> Meta Cheyenne is an SI data center in Cheyenne, Wyoming, owned by Meta. Epoch AI puts its IT power at 152 MW (Jul 25, 2026). Map, dated timeline and sources.

Source: https://siscto.si/power-map/meta-cheyenne/
Updated: 2026-11-10

1. [Home](https://siscto.si/)
2. [Power Map](https://siscto.si/power-map/)
3. Meta Cheyenne

Power Map · Operating, expanding

# Meta Cheyenne, Cheyenne

Meta Cheyenne is an SI data center in Cheyenne, Wyoming, United States, owned by Meta and used by Meta. [Epoch AI](https://epoch.ai/data/ai-data-centers) estimates its IT power at 152 MW as of July 25, 2026, with 2 buildings operating, and projects 207 MW by February 15, 2027. Its public timeline starts on April 1, 2024.

IT power
:   152 MW (Jul 25, 2026)

Facility power
:   182 MW

Status
:   Operating, expanding

Buildings operating
:   2

Where it is

## The site and its facts

Meta Cheyenne on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.

Place
:   Cheyenne, Wyoming, United States

Address
:   Cheyenne, WY 82007, USA

Coordinates
:   41.0801° N, 104.8241° W

Owner
:   Meta

Users
:   Meta

Chips
:   B300

Compute
:   About 172,815 H100 equivalents (Epoch AI estimate, Jul 25, 2026)

Projected
:   207 MW IT power by February 15, 2027 (Epoch AI projection, not a fact yet)

Timeline

### Heat Watch

Over the last three summers NASA's MODIS read the ground here -0.4 °C against the land 5 to 10 km around it by day.

[Open Heat Watch](https://siscto.si/heat-watch/meta-cheyenne/)

### Lights On

NASA's night imagery read 32.7 of 100 over this site in October 2026, against 7.1 in October 2018, the first month read. Against a year before: +17.8 points. Light is not proof of what runs inside.

[Open Lights On](https://siscto.si/lights-on/?site=meta-cheyenne#view)

## Dated, from the public record

Epoch AI's dated notes on Meta Cheyenne, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.

**Apr 1, 2024**

> Land clearing begins.

No IT power yet (0 operating)

**Jan 30, 2025**

> Structure for Building 1 and 2 under construction.

No IT power yet (0 operating)

**Mar 22, 2026**

> Building 1 shell and cooling looks complete, Building 2 roof almost complete.

No IT power yet (0 operating)

**Jul 25, 2026**

> Both buildings estimated to be operational.

152 MW (2 operating)

**Feb 15, 2027 (Projection)**

> Buildings 3 and 4 are similar in style and size to the ones seen at the Prometheus site, we estimate their operability based on that timeline.

207 MW (4 operating)

Adopt a site

## Watch Meta Cheyenne

One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.

### The watcher

Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.

Approved updates · 0

- Approved updates show here with their date.

Sources

## Where the facts come from

The sources Epoch AI lists for this site, and the record itself.

- [Meta Introduction to the Cheyenne Project](https://datacenters.atmeta.com/2024/07/hello-cheyenne/)

- [Fortis Construction announcement](https://fortisconstruction.com/news/fortis-building-metas-cheyenne-campus/)

- [Press announcement suggesting a 2027 operational date](https://cheyenneleads.org/meta-announces-new-data-center-a-major-investment-in-cheyenne-wyoming/)

- [Epoch AI](https://epoch.ai/data/ai-data-centers), "AI data centers", the record for Meta Cheyenne (CC BY 4.0), retrieved November 10, 2026

Nearby

## The nearest SI data centers

The four closest sites on the Power Map, as the crow flies.

613 km away

### Meta Eagle Mountain

Eagle Mountain, Utah, United States

133 MW IT power

614 km away

### QTS Eagle Mountain

Eagle Mountain, Utah, United States

IT power not stated

686 km away

### Google Lincoln

Lincoln, Nebraska, United States

141 MW IT power

716 km away

### Meta Los Lunas

Los Lunas, New Mexico, United States

118 MW IT power

Questions

## Meta Cheyenne, answered

Where it is, who owns it and how much power it uses, from the public record.

### Where is Meta Cheyenne?

Meta Cheyenne is in Cheyenne, Wyoming, United States, at Cheyenne, WY 82007, USA. Epoch AI publishes its coordinates as 41.0801, -104.8241.

### Who owns Meta Cheyenne?

Epoch AI lists Meta as its owner and Meta as its user.

### How much power does Meta Cheyenne use?

Epoch AI estimates its IT power at 152 MW as of July 25, 2026, and its total facility power at 182 MW. It projects 207 MW of IT power by February 15, 2027.

### Is Meta Cheyenne operating?

Yes, and it is growing. Epoch AI counts 2 buildings operating as of July 25, 2026, with more capacity on its timeline.

Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).