# Microsoft Fairwater Wisconsin, Mount Pleasant

Microsoft Fairwater Wisconsin is an SI data center in Mount Pleasant, Wisconsin, United States, owned by Microsoft and used by OpenAI (Epoch AI rates this likely), Microsoft (Epoch AI rates this likely). [Epoch AI](https://epoch.ai/data/ai-data-centers) estimates its IT power at 369 MW as of May 15, 2026, with 1 building operating, and projects 2,263 MW by May 13, 2028. Its public timeline starts on July 14, 2023.

IT power
:   369 MW (May 15, 2026)

Facility power
:   442 MW

Status
:   Operating, expanding

Buildings operating
:   1

Where it is

## The site and its facts

Microsoft Fairwater Wisconsin on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.

Place
:   Mount Pleasant, Wisconsin, United States

Address
:   4800 90th St, Mount Pleasant, WI 53403

Coordinates
:   42.6839° N, 87.9152° W

Owner
:   Microsoft

Users
:   OpenAI (Epoch AI rates this likely), Microsoft (Epoch AI rates this likely)

Project
:   Microsoft AI WAN

Chips
:   B200

Compute
:   About 445,680 H100 equivalents (Epoch AI estimate, May 15, 2026)

Energy
:   WE Energies

Projected
:   2,263 MW IT power by May 13, 2028 (Epoch AI projection, not a fact yet)

Seen from orbit · Compute Watch

### The newest clear pass over Microsoft Fairwater Wisconsin

The image loads from NASA's public imagery: true color at 30 m per pixel, about 5 km across, north up.

[Open Compute Watch](https://siscto.si/compute/)

Timeline

### The Gigawatt Ledger

Microsoft Fairwater Wisconsin: No power figure was announced for this project. No power figure was announced. Epoch AI estimates 369 MW of IT power in operation (442 MW for the whole facility) as of May 15, 2026, with more capacity on its timeline.

[Open it in the Ledger](https://siscto.si/ledger/microsoft-fairwater-wisconsin/)

### Heat Watch

Over the last three summers NASA's MODIS read the ground here +1.3 °C against the land 5 to 10 km around it by day.

[Open Heat Watch](https://siscto.si/heat-watch/microsoft-fairwater-wisconsin/)

### Lights On

NASA's night imagery read 72.3 of 100 over this site in October 2026, against 14.7 in October 2018, the first month read. Against a year before: +15.8 points. Light is not proof of what runs inside.

[Open Lights On](https://siscto.si/lights-on/?site=microsoft-fairwater-wisconsin#view)

## Dated, from the public record

Epoch AI's dated notes on Microsoft Fairwater Wisconsin, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.

**Jul 14, 2023**

> Land clearing begins for Building 1.

No IT power yet (0 operating)

**Sep 26, 2025**

> Building 1 cooling and backup generators all look complete from above but there is still construction visible around the building. Building 2 is well underway with a foundation and a complete substation. Large carpark and concrete area north of Building 2. Building 3 has a concrete foundation and a substation underway.

No IT power yet (0 operating)

**Jan 28, 2026**

> Building 1 looks complete, but based on Microsoft announcements, it's not fully operational yet. Steel framing is underway for Building 2.

No IT power yet (0 operating)

**Apr 16, 2026**

> Building 1 is operational. [X post](https://x.com/satyanadella/status/2044767391293509761?s=61) from Microsoft saying this date for Fairwater becoming operational.

369 MW (1 operating)

**May 15, 2026**

> The main shell of Building 2 looks almost completed. In Area 2 (northwest of Buildings 1-2), the grading for the original design has been replaced with grading for the new [9-building design](https://www.mtpleasantwi.gov/AgendaCenter/ViewFile/Agenda/_01212026-1292), making way for Buildings 3-11. Work continues on the northern substation in Area 2.

