# Google Mesa, Mesa

Google Mesa is an SI data center in Mesa, Arizona, United States, owned by Google. [Epoch AI](https://epoch.ai/data/ai-data-centers) estimates its IT power at 183 MW as of August 15, 2026, with 2 buildings operating. Its public timeline starts on July 1, 2023.

IT power
:   183 MW (Aug 15, 2026)

Facility power
:   237 MW

Status
:   Operating

Buildings operating
:   2

Where it is

## The site and its facts

Google Mesa on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.

Place
:   Mesa, Arizona, United States

Address
:   Not public

Coordinates
:   33.3546° N, 111.6759° W

Owner
:   Google

Chips
:   TPU v6e, TPU v5p

Compute
:   About 289,540 H100 equivalents (Epoch AI estimate, Aug 15, 2026)

Timeline

### Heat Watch

Over the last three summers NASA's MODIS read the ground here -1.1 °C against the land 5 to 10 km around it by day.

[Open Heat Watch](https://siscto.si/heat-watch/google-mesa/)

### Lights On

NASA's night imagery read 83.7 of 100 over this site in October 2026, against 62.0 in October 2018, the first month read. Against a year before: +0.4 points. The place was already bright at the first reading, so growth is harder to see. Light is not proof of what runs inside.

[Open Lights On](https://siscto.si/lights-on/?site=google-mesa#view)

## Dated, from the public record

Epoch AI's dated notes on Google Mesa, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.

**Jul 1, 2023**

> Land clearing begins for the entire site.

No IT power yet (0 operating)

**Jul 1, 2025**

> Building 1 is operational. This is based on the state of construction on 2025-03-02 as seen on [Google Earth](https://earth.google.com/web/@33.35450568,-111.67805903,407.02398359a,2119.1496037d,35y,-0h,0t,0r/data=ChYqEAgBEgoyMDI1LTAzLTAyGAFCAggBQgIIAEoNCP___________wEQAA), where building shell and external components seems to have been completed, but there is still a lot of construction equipment present. That equipment appears to have been cleared up by this date, 4 months later, with the 2025-09-07 satellite imagery providing an upper bound. Construction has begun on the Building 2 roof, with work beginning on the areas for cooling and generators as well.

90 MW (1 operating)

**Sep 7, 2025**

> Building 2 roof is mostly completed. Building 2's backup generators are almost complete, and cooling is a little more than halfway complete. The Building 2 substation is also under construction.

90 MW (1 operating)

**May 15, 2026**

> Building 2 is close to being operational. There is only construction left on the backup generators, which are almost complete. Some equipment is also strewn around the building, especially near the air-cooled chillers. Preparation seems to have begun for Building 3 at the site.

90 MW (1 operating)

**Aug 15, 2026**

> Building 2 is operational. This is estimated based on the close-to-complete construction status from May 2026.

183 MW (2 operating)

Adopt a site

## Watch Google Mesa

One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.

### The watcher

Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.

Approved updates · 0

- Approved updates show here with their date.

Sources

## Where the facts come from

The sources Epoch AI lists for this site, and the record itself.

- [DCD article on the site breaking ground](https://www.datacenterdynamics.com/en/news/google-breaks-ground-on-mesa-data-center-campus-in-arizona/)

- [DCD article on announcement to build Building 2](https://www.datacenterdynamics.com/en/news/google-files-to-build-second-data-center-at-mesa-campus-in-arizona/)

- [Epoch AI](https://epoch.ai/data/ai-data-centers), "AI data centers", the record for Google Mesa (CC BY 4.0), retrieved November 10, 2026

Nearby

## The nearest SI data centers

The four closest sites on the Power Map, as the crow flies.

64 km away

### Stream Phoenix

Goodyear, Arizona, United States

64 MW IT power

64 km away

### Microsoft Goodyear

Goodyear, Arizona, United States

202 MW IT power

479 km away

### Meta Los Lunas

Los Lunas, New Mexico, United States

118 MW IT power

498 km away

### OpenAI Stargate New Mexico

Santa Teresa, New Mexico, United States

IT power not stated

Questions

## Google Mesa, answered

Where it is, who owns it and how much power it uses, from the public record.

### Where is Google Mesa?

Google Mesa is in Mesa, Arizona, United States. Epoch AI publishes its coordinates as 33.3546, -111.6759.

### Who owns Google Mesa?

Epoch AI lists Google as its owner.

### How much power does Google Mesa use?

Epoch AI estimates its IT power at 183 MW as of August 15, 2026, and its total facility power at 237 MW.

### Is Google Mesa operating?

Yes. Epoch AI counts 2 buildings operating as of August 15, 2026.

Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).