# Microsoft-Nebius New Jersey SI Data Center, Vineland, NJ

> Microsoft-Nebius New Jersey is an SI data center in Vineland, New Jersey, owned by Nebius. Epoch AI puts its IT power at 50 MW (Jul 12, 2026). Map and timeline.

Source: https://siscto.si/power-map/microsoft-nebius-new-jersey/
Updated: 2026-11-10

1. [Home](https://siscto.si/)
2. [Power Map](https://siscto.si/power-map/)
3. Microsoft-Nebius New Jersey

Power Map · Operating

# Microsoft-Nebius New Jersey, Vineland

Microsoft-Nebius New Jersey is an SI data center in Vineland, New Jersey, United States, owned by Nebius and used by Microsoft (Epoch AI rates this likely). [Epoch AI](https://epoch.ai/data/ai-data-centers) estimates its IT power at 50 MW as of July 12, 2026, with 1 building operating. Its public timeline starts on May 31, 2024.

IT power
:   50 MW (Jul 12, 2026)

Facility power
:   70 MW

Status
:   Operating

Buildings operating
:   1

Where it is

## The site and its facts

Microsoft-Nebius New Jersey on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.

Place
:   Vineland, New Jersey, United States

Address
:   3963 S Lincoln Ave, Vineland, New Jersey

Coordinates
:   39.4267° N, 75.0168° W

Owner
:   Nebius

Users
:   Microsoft (Epoch AI rates this likely)

Chips
:   B300

Compute
:   About 56,847 H100 equivalents (Epoch AI estimate, Jul 12, 2026)

Timeline

### Heat Watch

Over the last three summers NASA's MODIS read the ground here +2.5 °C against the land 5 to 10 km around it by day.

[Open Heat Watch](https://siscto.si/heat-watch/microsoft-nebius-new-jersey/)

### Lights On

NASA's night imagery read 45.8 of 100 over this site in October 2026, against 31.0 in October 2018, the first month read. Against a year before: +7.9 points. Light is not proof of what runs inside.

[Open Lights On](https://siscto.si/lights-on/?site=microsoft-nebius-new-jersey#view)

## Dated, from the public record

Epoch AI's dated notes on Microsoft-Nebius New Jersey, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.

**May 31, 2024**

> Land clearing begins for northern two buildings (Building 1-2).

No IT power yet (0 operating)

**Dec 15, 2025**

> By mid-December 2025 the building was still not complete. A satellite analysis by SemiAnalysis found that the air-cooled chillers serving the second half of the first 50 MW phase were not yet installed, so the phase was not yet operational. SemiAnalysis estimated the full 50 MW would be reached around January to February 2026.

No IT power yet (0 operating)

**Apr 15, 2026**

> High-resolution satellite imagery shows the air-cooled chiller array has grown to roughly 30 units, enough to support the first phase. We estimate Building 1 became operational around early 2026 with about 50 MW of IT capacity (70 MW total facility power at a 1.4 PUE), based on DataOne's disclosure of a first 50 MW phase. SemiAnalysis estimated the full 50 MW was reached around January to February 2026 ([SemiAnalysis](https://newsletter.semianalysis.com/p/stop-saying-half-of-2026-us-datacenter)); this April image is our first high-resolution confirmation that the cooling is in place.

50 MW (1 operating)

**Jul 12, 2026**

> Compared with the April 2026 image, the building shell is closer to completion, and several additional air-cooled chillers have appeared on the ground, though they do not yet appear to be connected or operating. We therefore keep IT capacity at 50 MW.

50 MW (1 operating)

Adopt a site

## Watch Microsoft-Nebius New Jersey

One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.

### The watcher

Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.

Approved updates · 0

- Approved updates show here with their date.

Sources

## Where the facts come from

The sources Epoch AI lists for this site, and the record itself.

- [Nebius: up to 300 MW capacity at new New Jersey data center](https://nebius.com/newsroom/nebius-accelerates-us-expansion-adding-up-to-300-mw-capacity-at-new-data-center-in-new-jersey)

- [DataOne and Nebius partner for 300 MW AI data center (Data Centre Magazine)](https://datacentremagazine.com/articles/dataone-and-nebius-partner-for-new-300mw-ai-data-centre)

- [Microsoft secures 100,000 NVIDIA GB300 via Nebius deal (Tom's Hardware)](https://www.tomshardware.com/tech-industry/artificial-intelligence/microsoft-inks-usd33-billion-in-deals-with-neoclouds-like-nebius-coreweave-nebius-deal-alone-secures-100-000-nvidia-gb300-chips-for-internal-use)

- [DataOne CEO on first 50 MW delivery to Nebius (LinkedIn)](https://www.linkedin.com/feed/update/urn:li:activity:7367650153555591168/)

- [Large data center nears completion in Vineland (Cape May County Herald)](https://capemaycountyherald.com/article/large-data-center-nears-completion-in-vineland/)

- [SemiAnalysis: Stop Saying Half of 2026 US Datacenter Capacity Is Canceled](https://newsletter.semianalysis.com/p/stop-saying-half-of-2026-us-datacenter)

- [Epoch AI](https://epoch.ai/data/ai-data-centers), "AI data centers", the record for Microsoft-Nebius New Jersey (CC BY 4.0), retrieved November 10, 2026

Nearby

## The nearest SI data centers

The four closest sites on the Power Map, as the crow flies.

127 km away

### CoreWeave Lancaster Greenfield site

Lancaster, Pennsylvania, United States

IT power not stated

208 km away

### AWS Berwick

Berwick, Pennsylvania, United States

108 MW IT power

223 km away

### Google Arcola

Arcola, Virginia, United States

77 MW IT power

231 km away

### STACK Infrastructure NVA02

Manassas, Virginia, United States

85 MW IT power

Questions

## Microsoft-Nebius New Jersey, answered

Where it is, who owns it and how much power it uses, from the public record.

### Where is Microsoft-Nebius New Jersey?

Microsoft-Nebius New Jersey is in Vineland, New Jersey, United States, at 3963 S Lincoln Ave, Vineland, New Jersey. Epoch AI publishes its coordinates as 39.4267, -75.0168.

### Who owns Microsoft-Nebius New Jersey?

Epoch AI lists Nebius as its owner and Microsoft (Epoch AI rates this likely) as its user.

### How much power does Microsoft-Nebius New Jersey use?

Epoch AI estimates its IT power at 50 MW as of July 12, 2026, and its total facility power at 70 MW.

### Is Microsoft-Nebius New Jersey operating?

Yes. Epoch AI counts 1 building operating as of July 12, 2026.

Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).