# Anthropic Lake Mariner SI Data Center, Barker, NY | $SIS

> Anthropic Lake Mariner is an SI data center in Barker, New York, owned by AI XPV Platform. Epoch AI puts its IT power at 210 MW (Oct 31, 2026).

Source: https://siscto.si/power-map/anthropic-lake-mariner/
Updated: 2026-11-10

1. [Home](https://siscto.si/)
2. [Power Map](https://siscto.si/power-map/)
3. Anthropic Lake Mariner

Power Map · Operating, expanding

# Anthropic Lake Mariner, Barker

Anthropic Lake Mariner is an SI data center in Barker, New York, United States, owned by AI XPV Platform and used by Anthropic (Epoch AI rates this likely). [Epoch AI](https://epoch.ai/data/ai-data-centers) estimates its IT power at 210 MW as of October 31, 2026, with 2 buildings operating, and projects 378 MW by March 31, 2027. Its public timeline starts on June 11, 2025.

IT power
:   210 MW (Oct 31, 2026)

Facility power
:   245 MW

Status
:   Operating, expanding

Buildings operating
:   2

Where it is

## The site and its facts

Anthropic Lake Mariner on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.

Place
:   Barker, New York, United States

Address
:   7725 Lake Rd, Barker, NY 14012

Coordinates
:   43.3564° N, 78.6020° W

Owner
:   AI XPV Platform

Users
:   Anthropic (Epoch AI rates this likely)

Chips
:   TPU v7

Compute
:   About 292,830 H100 equivalents (Epoch AI estimate, Oct 31, 2026)

Projected
:   378 MW IT power by March 31, 2027 (Epoch AI projection, not a fact yet)

Timeline

### The Gigawatt Ledger

Lake Mariner: 440 MW was announced for this project. Public evidence puts 268 MW in operation as of October 31, 2026, against 440 MW announced: 61%. The announcement states IT load, so it is set against the IT load running.

[Open it in the Ledger](https://siscto.si/ledger/lake-mariner/)

### Heat Watch

Over the last three summers NASA's MODIS read the ground here +1.2 °C against the land 5 to 10 km around it by day.

[Open Heat Watch](https://siscto.si/heat-watch/anthropic-lake-mariner/)

### Lights On

NASA's night imagery read 28.4 of 100 over this site in October 2026, against 2.8 in October 2018, the first month read. Against a year before: +20.6 points. Light is not proof of what runs inside.

[Open Lights On](https://siscto.si/lights-on/?site=anthropic-lake-mariner#view)

## Dated, from the public record

Epoch AI's dated notes on Anthropic Lake Mariner, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.

**Jun 11, 2025**

> Land clearing begins for Building 1 (AKA CB3).

No IT power yet (0 operating)

**Mar 2, 2026**

> Building 1 appears to have a complete shell and cooling equipment. Building 2 shell is still under construction, but 17 cooling units are already loaded on the roof. The outline of Building 3 is visible at the foundation.

No IT power yet (0 operating)

**May 31, 2026**

> Building 1 is operational. On February 26, Terawulf [stated](https://investors.terawulf.com/news-events/press-releases/detail/132/terawulf-reports-fourth-quarter-and-full-year-2025-results) that CB3 was expected to be energized by mid-May 2026. A drone video commissioned from [RAAD](https://raad.com/) shows several cooling units operating on May 8. It's therefore likely that the building was fully operational around this date.

42 MW (1 operating)

**Jul 23, 2026**

> Building 1 looks complete, consistent with it going operational back in May. Building 2 is mostly complete, with the row of backup generators on the east side of the building still being installed. Building 3 shell is complete, with rooftop coolers midway through installation, and no neighboring generators installed/visible yet.

42 MW (1 operating)

**Oct 31, 2026**

> Building 2 (AKA CB4) is operational. On February 26, Terawulf [stated](https://investors.terawulf.com/news-events/press-releases/detail/132/terawulf-reports-fourth-quarter-and-full-year-2025-results) that CB4 was expected to be energized by Q3 2026.

210 MW (2 operating)

**Mar 31, 2027 (Projection)**

> Building 3 (AKA CB5) is operational. On February 26, 2026, Terawulf [stated](https://investors.terawulf.com/news-events/press-releases/detail/132/terawulf-reports-fourth-quarter-and-full-year-2025-results) that CB5 was expected to be energized by Q4 2026. However, based on the pace of Building 2, and comparisons to other projects like Stargate Abilene, we think this is optimistic. We expect a 3-month delay past the end of Q4 2026 to get to full operational capacity.

378 MW (3 operating)

Adopt a site

## Watch Anthropic Lake Mariner

One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.

### The watcher

Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.

Approved updates · 0

- Approved updates show here with their date.

Sources

## Where the facts come from

The sources Epoch AI lists for this site, and the record itself.

- [Terawulf press release with details and timeline for Buildings 1-5](https://investors.terawulf.com/news-events/press-releases/detail/132/terawulf-reports-fourth-quarter-and-full-year-2025-results)

- [DCD article suggesting that Fluidstack will deploy Google TPUs at Lake Mariner](https://www.datacenterdynamics.com/en/news/google-offers-its-tpus-to-ai-cloud-providers-report/)

- [Announcement of Anthropic-Fluidstack partnership, including data center(s) in New York](https://www.anthropic.com/news/anthropic-invests-50-billion-in-american-ai-infrastructure)

- [Epoch AI](https://epoch.ai/data/ai-data-centers), "AI data centers", the record for Anthropic Lake Mariner (CC BY 4.0), retrieved November 10, 2026

Nearby

## The nearest SI data centers

The four closest sites on the Power Map, as the crow flies.

0 km away

### Core42 Lake Mariner

Barker, New York, United States

58 MW IT power

309 km away

### OpenAI Stargate Lordstown

Lordstown, Ohio, United States

IT power not stated

323 km away

### AWS Berwick

Berwick, Pennsylvania, United States

108 MW IT power

416 km away

### CoreWeave Lancaster Greenfield site

Lancaster, Pennsylvania, United States

IT power not stated

Questions

## Anthropic Lake Mariner, answered

Where it is, who owns it and how much power it uses, from the public record.

### Where is Anthropic Lake Mariner?

Anthropic Lake Mariner is in Barker, New York, United States, at 7725 Lake Rd, Barker, NY 14012. Epoch AI publishes its coordinates as 43.3564, -78.6020.

### Who owns Anthropic Lake Mariner?

Epoch AI lists AI XPV Platform as its owner and Anthropic (Epoch AI rates this likely) as its user.

### How much power does Anthropic Lake Mariner use?

Epoch AI estimates its IT power at 210 MW as of October 31, 2026, and its total facility power at 245 MW. It projects 378 MW of IT power by March 31, 2027.

### Is Anthropic Lake Mariner operating?

Yes, and it is growing. Epoch AI counts 2 buildings operating as of October 31, 2026, with more capacity on its timeline.

Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).