# OpenAI Stargate Shackelford, Abilene

OpenAI Stargate Shackelford is an SI data center in Abilene, Texas, United States, owned by Oracle and used by OpenAI. [Epoch AI](https://epoch.ai/data/ai-data-centers) tracks it as under construction: no building is operating yet as of September 4, 2026, and projects 1,400 MW by November 11, 2028. Its public timeline starts on August 1, 2025.

IT power
:   Not stated (Epoch AI)

Facility power
:   Not stated

Status
:   Under construction

Buildings operating
:   0

Where it is

## The site and its facts

OpenAI Stargate Shackelford on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.

Place
:   Abilene, Texas, United States

Address
:   175 Private Road 1604, Abilene, TX 79601, Shackelford County

Coordinates
:   32.5438° N, 99.5483° W

Owner
:   Oracle

Users
:   OpenAI

Project
:   Stargate

Projected
:   1,400 MW IT power by November 11, 2028 (Epoch AI projection, not a fact yet)

Timeline

### The Gigawatt Ledger

Stargate Shackelford County: 1.4 GW was announced for this project. Epoch AI tracks the site as under construction, with no building operating as of September 4, 2026.

[Open it in the Ledger](https://siscto.si/ledger/stargate-shackelford-county/)

### Heat Watch

Over the last three summers NASA's MODIS read the ground here +0.7 °C against the land 5 to 10 km around it by day.

[Open Heat Watch](https://siscto.si/heat-watch/openai-stargate-shackelford/)

### Lights On

NASA's night imagery read 62.4 of 100 over this site in October 2026, against 0.8 in October 2018, the first month read. Against a year before: +60.0 points. Light is not proof of what runs inside.

[Open Lights On](https://siscto.si/lights-on/?site=openai-stargate-shackelford#view)

## Dated, from the public record

Epoch AI's dated notes on OpenAI Stargate Shackelford, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.

**Aug 1, 2025**

> Land clearing begins.

No IT power yet (0 operating)

**Jan 18, 2026**

> The layout of Buildings 1-5 is visible. Steel framing has just started on Building 1.

No IT power yet (0 operating)

**Apr 14, 2026**

> Steel framing is underway for Buildings 1-3, and roofing is underway for Building 1.

No IT power yet (0 operating)

**Sep 4, 2026**

> Buildings 1-5 shells complete and fully roofed. Buildings 1-3 appear to be actively installing cooling and backup generators nearby. The pads for Buildings 6-10 to the north have also been visibly cleared, with foundations for Buildings 6 and 7 underway.

No IT power yet (0 operating)

**Aug 15, 2027 (Projection)**

> Building 1 is operational (estimate). TDLR lists the construction completion date for Building 1 as 2027-02-15. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.

140 MW (1 operating)

**Oct 19, 2027 (Projection)**

> Building 2 is operational (estimate). TDLR lists the construction completion date for Building 2 as 2027-04-19. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.

280 MW (2 operating)

**Nov 18, 2027 (Projection)**

> Building 3 is operational (estimate). TDLR lists the construction completion date for Building 3 as 2027-05-18. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.

420 MW (3 operating)

**Feb 11, 2028 (Projection)**

> Building 4 is operational (estimate). TDLR lists the construction completion date for Building 4 as 2027-08-11. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.

560 MW (4 operating)

**Mar 8, 2028 (Projection)**

> Building 5 is operational (estimate). TDLR lists the construction completion date for Building 5 as 2027-09-08. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.

700 MW (5 operating)

**Apr 4, 2028 (Projection)**

> Building 6 is operational (estimate). TDLR lists the construction completion date for Building 6 as 2027-10-04. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.

840 MW (6 operating)

**May 12, 2028 (Projection)**

> Building 7 is operational (estimate). TDLR lists the construction completion date for Building 7 as 2027-11-12. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.

980 MW (7 operating)

**Oct 17, 2028 (Projection)**

> Building 8 is operational (estimate). TDLR lists the construction completion date for Building 8 as 2028-04-17. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.

1,120 MW (8 operating)

**Oct 18, 2028 (Projection)**

> Building 9 is operational (estimate). TDLR lists the construction completion date for Building 9 as 2028-04-18. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.

1,260 MW (9 operating)

**Nov 11, 2028 (Projection)**

> Building 10 is operational (estimate). TDLR lists the construction completion date for Building 10 as 2028-05-11. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.

1,400 MW (10 operating)

Adopt a site

## Watch OpenAI Stargate Shackelford

One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.

### The watcher

Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.

Approved updates · 0

- Approved updates show here with their date.

Sources

## Where the facts come from

The sources Epoch AI lists for this site, and the record itself.

- [Vantage data center page with power capacity, number of buildings, and first building timeline](https://vantage-dc.com/data-center-locations/north-america/shackelford-county-tx)

- [OpenAI Stargate expansion announcement mentioning Shackelford site](https://openai.com/index/five-new-stargate-sites/)

- [Vantage LinkedIn post connecting the data center to OpenAI Stargate](https://web.archive.org/web/20260226203340/https://www.linkedin.com/posts/vantage-data-centers_ai-digitalinfrastructure-stargate-activity-7405254667062124544-FOcd/?rcm=ACoAAAmuuF4BvsgagH4Z8-Z8-0LaBPPY6467cAs)

- [TDLR filing for first building (other buildings are also on TDLR)](https://www.tdlr.texas.gov/TABS/Search/Project/TABS2026024094)

- [Epoch AI](https://epoch.ai/data/ai-data-centers), "AI data centers", the record for OpenAI Stargate Shackelford (CC BY 4.0), retrieved November 10, 2026

Nearby

## The nearest SI data centers

The four closest sites on the Power Map, as the crow flies.

23 km away

### Crusoe Abilene Expansion

Abilene, Texas, United States

IT power not stated

23 km away

### OpenAI Stargate Abilene

Abilene, Texas, United States

824 MW IT power

130 km away

### Anthropic Barber Lake

Colorado City, Texas, United States

IT power not stated

184 km away

### Coreweave Helios

Afton, Texas, United States

132 MW IT power

Questions

## OpenAI Stargate Shackelford, answered

Where it is, who owns it and how much power it uses, from the public record.

### Where is OpenAI Stargate Shackelford?

OpenAI Stargate Shackelford is in Abilene, Texas, United States, at 175 Private Road 1604, Abilene, TX 79601, Shackelford County. Epoch AI publishes its coordinates as 32.5438, -99.5483.

### Who owns OpenAI Stargate Shackelford?

Epoch AI lists Oracle as its owner and OpenAI as its user.

### How much power does OpenAI Stargate Shackelford use?

No building is operating yet, so Epoch AI states no IT power for it today. It projects 1,400 MW of IT power by November 11, 2028.

### Is OpenAI Stargate Shackelford operating?

Not yet. Epoch AI tracks it as under construction, with no building operating on its latest entry.

Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).