# Anthropic-Amazon New Carlisle, New Carlisle, IN | $SIS

> Anthropic-Amazon New Carlisle is an SI data center in New Carlisle, Indiana, owned by Amazon. Epoch AI puts its IT power at 1,037 MW (Oct 19, 2026).

Source: https://siscto.si/power-map/anthropic-amazon-new-carlisle/
Updated: 2026-11-10

1. [Home](https://siscto.si/)
2. [Power Map](https://siscto.si/power-map/)
3. Anthropic-Amazon New Carlisle

Power Map · Operating, expanding

# Anthropic-Amazon New Carlisle, New Carlisle

Anthropic-Amazon New Carlisle is an SI data center in New Carlisle, Indiana, United States, owned by Amazon and used by Anthropic. [Epoch AI](https://epoch.ai/data/ai-data-centers) estimates its IT power at 1,037 MW as of October 19, 2026, with 18 buildings operating, and projects 1,925 MW by March 17, 2028. Its public timeline starts on February 9, 2024.

IT power
:   1,037 MW (Oct 19, 2026)

Facility power
:   1,244 MW

Status
:   Operating, expanding

Buildings operating
:   18

Where it is

## The site and its facts

Anthropic-Amazon New Carlisle on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.

Place
:   New Carlisle, Indiana, United States

Address
:   55001 Larrison Blvd, New Carlisle, IN 46552

Coordinates
:   41.6794° N, 86.4712° W

Owner
:   Amazon

Users
:   Anthropic

Project
:   Project Rainier

Chips
:   Trainium2

Compute
:   About 818,428 H100 equivalents (Epoch AI estimate, Oct 19, 2026)

Projected
:   1,925 MW IT power by March 17, 2028 (Epoch AI projection, not a fact yet)

Seen from orbit · Compute Watch

### The newest clear pass over Anthropic-Amazon New Carlisle

The image loads from NASA's public imagery: true color at 30 m per pixel, about 5 km across, north up.

[Open Compute Watch](https://siscto.si/compute/)

Timeline

### The Gigawatt Ledger

Project Rainier, New Carlisle: No power figure was announced for this project. No power figure was announced. Epoch AI estimates 1,037 MW of IT power in operation (1,244 MW for the whole facility) as of October 19, 2026, with more capacity on its timeline.

[Open it in the Ledger](https://siscto.si/ledger/project-rainier-new-carlisle/)

### Heat Watch

Over the last three summers NASA's MODIS read the ground here +0.7 °C against the land 5 to 10 km around it by day.

[Open Heat Watch](https://siscto.si/heat-watch/anthropic-amazon-new-carlisle/)

### Lights On

NASA's night imagery read 59.5 of 100 over this site in October 2026, against 9.5 in October 2018, the first month read. Against a year before: +7.2 points. Light is not proof of what runs inside.

[Open Lights On](https://siscto.si/lights-on/?site=anthropic-amazon-new-carlisle#view)

## Dated, from the public record

Epoch AI's dated notes on Anthropic-Amazon New Carlisle, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.

**Feb 9, 2024**

> Land clearing begins in the northern section

No IT power yet (0 operating)

**Jun 10, 2024**

> Land clearing begins in the southern section

No IT power yet (0 operating)

**May 10, 2025**

> Roof complete on building 11

No IT power yet (0 operating)

**Jun 23, 2025**

> Buildings 1-7 are operational. Based on all of the roofs being completed for over 5 months.

398 MW (7 operating)

**Sep 26, 2025**

> Roof complete on building 16. Generators are being installed for buildings 8-15. In the north, Building 17 and 18 are under construction. To the south of buildings 8-16, a concrete pad is visible, and an expanded car park next to it.

398 MW (7 operating)

**Oct 17, 2025**

> Confirmation that nearly 500,000 chips are operational, which fits buildings 1-7. In an [interview](https://www.youtube.com/watch?v=jwgW_gHI1Vs&t=220s), AWS CEO says "they're already running...about 500,000 [Trainium2] chips in Indiana today".

398 MW (7 operating)

**Dec 23, 2025**

> Buildings 8-11 are operational, given it's been over 7 months since their roofs were complete, and the backup generators and roof chimneys look complete. The roof is almost complete for Building 17 and 18.

