siscto.si/assets/data/onsite-power.json), and a public JSON answers at https://sicto.si/api/sis-onsite.php?a=list for any origin, with no key.

Join the takeover

## Watch the plants with us

Found a permit or a filing for a plant that runs a data center? Bring it to the $SIS Telegram with its link.