# DayOne Kempas SI Data Center, Kempas, Malaysia | $SIS

> DayOne Kempas is an SI data center in Kempas, Johor, Malaysia. Epoch AI puts its IT power at 421.7 MW (Oct 1, 2026). Map, timeline, sources and its watcher.

Source: https://siscto.si/power-map/dayone-kempas/
Updated: 2026-11-10

1. [Home](https://siscto.si/)
2. [Power Map](https://siscto.si/power-map/)
3. DayOne Kempas

Power Map · Operating

# DayOne Kempas, Kempas

DayOne Kempas is an SI data center in Kempas, Johor, Malaysia. [Epoch AI](https://epoch.ai/data/ai-data-centers) estimates its IT power at 421.7 MW as of October 1, 2026, with 9 buildings operating. Its public timeline starts on November 11, 2023.

IT power
:   421.7 MW (Oct 1, 2026)

Facility power
:   590.4 MW

Status
:   Operating

Buildings operating
:   9

Where it is

## The site and its facts

DayOne Kempas on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.

Place
:   Kempas, Johor, Malaysia

Address
:   HP79+MP, 81300 Johor Bahru, Johor, Malaysia

Coordinates
:   1.5594° N, 103.7199° E

Owner
:   Not public

Chips
:   B300

Compute
:   About 480,639 H100 equivalents (Epoch AI estimate, Oct 1, 2026)

Timeline

### Heat Watch

Over the last three summers NASA's MODIS read the ground here -1.7 °C against the land 5 to 10 km around it by day.

[Open Heat Watch](https://siscto.si/heat-watch/dayone-kempas/)

### Lights On

NASA's night imagery read 95.6 of 100 over this site in October 2026, against 68.7 in October 2018, the first month read. Against a year before: +11.8 points. The place was already bright at the first reading, so growth is harder to see. Light is not proof of what runs inside.

[Open Lights On](https://siscto.si/lights-on/?site=dayone-kempas#view)

## Dated, from the public record

Epoch AI's dated notes on DayOne Kempas, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.

**Nov 11, 2023**

> Land clearing begins.

No IT power yet (0 operating)

**Sep 15, 2025**

> In this [video](https://www.youtube.com/watch?v=HODHjDbFt10) at 6:28, some fans can be seen in motion for Building 3. However, we think it's unlikely that any buildings are at fully operational capacity yet. Buildings 1-4 are roofed. Building 5-6 shells are underway.

No IT power yet (0 operating)

**Jan 22, 2026**

> Buildings 3 and 4 are operational. This is based on construction looking complete, and DayOne [reporting](https://archive.is/8CFXN) 390 MW "in service" across both Nusajaya and Kempas campuses as of Jan 30. Subtracting our [Nusajaya estimates](https://epoch.ai/data/ai-data-centers/directory/dayone-nusajaya) (69.5 MW excluded in Phase 1 + 240.3 MW AI) implies ~80 MW in service at KTP, consistent with roughly 2 buildings per our ~49.6 MW per-building estimate, but not at full capacity. Buildings 1 and 2 look complete with rooftop cooling equipment installed (32 units each, in 2 strips of 16). The units are almost all single-fan cells; Building 2 has one strip of 16 single-fan cells and one darker bank of 16 long multi-fan air-cooled (slat) units - this suggests an cell-to-air-cooled power equivalence that informs our power estimates. The smaller Building 9 (west of Building 1, half fit-out: 16 cells) also has its cooling installed. Building 5 has rooftop equipment partially installed; Building 6 is roofed; Buildings 7-8 shells are still underway.

80.2 MW (2 operating)

**Jun 1, 2026**

> Buildings 1-4 and the smaller Building 9 assumed fully operational: cooling equipment was installed by Jan 2026 (Building 9 on the same timeline as Building 1) and the implied KTP in-service figure (~80 MW) shows them ramping in early 2026, so we allow ~3 more months to reach full capacity. Rooftop equipment texture is visible campus-wide.

223.2 MW (5 operating)

**Aug 10, 2026**

> Buildings 5-6 look complete and parking lot activity suggests they are nearly operational. Building 7-8 nearing completion with some construction equipment still in their vicinity.

223.2 MW (5 operating)

**Sep 1, 2026**

> Buildings 5-6 assumed operational. These buildings were roofed between Sep and Dec 2025 and equipment fit-out was underway in Jan 2026; applying the default roof-to-operational delay plus ramp time approximates their operability to this date.

322.5 MW (7 operating)

**Oct 1, 2026**

> Buildings 7-8 assumed operational. These buildings were roofed by March 2026 and by August 2026 their cooling and backup power equipment looked complete. With an additional two months of commissioning after August we approximate their operability to this date.

421.7 MW (9 operating)

Adopt a site

## Watch DayOne Kempas

One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.

### The watcher

Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.

Approved updates · 0

- Approved updates show here with their date.

Sources

## Where the facts come from

The sources Epoch AI lists for this site, and the record itself.

- [News of Phase 2 operation](https://www.moomoo.com/news/post/41886329/support-ai-computing-deployment-gds-holdings-nusajaya-technology-park-datacenter?level=1&data_ticket=1778269491837872)

- [Archived DayOne website - "120 MW in operation" in Johor](https://web.archive.org/web/20241231165420/https://dayonedc.com/)

- [Archived DayOne website - 390 MW "in service" in Johor](https://web.archive.org/web/20260314134756/https://dayonedc.com/market/johor)

- [Financial Times report that Alibaba and ByteDance are training AI models in southeast Asia](https://www.ft.com/content/96fe9898-a3a4-4a33-be1d-da06bdb6cb2b)

- [Epoch AI](https://epoch.ai/data/ai-data-centers), "AI data centers", the record for DayOne Kempas (CC BY 4.0), retrieved November 10, 2026

Nearby

## The nearest SI data centers

The four closest sites on the Power Map, as the crow flies.

20 km away

### DayOne Nusajaya

Johor Bahru, Johor, Malaysia

473 MW IT power

23 km away

### YTL Johor

Kulai, Johor, Malaysia

113 MW IT power

37 km away

### Bridge Data Centres MY06

Kulai, Johor, Malaysia

243 MW IT power

59 km away

### Oracle Batam

Batam, Riau Islands, Indonesia

72 MW IT power

Questions

## DayOne Kempas, answered

Where it is, who owns it and how much power it uses, from the public record.

### Where is DayOne Kempas?

DayOne Kempas is in Kempas, Johor, Malaysia, at HP79+MP, 81300 Johor Bahru, Johor, Malaysia. Epoch AI publishes its coordinates as 1.5594, 103.7199.

### Who owns DayOne Kempas?

Epoch AI does not name an owner yet.

### How much power does DayOne Kempas use?

Epoch AI estimates its IT power at 421.7 MW as of October 1, 2026, and its total facility power at 590.4 MW.

### Is DayOne Kempas operating?

Yes. Epoch AI counts 9 buildings operating as of October 1, 2026.

Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).