# Google Red Oak SI Data Center, Red Oak, TX | $SIS

> Google Red Oak is an SI data center in Red Oak, Texas, owned by Google. Epoch AI puts its IT power at 77 MW (Feb 6, 2026). Map, dated timeline and sources.

Source: https://siscto.si/power-map/google-red-oak/
Updated: 2026-11-10

1. [Home](https://siscto.si/)
2. [Power Map](https://siscto.si/power-map/)
3. Google Red Oak

Power Map · Operating, expanding

# Google Red Oak, Red Oak

Google Red Oak is an SI data center in Red Oak, Texas, United States, owned by Google. [Epoch AI](https://epoch.ai/data/ai-data-centers) estimates its IT power at 77 MW as of February 6, 2026, with 1 building operating, and projects 154 MW by December 1, 2026. Its public timeline starts on April 30, 2023.

IT power
:   77 MW (Feb 6, 2026)

Facility power
:   93 MW

Status
:   Operating, expanding

Buildings operating
:   1

Where it is

## The site and its facts

Google Red Oak on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.

Place
:   Red Oak, Texas, United States

Address
:   330 Austin Blvd, Red Oak, TX 75154

Coordinates
:   32.5377° N, 96.7935° W

Owner
:   Google

Chips
:   TPU v6e

Compute
:   About 108,135 H100 equivalents (Epoch AI estimate, Feb 6, 2026)

Projected
:   154 MW IT power by December 1, 2026 (Epoch AI projection, not a fact yet)

Timeline

### Heat Watch

Over the last three summers NASA's MODIS read the ground here +0.8 °C against the land 5 to 10 km around it by day.

[Open Heat Watch](https://siscto.si/heat-watch/google-red-oak/)

### Lights On

NASA's night imagery read 58.8 of 100 over this site in October 2026, against 21.3 in October 2018, the first month read. Against a year before: +3.2 points. Light is not proof of what runs inside.

[Open Lights On](https://siscto.si/lights-on/?site=google-red-oak#view)

## Dated, from the public record

Epoch AI's dated notes on Google Red Oak, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.

**Apr 30, 2023**

> First signs of development/land clearing

No IT power yet (0 operating)

**Aug 25, 2025**

> Building 1 is operational, based on a Google Earth [image](https://earth.google.com/web/@32.53855187,-96.7936939,182.71625265a,4648.56607908d,30.00094375y,3.66969189h,0t,0r/) showing a completed building shell and equipment, and the large construction car park being emptied. Building 2 shell looks mostly completed.

77 MW (1 operating)

**Feb 6, 2026**

> Building 1 appears active - the surrounding land is finished including the site entrance and the parking lot. The dry coolers for Building 2 are nearly complete although the building is still clearly a construction zone. The Building 2 substation also appears complete.

77 MW (1 operating)

**Dec 1, 2026 (Projection)**

> Building 2 is estimated to be operational.

154 MW (2 operating)

Adopt a site

## Watch Google Red Oak

One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.

### The watcher

Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.

Approved updates · 0

- Approved updates show here with their date.

Sources

## Where the facts come from

The sources Epoch AI lists for this site, and the record itself.

- [Media coverage confirming location, project name, investment size, and some timing](https://www.mysanantonio.com/business/article/google-texas-data-center-21236627.php)

- [Google PUE data listing the Red Oak site from Q1 2026](https://datacenters.google/efficiency/)

- [Epoch AI](https://epoch.ai/data/ai-data-centers), "AI data centers", the record for Google Red Oak (CC BY 4.0), retrieved November 10, 2026

Nearby

## The nearest SI data centers

The four closest sites on the Power Map, as the crow flies.

27 km away

### Google Midlothian

Midlothian, Texas, United States

103 MW IT power

85 km away

### CoreWeave Denton TX

Denton, Texas, United States

262 MW IT power

166 km away

### Meta Temple

Temple, Texas, United States

178 MW IT power

173 km away

### OpenAI Stargate Milam

Burlington, Texas, United States

IT power not stated

Questions

## Google Red Oak, answered

Where it is, who owns it and how much power it uses, from the public record.

### Where is Google Red Oak?

Google Red Oak is in Red Oak, Texas, United States, at 330 Austin Blvd, Red Oak, TX 75154. Epoch AI publishes its coordinates as 32.5377, -96.7935.

### Who owns Google Red Oak?

Epoch AI lists Google as its owner.

### How much power does Google Red Oak use?

Epoch AI estimates its IT power at 77 MW as of February 6, 2026, and its total facility power at 93 MW. It projects 154 MW of IT power by December 1, 2026.

### Is Google Red Oak operating?

Yes, and it is growing. Epoch AI counts 1 building operating as of February 6, 2026, with more capacity on its timeline.

Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).