Power Map · Operating, expanding

# Nscale Keflavik, Reykjanesbær

Nscale Keflavik is an SI data center in Reykjanesbær, Suðurnes, Iceland, owned by Nscale. [Epoch AI](https://epoch.ai/data/ai-data-centers) estimates its IT power at 5.1 MW as of July 27, 2026, with 1 building operating, and projects 10.2 MW by December 31, 2026. Its public timeline starts on July 8, 2022.

IT power
:   5.1 MW (Jul 27, 2026)

Facility power
:   6.6 MW

Status
:   Operating, expanding

Buildings operating
:   1

Where it is

## The site and its facts

Nscale Keflavik on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.

Place
:   Reykjanesbær, Suðurnes, Iceland

Address
:   Valhallarbraut 868, 262 Reykjanesbær, Iceland

Coordinates
:   63.9762° N, 22.5764° W

Owner
:   Nscale

Chips
:   B300

Compute
:   About 5,821 H100 equivalents (Epoch AI estimate, Jul 27, 2026)

Projected
:   10.2 MW IT power by December 31, 2026 (Epoch AI projection, not a fact yet)

Timeline

### Heat Watch

Over the last three summers NASA's MODIS read the ground here +0.6 °C against the land 5 to 10 km around it by day.

[Open Heat Watch](https://siscto.si/heat-watch/nscale-keflavik/)

### Lights On

NASA's night imagery read 42.8 of 100 over this site in October 2026, against 39.3 in October 2018, the first month read. Against a year before: +4.8 points. Light is not proof of what runs inside.

[Open Lights On](https://siscto.si/lights-on/?site=nscale-keflavik#view)

## Dated, from the public record

Epoch AI's dated notes on Nscale Keflavik, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.

**Jul 8, 2022**

> Site preparation begins for the southernmost KEF301 data center, here labeled as Building 1. [Heilbrigðiseftirlit Suðurnesja](https://hes.is/mengunareftirlit/leyfisveitingar-mengunareftirlit/starfsleyfi-i-auglysingu/page/2/) records authorization for Mannverk to demolish the existing structure at Valhallarbraut 872, the parcel later identified as KEF301.

No IT power yet (0 operating)

**May 1, 2023**

> Construction of Building 1 begins. [Reykjanesbær planning records](https://www.reykjanesbaer.is/static/files/Fundargerdir/umhverfis_skipulagsrad/2023/315/12.-2023.05.11-bref-til-skipulagsfulltrua-vegna-kef020.pdf) from May 11 explicitly state that the next construction phase of KEF301 was under construction by May 2023, so we model it as starting by the beginning of the month as a conservative estimate.

No IT power yet (0 operating)

**Jan 23, 2026**

> Nscale's GPU fit-out begins at the datacenter owned by Verne in Keflavik, Iceland. Estimated from [Verne's statement](https://www.linkedin.com/posts/verne-dc_phase-1-complete-in-just-three-months-75mw-activity-7452982122384027648-bxbA) that the first 7.5 MW deployment was completed in approximately three months; the exact start date was not disclosed.

No IT power yet (0 operating)

**Apr 23, 2026**

> First Nscale AI capacity operational. [Verne reports](https://www.linkedin.com/posts/verne-dc_phase-1-complete-in-just-three-months-75mw-activity-7452982122384027648-bxbA) the first 7.5 MW of Nscale capacity deployed with 128 racks, including 64 liquid-cooled NVIDIA GB300 racks. The AI capacity is assumed to be in the southernmost white building because it is the newest major data hall, has roughly 16 MW of capacity, and was the hall still being expanded most recently before Nscale's deployment; however, Verne and Nscale have not publicly confirmed the building assignment. [Digital 9](https://www.d9infrastructure.com/wp-content/uploads/2023/03/Digital-9-Infrastructure-Capital-Markets-Day-Presentation-March-2023.pdf) [Reykjanesbær](https://www.reykjanesbaer.is/static/files/Fundargerdir/umhverfis_skipulagsrad/2023/315/12.-2023.05.11-bref-til-skipulagsfulltrua-vegna-kef020.pdf)

5.1 MW (1 operating)

**Jun 30, 2026**

> 64-rack NVIDIA GB300 NVL72 cluster confirmed in production. [Nscale reports](https://www.nscale.com/blog/nscale-achieves-nvidia-exemplar-cloud-status-on-nvidia-gb300-nvl72) that production benchmarking was performed during June across all 64 racks. Month-end is used because the exact benchmark date was not disclosed.

5.1 MW (1 operating)

**Jul 27, 2026**

> Building 1 is operational (estimate). Full campus visibly externally complete from satellite imagery. Virtually no active construction visible.

5.1 MW (1 operating)

**Dec 31, 2026 (Projection)**

> Full 15 MW AI deployment projected operational. [Nscale and Verne announced](https://www.nscale.com/press-releases/nscale-and-verne) a 15 MW deployment across Verne's Iceland campus during 2026. We're modeling the end of the year as the completion date based on this announcement and the progress visible.

10.2 MW (1 operating)

Adopt a site

## Watch Nscale Keflavik

One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.

### The watcher

Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.

Approved updates · 0

- Approved updates show here with their date.

Sources

## Where the facts come from

The sources Epoch AI lists for this site, and the record itself.

- [Nscale / Verne 15 MW deployment announcement](https://www.nscale.com/press-releases/nscale-and-verne)

- [Nscale GB300 NVL72 production cluster confirmation](https://www.nscale.com/blog/nscale-achieves-nvidia-exemplar-cloud-status-on-nvidia-gb300-nvl72)

- [Verne Keflavík campus specifications](https://www.verne.co/iceland)

- [Lenovo Nscale Iceland AI infrastructure case study](https://www.lenovo.com/content/dam/lenovo/iso/customer-references-coe/global/en/case-studies/nscale-nvidia/lenovo_nscale_casestudy.pdf)

- [Epoch AI](https://epoch.ai/data/ai-data-centers), "AI data centers", the record for Nscale Keflavik (CC BY 4.0), retrieved November 10, 2026

Nearby

## The nearest SI data centers

The four closest sites on the Power Map, as the crow flies.

1,735 km away

### CoreWeave Norway

Øvrebø, Agder, Norway

42 MW IT power

1,831 km away

### Microsoft Narvik Norway

Bjerkvik, Narvik, Norway

IT power not stated

1,889 km away

### Google Waltham Cross

Cheshunt, Hertfordshire, United Kingdom

88 MW IT power

1,973 km away

### EcoDataCenter 2

Borlänge, Dalarna County, Sweden

IT power not stated

Questions

## Nscale Keflavik, answered

Where it is, who owns it and how much power it uses, from the public record.

### Where is Nscale Keflavik?

Nscale Keflavik is in Reykjanesbær, Suðurnes, Iceland, at Valhallarbraut 868, 262 Reykjanesbær, Iceland. Epoch AI publishes its coordinates as 63.9762, -22.5764.

### Who owns Nscale Keflavik?

Epoch AI lists Nscale as its owner.

### How much power does Nscale Keflavik use?

Epoch AI estimates its IT power at 5.1 MW as of July 27, 2026, and its total facility power at 6.6 MW. It projects 10.2 MW of IT power by December 31, 2026.

### Is Nscale Keflavik operating?

Yes, and it is growing. Epoch AI counts 1 building operating as of July 27, 2026, with more capacity on its timeline.

Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).