369 MW (1 operating)

**Feb 20, 2027 (Projection)**

> Building 2 is operational. This is estimated based on (1) the delay between Building 1 and Building 2 starting land clearing, (2) in March 2025, a Microsoft spokesperson [said](https://www.wpr.org/news/microsoft-pauses-construction-on-parts-of-mount-pleasant-site-again) “fully on track” with the first phase , where “southern datacenter buildings complete, and preparation begins for operations” was [expected](https://local.microsoft.com/blog/mount-pleasant-datacenter-project-update/) by late 2026. Finally, while it's not 100% consistent with our estimates, MISO was [planning](https://cdn.misoenergy.org/NEW%20LOAD%20ANNOUNCEMENTS%20IN%20MISO%20REGIONS%2012062024684954.pdf) 1480 MW of load for Microsoft in Mount Pleasant in 2026.

737 MW (2 operating)

**May 13, 2028 (Projection)**

> Buildings 3-11 are estimated to be operational. The grading for this revised 9-building plan was underway in May 2026, and we assume an average 2-year [build time](https://epoch.ai/data-insights/data-centers-buildout-speeds) from that point.

2,263 MW (11 operating)

Adopt a site

## Watch Microsoft Fairwater Wisconsin

One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.

### The watcher

Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.

Approved updates · 0

- Approved updates show here with their date.

Sources

## Where the facts come from

The sources Epoch AI lists for this site, and the record itself.

- [Microsoft blog with engineering details](https://blogs.microsoft.com/blog/2025/09/18/inside-the-worlds-most-powerful-ai-datacenter/)

- [Microsoft blog with more general information](https://blogs.microsoft.com/on-the-issues/2025/09/18/made-in-wisconsin-the-worlds-most-powerful-ai-datacenter/)

- [Construction Permit Application for building 1](https://drive.google.com/file/d/1azyXnreQBuYEqX2oaSUgePDGCMneez5Z/view?usp=sharing)

- [Plan for 9-building and 6-building expansions](https://drive.google.com/file/d/1PQKzfauDNzabN7oNviMKTvsZmxlsUVpG/view?usp=sharing)

- [OpenAI article mentioning they use Microsoft's Fairwater supercomputers](https://openai.com/index/mrc-supercomputer-networking/)

- [Epoch AI](https://epoch.ai/data/ai-data-centers), "AI data centers", the record for Microsoft Fairwater Wisconsin (CC BY 4.0), retrieved November 10, 2026

Nearby

## The nearest SI data centers

The four closest sites on the Power Map, as the crow flies.

83 km away

### OpenAI Stargate Wisconsin

Port Washington, Wisconsin, United States

IT power not stated

163 km away

### Anthropic-Amazon New Carlisle

New Carlisle, Indiana, United States

1,037 MW IT power

300 km away

### Google Fort Wayne

Fort Wayne, Indiana, United States

IT power not stated

324 km away

### Google Cedar Rapids

Cedar Rapids, Iowa, United States

IT power not stated

Questions

## Microsoft Fairwater Wisconsin, answered

Where it is, who owns it and how much power it uses, from the public record.

### Where is Microsoft Fairwater Wisconsin?

Microsoft Fairwater Wisconsin is in Mount Pleasant, Wisconsin, United States, at 4800 90th St, Mount Pleasant, WI 53403. Epoch AI publishes its coordinates as 42.6839, -87.9152.

### Who owns Microsoft Fairwater Wisconsin?

Epoch AI lists Microsoft as its owner and OpenAI (Epoch AI rates this likely), Microsoft (Epoch AI rates this likely) as its users.

### How much power does Microsoft Fairwater Wisconsin use?

Epoch AI estimates its IT power at 369 MW as of May 15, 2026, and its total facility power at 442 MW. It projects 2,263 MW of IT power by May 13, 2028.

### Is Microsoft Fairwater Wisconsin operating?

Yes, and it is growing. Epoch AI counts 1 building operating as of May 15, 2026, with more capacity on its timeline.