# Bridge Data Centres MY06, Kulai

Bridge Data Centres MY06 is an SI data center in Kulai, Johor, Malaysia, owned by ByteDance (Epoch AI rates this likely) and used by ByteDance (Epoch AI rates this likely). [Epoch AI](https://epoch.ai/data/ai-data-centers) estimates its IT power at 243 MW as of September 13, 2026, with 7 buildings operating. Its public timeline starts on October 1, 2021.

IT power
:   243 MW (Sep 13, 2026)

Facility power
:   315 MW

Status
:   Operating

Buildings operating
:   7

Where it is

## The site and its facts

Bridge Data Centres MY06 on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.

Place
:   Kulai, Johor, Malaysia

Address
:   Bridge Data Centres, Sedenak Tech Park, Johor, Malaysia

Coordinates
:   1.6972° N, 103.4159° E

Owner
:   ByteDance (Epoch AI rates this likely)

Users
:   ByteDance (Epoch AI rates this likely)

Chips
:   A100, H100, B200

Compute
:   About 221,052 H100 equivalents (Epoch AI estimate, Sep 13, 2026)

Timeline

### Heat Watch

Over the last three summers NASA's MODIS read the ground here -0.6 °C against the land 5 to 10 km around it by day, a change of -0.5 °C since before work on this build began.

[Open Heat Watch](https://siscto.si/heat-watch/bridge-data-centres-my06/)

### Lights On

NASA's night imagery read 46.4 of 100 over this site in October 2026, against 5.4 in October 2018, the first month read. Against a year before: +12.9 points. Light is not proof of what runs inside.

[Open Lights On](https://siscto.si/lights-on/?site=bridge-data-centres-my06#view)

## Dated, from the public record

Epoch AI's dated notes on Bridge Data Centres MY06, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.

**Oct 1, 2021**

> Land clearing begins for campus 1, seen via satellite imagery. This start date is corroborated by the [Malaysian Investment Development Authority](https://www.mida.gov.my/media-release/bridge-data-centres-and-bytedance-celebrate-grand-opening-of-the-first-phase-hyperscale-data-centre-my06-in-johor-malaysia/), citing November for officially first breaking ground.

No IT power yet (0 operating)

**Dec 31, 2022**

> Building 1 (MY06-1) is operational. The [SEC filing for Chindata](https://www.sec.gov/Archives/edgar/data/1807192/000095017022025569/cd-ex99_1.htm) and [local news sources](https://www.malaymail.com/news/money/2022/10/21/mida-malaysia-still-most-desirable-location-for-data-centre-hubs-in-the-region/34929) reported the building was in service as of October 20, but only a [subsequent filing](https://www.sec.gov/Archives/edgar/data/1807192/000095017023015950/cd-20221231.htm) confirmed 19 MW was utilized by December 31, so we conservatively assume December 31.

19 MW (1 operating)

**Mar 1, 2023**

> [Drone footage](https://www.youtube.com/watch?v=ozi5G1Lt4Ew) indicates that Building 1 is operating at full capacity, with 4 of 5 cooling tower fans spinning. Building 2 has 2 of 21 fans spinning and some ongoing construction work, so we assume it's not fully operational yet. We estimate another 3 months until full utilization.

19 MW (1 operating)

**May 30, 2023**

> Building 2 (MY06-2) is operational.

61 MW (2 operating)

**Nov 5, 2024**

> Building 3 and 4 are operational. Building 3 was [originally scheduled](https://www.sec.gov/Archives/edgar/data/1807192/000119312523034103/d282677dex994.htm) for 2024Q4, and seemed partly operational in June, so it's likely to be fully utilized by this date. Building 4 was [scheduled](https://www.sec.gov/Archives/edgar/data/1807192/000095017023045611/cd-ex99_1.htm) for delivery starting 2024Q1, but it typically takes a few more months to fit out and reach full utilization, so we think it's only fully utilized by this date. At Campus 2, Buildings 5-7 and Building 9 are close to finishing construction while Buildings 8 and 10 shells are still under construction. The Campus 2 substation looks complete.

114 MW (4 operating)

**Feb 9, 2025**

> Construction looks complete on Building 5, 6 and 7, but we allow 3 more months for fit-out and ramping before declaring them operational.

114 MW (4 operating)

**May 25, 2025**

> Buildings 5-7 are operational.

243 MW (7 operating)

**Sep 23, 2025**

> Buildings 8 and 9 look structurally complete. The remaining building, building 10, still has construction material around it and scaffolding on the roof, with cooling units yet to be installed.

243 MW (7 operating)

**Mar 3, 2026**

> All cooling units are now installed on Building 10. [Drone footage](https://www.youtube.com/watch?v=BVdGV8FFaLw) from the same month shows most cooling units operating for Buildings 5-7, but none (or very few) for Buildings 8-10. So we don't think Buildings 8-10 are operating significantly yet.

243 MW (7 operating)

**Sep 13, 2026**

> No visible construction work on Buildings 8-10, but no cars in their carparks either (whereas Building 7 has many cars). So we still don't think Buildings 8-10 are utilized.

243 MW (7 operating)

Adopt a site

## Watch Bridge Data Centres MY06

One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.

### The watcher

Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.

Approved updates · 0

- Approved updates show here with their date.

Sources

## Where the facts come from

The sources Epoch AI lists for this site, and the record itself.

- [Bridge Data Centers 2025 article about MY06](https://www.bridgedatacentres.com/bridge-data-centres-and-bca-international-to-partner-to-promote-green-data-centers-globally/)

- [Drone footage from 2024](https://www.youtube.com/watch?v=n2b0ljMXyEg)

- [Development authority linking Bytedance](https://www.mida.gov.my/media-release/bridge-data-centres-and-bytedance-celebrate-grand-opening-of-the-first-phase-hyperscale-data-centre-my06-in-johor-malaysia/)

- [Street view linking second campus MY06-2](https://www.google.com/maps/@1.695402,103.4214409,3a,47.7y,213.04h,92.05t/data=!3m7!1e1!3m5!1sG4O28vWhkgGAlyz3dZ-fdg!2e0!6shttps:%2F%2Fstreetviewpixels-pa.googleapis.com%2Fv1%2Fthumbnail%3Fcb_client%3Dmaps_sv.tactile%26w%3D900%26h%3D600%26pitch%3D-2.0537269881136098%26panoid%3DG4O28vWhkgGAlyz3dZ-fdg%26yaw%3D213.043859649809!7i16384!8i8192?entry=ttu&g_ep=EgoyMDI2MDgxMi4wIKXMDSoASAFQAw%3D%3D)

- [Epoch AI](https://epoch.ai/data/ai-data-centers), "AI data centers", the record for Bridge Data Centres MY06 (CC BY 4.0), retrieved November 10, 2026

Nearby

## The nearest SI data centers

The four closest sites on the Power Map, as the crow flies.

14 km away

### YTL Johor

Kulai, Johor, Malaysia

113 MW IT power

36 km away

### DayOne Nusajaya

Johor Bahru, Johor, Malaysia

473 MW IT power

37 km away

### DayOne Kempas

Kempas, Johor, Malaysia

421.7 MW IT power

95 km away

### Oracle Batam

Batam, Riau Islands, Indonesia

72 MW IT power

Questions

## Bridge Data Centres MY06, answered

Where it is, who owns it and how much power it uses, from the public record.

### Where is Bridge Data Centres MY06?

Bridge Data Centres MY06 is in Kulai, Johor, Malaysia, at Bridge Data Centres, Sedenak Tech Park, Johor, Malaysia. Epoch AI publishes its coordinates as 1.6972, 103.4159.

### Who owns Bridge Data Centres MY06?

Epoch AI lists ByteDance (Epoch AI rates this likely) as its owner and ByteDance (Epoch AI rates this likely) as its user.

### How much power does Bridge Data Centres MY06 use?

Epoch AI estimates its IT power at 243 MW as of September 13, 2026, and its total facility power at 315 MW.

### Is Bridge Data Centres MY06 operating?

Yes. Epoch AI counts 7 buildings operating as of September 13, 2026.