# Google Columbus SI Data Center, Columbus, OH | $SIS

> Google Columbus is an SI data center in Columbus, Ohio, owned by Google. Epoch AI puts its IT power at 303 MW (Aug 5, 2026). Map, dated timeline and sources.

Source: https://siscto.si/power-map/google-columbus/
Updated: 2026-11-10

1. [Home](https://siscto.si/)
2. [Power Map](https://siscto.si/power-map/)
3. Google Columbus

Power Map · Operating, expanding

# Google Columbus, Columbus

Google Columbus is an SI data center in Columbus, Ohio, United States, owned by Google and used by Google DeepMind (Epoch AI rates this speculative). [Epoch AI](https://epoch.ai/data/ai-data-centers) estimates its IT power at 303 MW as of August 5, 2026, with 4 buildings operating, and projects 386 MW by July 1, 2027. Its public timeline starts on October 1, 2021.

IT power
:   303 MW (Aug 5, 2026)

Facility power
:   364 MW

Status
:   Operating, expanding

Buildings operating
:   4

Where it is

## The site and its facts

Google Columbus on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.

Place
:   Columbus, Ohio, United States

Address
:   5076 S High St, Columbus, OH 43207

Coordinates
:   39.8491° N, 82.9966° W

Owner
:   Google

Users
:   Google DeepMind (Epoch AI rates this speculative)

Chips
:   TPU v5e, TPU v5p, TPU v6e, TPU v7

Compute
:   About 331,986 H100 equivalents (Epoch AI estimate, Aug 5, 2026)

Projected
:   386 MW IT power by July 1, 2027 (Epoch AI projection, not a fact yet)

Timeline

### Heat Watch

Over the last three summers NASA's MODIS read the ground here -2.6 °C against the land 5 to 10 km around it by day, a change of +0.8 °C since before work on this build began.

[Open Heat Watch](https://siscto.si/heat-watch/google-columbus/)

### Lights On

NASA's night imagery read 56.0 of 100 over this site in October 2026, against 31.3 in October 2018, the first month read. Against a year before: +3.8 points. The place was already bright at the first reading, so growth is harder to see. Light is not proof of what runs inside.

[Open Lights On](https://siscto.si/lights-on/?site=google-columbus#view)

## Dated, from the public record

Epoch AI's dated notes on Google Columbus, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.

**Oct 1, 2021**

> Land clearing begins on the eastern half of the site, for Buildings 1-2

No IT power yet (0 operating)

**Jul 1, 2023**

> Building 2 foundation work begins. Building 1 generators seem complete, cooling towers still under construction.

No IT power yet (0 operating)

**Apr 1, 2024**

> Building 1 operational. No visible construction and roads/parking complete around the building. Building 2 chillers are beginning construction. Foundation work begins for Building 3.

65 MW (1 operating)

**Mar 1, 2025**

> Building 2 operational. Parking complete, no more visible construction.

130 MW (2 operating)

**Oct 1, 2025**

> Building 3 operational. Surrounding roads finished, no more visible construction.

216 MW (3 operating)

**Feb 21, 2026**

> Buildings 1-3 are visibly operational, with steam coming out of the cooling towers. Meanwhile Building 4 is extremely close to completion, with all backup generators complete with only 3 cooling towers missing their fans. ~1/2 the generators are installed for Building 5, and the roof is mostly complete (starting to install the final white layer, with the actual roof structure already complete).

216 MW (3 operating)

**May 1, 2026**

> Building 4 operational. No more visible construction, and since only 3 fans needed to be installed since Feburary, operational date was likely soon after. Building 5 roof almost complete.

303 MW (4 operating)

**Aug 5, 2026**

> Confirmation that Building 4 is complete. Building 5 has progressed since February, with a complete roof, all backup generators in place, and five cooling towers in place.

303 MW (4 operating)

**Jul 1, 2027 (Projection)**

> Building 5 operational. The [transmission line construction notice](https://www.aeptransmission.com/ohio/docs/Hartman%20Farms%20Extension%20No.%202%20138%20kV%20Transmission%20Line%20Project%20Construction%20Notice.pdf) that expands site by 100 MW is assumed to be entirely for Building 5, and has an in-service date of July 1, 2027 (page 3). Estimate taken on the safe side based on completion times for Building 3-4 from when roof was complete.

386 MW (5 operating)

Adopt a site

## Watch Google Columbus

One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.

### The watcher

Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.

Approved updates · 0

- Approved updates show here with their date.

Sources

## Where the facts come from

The sources Epoch AI lists for this site, and the record itself.

- [DCD article detailing early work beginning on the site](https://www.datacenterdynamics.com/en/news/google-breaks-ground-on-columbus-ohio-data-center/)

- [Transmission line construction notice; details current site capacity, expansion, and maximum future site capacity](https://www.aeptransmission.com/ohio/docs/Hartman%20Farms%20Extension%20No.%202%20138%20kV%20Transmission%20Line%20Project%20Construction%20Notice.pdf)

- [Epoch AI](https://epoch.ai/data/ai-data-centers), "AI data centers", the record for Google Columbus (CC BY 4.0), retrieved November 10, 2026

Nearby

## The nearest SI data centers

The four closest sites on the Power Map, as the crow flies.

30 km away

### Google Lancaster

Lancaster, Ohio, United States

137 MW IT power

30 km away

### Google New Albany

New Albany, Ohio, United States

333 MW IT power

34 km away

### Meta Prometheus

New Albany, Ohio, United States

471 MW IT power

36 km away

### AWS New Albany

New Albany, Ohio, United States

213 MW IT power

Questions

## Google Columbus, answered

Where it is, who owns it and how much power it uses, from the public record.

### Where is Google Columbus?

Google Columbus is in Columbus, Ohio, United States, at 5076 S High St, Columbus, OH 43207. Epoch AI publishes its coordinates as 39.8491, -82.9966.

### Who owns Google Columbus?

Epoch AI lists Google as its owner and Google DeepMind (Epoch AI rates this speculative) as its user.

### How much power does Google Columbus use?

Epoch AI estimates its IT power at 303 MW as of August 5, 2026, and its total facility power at 364 MW. It projects 386 MW of IT power by July 1, 2027.

### Is Google Columbus operating?

Yes, and it is growing. Epoch AI counts 4 buildings operating as of August 5, 2026, with more capacity on its timeline.

Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).