# Southgate Melbourne SI Data Center, Melbourne, Australia

> Southgate Melbourne is an SI data center in Melbourne, Victoria, Australia, owned by Firmus. Epoch AI puts its IT power at 41 MW (Aug 9, 2026).

Source: https://siscto.si/power-map/southgate-melbourne/
Updated: 2026-11-10

1. [Home](https://siscto.si/)
2. [Power Map](https://siscto.si/power-map/)
3. Southgate Melbourne

Power Map · Operating

# Southgate Melbourne, Melbourne

Southgate Melbourne is an SI data center in Melbourne, Victoria, Australia, owned by Firmus. [Epoch AI](https://epoch.ai/data/ai-data-centers) estimates its IT power at 41 MW as of August 9, 2026, with 1 building operating. Its public timeline starts on December 26, 2022.

IT power
:   41 MW (Aug 9, 2026)

Facility power
:   57 MW

Status
:   Operating

Buildings operating
:   1

Where it is

## The site and its facts

Southgate Melbourne on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.

Place
:   Melbourne, Victoria, