# AWS New Albany, New Albany

AWS New Albany is an SI data center in New Albany, Ohio, United States, owned by Amazon. [Epoch AI](https://epoch.ai/data/ai-data-centers) estimates its IT power at 213 MW as of May 18, 2026, with 9 buildings operating, and projects 338 MW by July 1, 2027. Its public timeline starts on July 1, 2022.

IT power
:   213 MW (May 18, 2026)

Facility power
:   255 MW

Status
:   Operating, expanding

Buildings operating
:   9

Where it is

## The site and its facts

AWS New Albany on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.

Place
:   New Albany, Ohio, United States

Address
:   13360 Miller Rd NW

Coordinates
:   40.1059° N, 82.7403° W

Owner
:   Amazon

Chips
:   Trainium2, H100, H200, B200

Compute
:   About 201,112 H100 equivalents (Epoch AI estimate, May 18, 2026)

Projected
:   338 MW IT power by July 1, 2027 (Epoch AI projection, not a fact yet)

Timeline

### Heat Watch

Over the last three summers NASA's MODIS read the ground here +1.3 °C against the land 5 to 10 km around it by day, a change of +1.4 °C since before work on this build began.

[Open Heat Watch](https://siscto.si/heat-watch/aws-new-albany/)

### Lights On

NASA's night imagery read 81.5 of 100 over this site in October 2026, against 8.2 in October 2018, the first month read. Against a year before: +25.4 points. Light is not proof of what runs inside.

[Open Lights On](https://siscto.si/lights-on/?site=aws-new-albany#view)

## Dated, from the public record

Epoch AI's dated notes on AWS New Albany, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.

**Jul 1, 2022**

> Land clearing begins for Buildings 5-9 (eastern campus).

No IT power yet (0 operating)

**Dec 1, 2024**

> Buildings 5-9 (eastern campus) operational. [New Albany’s Dec. 2024 report](https://newalbanyohio.org/wp-content/uploads/2025/01/CD-2024-12.pdf) lists AWS partial occupancy for 5 buildings at the eastern campus. Note that we're only including roughly 44% of all the New Albany campuses IT Power as being dedicated to leading AI chips, based on all the types of compute instances [listed](https://docs.aws.amazon.com/ec2/latest/instancetypes/ec2-instance-regions.html). The full IT power is much higher than 113 MW.

113 MW (5 operating)

**Mar 12, 2026**

> Middle campus Buildings 10, 12, 13, and 14 appear complete/likely operational. Building 11 is still installing backup generators, so it is not counted as operational. Based on satellite imagery, northern campus Buildings 1-3 appear in late construction, with all roofs complete but nearby generator/cooling equipment still being installed for buildings 2-3. Building 4 is still early in construction. Eastern campus Buildings 5-9 appear complete and operational as expected. Note that we're only including roughly 44% of all the New Albany campuses IT Power as being dedicated to leading AI chips, based on all the types of compute instances [listed](https://docs.aws.amazon.com/ec2/latest/instancetypes/ec2-instance-regions.html).

213 MW (9 operating)

**May 18, 2026**

> Satellite imagery shows Building 1 in the northern campus still appears structurally finished, with no visible change from the prior two months, but we're still not counting it operational due to visible construction work around the perimeter. Buildings 2-3 still have nearby generators/cooling equipment being installed, and Building 4 is only roughly 80% roofed. Eastern campus Buildings 5-9 remain operational. Middle campus Buildings 10, 12, 13, and 14 remain operational; Building 11 is still installing backup generators and is not counted.

213 MW (9 operating)

**Jul 1, 2027 (Projection)**

> Expected operational date for the remaining tracked buildings (11, and 1-4) across the three campuses. This estimate is based on the previous buildings taking roughly 1.5 years from steel framing to complete operational status. Note that we're only including roughly 44% of all the New Albany campuses IT Power as being dedicated to leading AI chips, based on all the types of compute instances [listed](https://docs.aws.amazon.com/ec2/latest/instancetypes/ec2-instance-regions.html).

338 MW (14 operating)

Adopt a site

## Watch AWS New Albany

One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.

### The watcher

Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.

Approved updates · 0

- Approved updates show here with their date.

Sources

## Where the facts come from

The sources Epoch AI lists for this site, and the record itself.

- [City of New Albany Project Updates](https://newalbanyohio.org/community-development/project-updates/)

- [New Albany Community Development Report - Dec. 2024](https://newalbanyohio.org/wp-content/uploads/2025/01/CD-2024-12.pdf)

- [New Albany Community Development Report - Aug. 2025](https://newalbanyohio.org/wp-content/uploads/2025/09/CD-2025-08.pdf)

- [Article reporting first signing of the project](https://www.wosu.org/politics-government/2023-09-20/new-albany-city-council-approves-tax-break-deal-for-3-5-billion-amazon-data-center-project)

- [Epoch AI](https://epoch.ai/data/ai-data-centers), "AI data centers", the record for AWS New Albany (CC BY 4.0), retrieved November 10, 2026

Nearby

## The nearest SI data centers

The four closest sites on the Power Map, as the crow flies.

2 km away

### Meta Prometheus

New Albany, Ohio, United States

471 MW IT power

6 km away

### Google New Albany

New Albany, Ohio, United States

333 MW IT power

36 km away

### Google Columbus

Columbus, Ohio, United States

303 MW IT power

43 km away

### Google Lancaster

Lancaster, Ohio, United States

137 MW IT power

Questions

## AWS New Albany, answered

Where it is, who owns it and how much power it uses, from the public record.

### Where is AWS New Albany?

AWS New Albany is in New Albany, Ohio, United States, at 13360 Miller Rd NW. Epoch AI publishes its coordinates as 40.1059, -82.7403.

### Who owns AWS New Albany?

Epoch AI lists Amazon as its owner.

### How much power does AWS New Albany use?

Epoch AI estimates its IT power at 213 MW as of May 18, 2026, and its total facility power at 255 MW. It projects 338 MW of IT power by July 1, 2027.

### Is AWS New Albany operating?

Yes, and it is growing. Epoch AI counts 9 buildings operating as of May 18, 2026, with more capacity on its timeline.