# Google Lincoln SI Data Center, Lincoln, NE | $SIS

> Google Lincoln is an SI data center in Lincoln, Nebraska, owned by Google. Epoch AI puts its IT power at 141 MW (May 12, 2026). Map, dated timeline and sources.

Source: https://siscto.si/power-map/google-lincoln/
Updated: 2026-11-10

1. [Home](https://siscto.si/)
2. [Power Map](https://siscto.si/power-map/)
3. Google Lincoln

Power Map · Operating, expanding

# Google Lincoln, Lincoln

Google Lincoln is an SI data center in Lincoln, Nebraska, United States, owned by Google. [Epoch AI](https://epoch.ai/data/ai-data-centers) estimates its IT power at 141 MW as of May 12, 2026, with 1 building operating, and projects 283 MW by October 1, 2027. Its public timeline starts on July 1, 2023.

IT power
:   141 MW (May 12, 2026)

Facility power
:   170 MW

Status
:   Operating, expanding

Buildings operating
:   1

Where it is

## The site and its facts

Google Lincoln on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.

Place
:   Lincoln, Nebraska, United States

Address
:   5475 Cloud Ct, Lincoln, NE 68514

Coordinates
:   40.9070° N, 96.6536° W

Owner
:   Google

Chips
:   TPU v6e, TPU v7

Compute
:   About 197,575 H100 equivalents (Epoch AI estimate, May 12, 2026)

Projected
:   283 MW IT power by October 1, 2027 (Epoch AI projection, not a fact yet)

Timeline

### Heat Watch

Over the last three summers NASA's MODIS read the ground here -0.7 °C against the land 5 to 10 km around it by day.

[Open Heat Watch](https://siscto.si/heat-watch/google-lincoln/)

### Lights On

NASA's night imagery read 25.3 of 100 over this site in October 2026, against 7.7 in October 2018, the first month read. Against a year before: +6.0 points. Light is not proof of what runs inside.

[Open Lights On](https://siscto.si/lights-on/?site=google-lincoln#view)

## Dated, from the public record

Epoch AI's dated notes on Google Lincoln, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.

**Jul 1, 2023**

> Land clearing begins for the site

No IT power yet (0 operating)

**Oct 23, 2025**

> Building 1 looks mostly complete: the large items like generators and substation are done. It is just missing 2 more cooling towers (4 fans). They just seem to be paving and setting up the secondary equipment so it is probably a few months away from operation. Building 2 foundation has been laid.

No IT power yet (0 operating)

**May 12, 2026**

> Building 1 operational. This is based on the fact that is no more visible equipment or construction around the building, and based on previous imagery and when construction started on the last pieces of equipment (fans). Building 2's roof is complete, with generator construction more than halfway complete and cooling construction beginning. Electrical equipment on the side of Building 2 is also around halfway complete.

141 MW (1 operating)

**Oct 1, 2027 (Projection)**

> Building 2 operational. Estimated based on the construction timeline for Building 1, specifically the time to operational since the roof was complete and the time to operational since the foundation work began.

283 MW (2 operating)

Adopt a site

## Watch Google Lincoln

One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.

### The watcher

Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.

Approved updates · 0

- Approved updates show here with their date.

Sources

## Where the facts come from

The sources Epoch AI lists for this site, and the record itself.

- [Army corps land use application with a useful construction plan diagram, split across 7 phases](https://upload.wikimedia.org/wikipedia/commons/2/25/Application_no-_NWO-2019-00110-WEH_-_USACE-p16021coll15-1525.pdf)

- [DCD article on the start of site construction](https://www.datacenterdynamics.com/en/news/work-on-data-center-in-lincoln-nebraska-finally-starting/)

- [Rezoning approval, stating 75 ft building height](https://lnklan.granicus.com/DocumentViewer.php?file=lnklan_bfe1e3023d49404348f26355e113cb22.pdf&view=1)

- [Epoch AI](https://epoch.ai/data/ai-data-centers), "AI data centers", the record for Google Lincoln (CC BY 4.0), retrieved November 10, 2026

Nearby

## The nearest SI data centers

The four closest sites on the Power Map, as the crow flies.

48 km away

### Meta Sarpy

Springfield, Nebraska, United States

80 MW IT power

49 km away

### Google Papillion

Papillion, Nebraska, United States

237 MW IT power

68 km away

### Google Omaha

Omaha, Nebraska, United States

237 MW IT power

78 km away

### Google Council Bluffs (East)

Council Bluffs, Iowa, United States

237 MW IT power

Questions

## Google Lincoln, answered

Where it is, who owns it and how much power it uses, from the public record.

### Where is Google Lincoln?

Google Lincoln is in Lincoln, Nebraska, United States, at 5475 Cloud Ct, Lincoln, NE 68514. Epoch AI publishes its coordinates as 40.9070, -96.6536.

### Who owns Google Lincoln?

Epoch AI lists Google as its owner.

### How much power does Google Lincoln use?

Epoch AI estimates its IT power at 141 MW as of May 12, 2026, and its total facility power at 170 MW. It projects 283 MW of IT power by October 1, 2027.

### Is Google Lincoln operating?

Yes, and it is growing. Epoch AI counts 1 building operating as of May 12, 2026, with more capacity on its timeline.

Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).