626 MW (11 operating)

**Feb 9, 2026**

> Buildings 12-16 still have a few generators that look incomplete, so they are unlikely to be operational just yet. Buildings 17-18 still have ongoing roof work, no generators. Just south of Buildings 9-16, the outlines of a site for Buildings 19-32 are taking shape.

626 MW (11 operating)

**Mar 23, 2026**

> Buildings 12-16 are operational. Based on how long previous buildings took, when they were in a similar state to Buildings 12-16 in December.

910 MW (16 operating)

**Jun 3, 2026**

> Buildings 17-18 fully roofed but still having surrounding generators/cooling under construction. Cleared land for buildings 19-32 is still bare, with no building foundations visible yet. Based on satellite imagery.

910 MW (16 operating)

**Oct 19, 2026**

> Buildings 17-18 are operational. This is an estimate based on a rule of thumb of "operational 5 months after roof is complete", assuming the roofs took one more month after 2025-12-23. Also added four more months to account for commissioning and adjacent cooling units not being complete yet.

1,037 MW (18 operating)

**Mar 17, 2028 (Projection)**

> Buildings 19-32 are operational. This is an estimate based on how long Buildings 1-16 took to become operational. In May 2026, the foundation of several buildings and a substation was visible at the site of Buildings 19-32. Buildings 1-16 took 1 year and 10 months to go from a similar state to operational. So we add 1 year and 10 months to May 2026 to get this date estimate. The power capacity is based on an [air quality permit](https://t.co/HsAO7oyKa2) filed in May 2026, and the compute capacity is based on Trainium3 chips.

1,925 MW (32 operating)

Adopt a site

## Watch Anthropic-Amazon New Carlisle

One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.

### The watcher

Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.

Approved updates · 0

- Approved updates show here with their date.

Sources

## Where the facts come from

The sources Epoch AI lists for this site, and the record itself.

- [Air Construction Permit application for the northern portion](https://drive.google.com/file/d/1BKiTFNUk2KDaUaiHG7fz0KlkNSBTHzbb/view?usp=sharing)

- [Backup diesel generator referenced in the permit](https://www.cat.com/en_US/products/new/power-systems/electric-power/diesel-generator-sets/117341.html)

- [Announcement of Project Rainier coming online](https://www.aboutamazon.com/news/aws/aws-project-rainier-ai-trainium-chips-compute-cluster)

- [Air permit for Buildings 19-32, suggesting expansion to 2.3 GW total facility power](https://t.co/HsAO7oyKa2)

- [Epoch AI](https://epoch.ai/data/ai-data-centers), "AI data centers", the record for Anthropic-Amazon New Carlisle (CC BY 4.0), retrieved November 10, 2026

Nearby

## The nearest SI data centers

The four closest sites on the Power Map, as the crow flies.

139 km away

### Google Fort Wayne

Fort Wayne, Indiana, United States

IT power not stated

163 km away

### Microsoft Fairwater Wisconsin

Mount Pleasant, Wisconsin, United States

369 MW IT power

220 km away

### OpenAI Stargate Michigan

Benton, Michigan, United States

IT power not stated

225 km away

### OpenAI Stargate Wisconsin

Port Washington, Wisconsin, United States

IT power not stated

Questions

## Anthropic-Amazon New Carlisle, answered

Where it is, who owns it and how much power it uses, from the public record.

### Where is Anthropic-Amazon New Carlisle?

Anthropic-Amazon New Carlisle is in New Carlisle, Indiana, United States, at 55001 Larrison Blvd, New Carlisle, IN 46552. Epoch AI publishes its coordinates as 41.6794, -86.4712.

### Who owns Anthropic-Amazon New Carlisle?

Epoch AI lists Amazon as its owner and Anthropic as its user.

### How much power does Anthropic-Amazon New Carlisle use?

Epoch AI estimates its IT power at 1,037 MW as of October 19, 2026, and its total facility power at 1,244 MW. It projects 1,925 MW of IT power by March 17, 2028.

### Is Anthropic-Amazon New Carlisle operating?

Yes, and it is growing. Epoch AI counts 18 buildings operating as of October 19, 2026, with more capacity on its timeline.

Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).