# Huawei Wuhu, Wuhu

Huawei Wuhu is an SI data center in Wuhu, Anhui, China, owned by Huawei. [Epoch AI](https://epoch.ai/data/ai-data-centers) estimates its IT power at 197 MW as of November 1, 2026, with 5 buildings operating, and projects 453 MW by December 1, 2027. Its public timeline starts on January 1, 2023.

IT power
:   197 MW (Nov 1, 2026)

Facility power
:   256 MW

Status
:   Operating, expanding

Buildings operating
:   5

Where it is

## The site and its facts

Huawei Wuhu on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.

Place
:   Wuhu, Anhui, China

Address
:   Wuhu, China

Coordinates
:   31.2918° N, 118.2998° E

Owner
:   Huawei

Chips
:   Ascend 910C, H20, Ascend 910B, Ascend 950PR

Compute
:   About 52,831 H100 equivalents (Epoch AI estimate, Nov 1, 2026)

Projected
:   453 MW IT power by December 1, 2027 (Epoch AI projection, not a fact yet)

Timeline

### Heat Watch

Over the last three summers NASA's MODIS read the ground here -3.4 °C against the land 5 to 10 km around it by day, a change of +1.8 °C since before work on this build began.

[Open Heat Watch](https://siscto.si/heat-watch/huawei-wuhu/)

### Lights On

NASA's night imagery read 4.0 of 100 over this site in October 2026, against 2.0 in October 2018, the first month read. Against a year before: -0.3 points. Light is not proof of what runs inside.

[Open Lights On](https://siscto.si/lights-on/?site=huawei-wuhu#view)

## Dated, from the public record

Epoch AI's dated notes on Huawei Wuhu, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.

**Jan 1, 2023**

> Land clearing begins, with the east campus being the first of the three. Land clearing begins for the other two campuses months after.

No IT power yet (0 operating)

**Jan 1, 2025**

> The first building is operational. On the north campus, building 4 is operational assuming a 3-month fit-out post structural completion. We multiply each building's estimated capacity by an assumed 65% rack occupancy rate. This is close to the ~62 to 64% reported for Wuhu and other national data center hubs in 2023, and matches Anhui's 65% target for the Wuhu cluster. Occupied capacity is assumed to be all AI chips.

44 MW (1 operating)

**Mar 1, 2025**

> Three buildings are operational. On the west campus, building 1 is operational, and on the east campus, building 7 is operational. The second building on the east campus has installed generators, but as of 2026 does not have the cooling sufficient for AI. Assumes a 3-month fit-out post structural completion. As with the other buildings, we assume 65% rack occupancy.

118 MW (3 operating)

**Nov 1, 2025**

> Four buildings are operational. On the west campus, building 2 is operational assuming a 3-month fit-out post structural completion. As with the other buildings, we assume 65% rack occupancy.

156 MW (4 operating)

**Jan 24, 2026**

> Four buildings are operational in total. A fifth building, building 5 on the north campus, is finishing installing roofside cooling. Another building on the east campus is complete but does not have sufficient cooling for AI despite its backup generators. The remaining three buildings, one per campus, have not begun construction.

156 MW (4 operating)

**Jun 1, 2026**

> Four buildings are operational. On the north campus, building 5 is nearing structural completion but still has roofing and cooling remaining.

156 MW (4 operating)

**Aug 6, 2026**

> On the north campus, building 5 is structurally complete but not operational as seen by barricades and no parked cars. Building 6, a much larger building across the pond, should finish construction in approximately one month, given that it is structurally complete and 75% of its cooling looks to be installed. On the east campus, building 9 is under construction.

156 MW (4 operating)

**Nov 1, 2026**

> Five buildings are operational. On the north campus, building 5 is operational assuming a 3-month fit-out post structural completion. As with the other buildings, we assume 65% rack occupancy.

197 MW (5 operating)

**Dec 31, 2026 (Projection)**

> Six buildings are operational. On the north campus, building 6, the larger building, is operational assuming a 3-month fit-out if it is structurally complete in September. We assume Building 6 is about 3.7x more power than one of the previous buildings, based on the size and quantity of cooling and backup generator equipment observed in satellite imagery. As with the other buildings, we assume 65% rack occupancy.

360 MW (6 operating)

**Dec 1, 2027 (Projection)**

> All eight AI buildings are operational. Buildings 3 and 9 are assumed to be 1.25x the power and compute of buildings 1 and 7 based on the sizing of the backup generator enclosures; building 8 is excluded due to insufficient cooling. The time from observed land-clearing to operational is 23-26 months based on previous buildings. As with the other buildings, we assume 65% rack occupancy.

453 MW (8 operating)

Adopt a site

## Watch Huawei Wuhu

One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.

### The watcher

Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.

Approved updates · 0

- Approved updates show here with their date.

Sources

## Where the facts come from

The sources Epoch AI lists for this site, and the record itself.

- [Epoch AI](https://epoch.ai/data/ai-data-centers), "AI data centers", the record for Huawei Wuhu (CC BY 4.0), retrieved November 10, 2026

Nearby

## The nearest SI data centers

The four closest sites on the Power Map, as the crow flies.

1,145 km away

### Alibaba Zhangbei

Zhangbei, Hebei, China

169 MW IT power

1,165 km away

### Envision Galaxy Ulanqab

Ulanqab, Inner Mongolia, China

118 MW IT power

1,166 km away

### VNET Bayin Ulanqab

Ulanqab, Inner Mongolia, China

221 MW IT power

1,181 km away

### Huawei Horinger

Hohhot, Inner Mongolia, China

169.9 MW IT power

Questions

## Huawei Wuhu, answered

Where it is, who owns it and how much power it uses, from the public record.

### Where is Huawei Wuhu?

Huawei Wuhu is in Wuhu, Anhui, China, at Wuhu, China. Epoch AI publishes its coordinates as 31.2918, 118.2998.

### Who owns Huawei Wuhu?

Epoch AI lists Huawei as its owner.

### How much power does Huawei Wuhu use?

Epoch AI estimates its IT power at 197 MW as of November 1, 2026, and its total facility power at 256 MW. It projects 453 MW of IT power by December 1, 2027.

### Is Huawei Wuhu operating?

Yes, and it is growing. Epoch AI counts 5 buildings operating as of November 1, 2026, with more capacity on its timeline.