# Amazon Madison Mega Site SI Data Center, Canton, MS | $SIS

> Amazon Madison Mega Site is an SI data center in Canton, Mississippi, owned by Amazon. Epoch AI puts its IT power at 284 MW (Jun 4, 2026). Map and timeline.

Source: https://siscto.si/power-map/amazon-madison-mega-site/
Updated: 2026-11-10

1. [Home](https://siscto.si/)
2. [Power Map](https://siscto.si/power-map/)
3. Amazon Madison Mega Site

Power Map · Operating, expanding

# Amazon Madison Mega Site, Canton

Amazon Madison Mega Site is an SI data center in Canton, Mississippi, United States, owned by Amazon and used by Anthropic (Epoch AI rates this speculative). [Epoch AI](https://epoch.ai/data/ai-data-centers) estimates its IT power at 284 MW as of June 4, 2026, with 5 buildings operating, and projects 683 MW by March 15, 2028. Its public timeline starts on October 2, 2023.

IT power
:   284 MW (Jun 4, 2026)

Facility power
:   341 MW

Status
:   Operating, expanding

Buildings operating
:   5

Where it is

## The site and its facts

Amazon Madison Mega Site on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.

Place
:   Canton, Mississippi, United States

Address
:   Amazon Data Services Inc, Madison Mega Site Nissan Parkway and Highway 22 Canton, Mississippi Madison County

Coordinates
:   32.5974° N, 90.0913° W

Owner
:   Amazon

Users
:   Anthropic (Epoch AI rates this speculative)

Project
:   Project Rainier

Chips
:   Trainium2

Compute
:   About 214,348 H100 equivalents (Epoch AI estimate, Jun 4, 2026)

Projected
:   683 MW IT power by March 15, 2028 (Epoch AI projection, not a fact yet)

Timeline

### Heat Watch

Over the last three summers NASA's MODIS read the ground here +1.1 °C against the land 5 to 10 km around it by day.

[Open Heat Watch](https://siscto.si/heat-watch/amazon-madison-mega-site/)

### Lights On

NASA's night imagery read 68.8 of 100 over this site in October 2026, against 16.9 in October 2018, the first month read. Against a year before: +21.0 points. Light is not proof of what runs inside.

[Open Lights On](https://siscto.si/lights-on/?site=amazon-madison-mega-site#view)

## Dated, from the public record

Epoch AI's dated notes on Amazon Madison Mega Site, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.

**Oct 2, 2023**

> Land clearing begins

No IT power yet (0 operating)

**Mar 11, 2025**

> Generators and chillers still being installed on buildings 1-5.

No IT power yet (0 operating)

**Jun 23, 2025**

> Buildings 1-5 are operational, based on roofs being completed 5 months ago and generators being installed by 2025-04-10.

284 MW (5 operating)

**Oct 4, 2025**

> Confirmation that five buildings are fully equipped with cooling and backup generators.

284 MW (5 operating)

**Jun 4, 2026**

> Buildings 6 and 7 roof completed. Building 8 roof nearly completed. Building 9 roof half way up. No new operational buildings.

284 MW (5 operating)

**Mar 1, 2027 (Projection)**

> Buildings 6 and 7 operational, estimated from roofs having been completed 9 months ago (similar timeline to AWS buildings at New Carlisle in 2025).

284 MW (7 operating)

**Mar 15, 2028 (Projection)**

> Buildings 8-12 are operational. In June of 2026 only a faint outline of buildings 10,11 and 12 is visible, estimating construction completion to be the end of 2027, alligning with [expected completion by 2027](https://www.datacenterdynamics.com/en/news/aws-confirmed-as-company-behind-10bn-mississippi-data-center-development/). This final estimates adds three months to that for server installation.

683 MW (12 operating)

Adopt a site

## Watch Amazon Madison Mega Site

One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.

### The watcher

Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.

Approved updates · 0

- Approved updates show here with their date.

Sources

## Where the facts come from

The sources Epoch AI lists for this site, and the record itself.

- [Air Construction Permit](https://drive.google.com/file/d/1lhSF8TBA7fNWsN4Onj-nfL7X_-BN573r/view?usp=sharing)

- [Backup diesel generator referenced in the permit](https://www.cat.com/en_US/products/new/power-systems/electric-power/diesel-generator-sets/117341.html)

- [New York Times article on Project Rainier](https://www.nytimes.com/2025/06/24/technology/amazon-ai-data-centers.html)

- [SemiAnalysis article with imagery of Canton they have labeled as being an Amazon-Anthropic collaboration](https://newsletter.semianalysis.com/p/amazons-ai-resurgence-aws-anthropics-multi-gigawatt-trainium-expansion)

- [Epoch AI](https://epoch.ai/data/ai-data-centers), "AI data centers", the record for Amazon Madison Mega Site (CC BY 4.0), retrieved November 10, 2026

Nearby

## The nearest SI data centers

The four closest sites on the Power Map, as the crow flies.

23 km away

### Amazon Ridgeland

Ridgeland, Mississippi, United States

228 MW IT power

145 km away

### Meta Hyperion

Holly Ridge, Louisiana, United States

IT power not stated

266 km away

### Colossus 2

Memphis, Tennessee, United States

946 MW IT power

274 km away

### Colossus 1

Memphis, Tennessee, United States

340 MW IT power

Questions

## Amazon Madison Mega Site, answered

Where it is, who owns it and how much power it uses, from the public record.

### Where is Amazon Madison Mega Site?

Amazon Madison Mega Site is in Canton, Mississippi, United States, at Amazon Data Services Inc, Madison Mega Site Nissan Parkway and Highway 22 Canton, Mississippi Madison County. Epoch AI publishes its coordinates as 32.5974, -90.0913.

### Who owns Amazon Madison Mega Site?

Epoch AI lists Amazon as its owner and Anthropic (Epoch AI rates this speculative) as its user.

### How much power does Amazon Madison Mega Site use?

Epoch AI estimates its IT power at 284 MW as of June 4, 2026, and its total facility power at 341 MW. It projects 683 MW of IT power by March 15, 2028.

### Is Amazon Madison Mega Site operating?

Yes, and it is growing. Epoch AI counts 5 buildings operating as of June 4, 2026, with more capacity on its timeline.

Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).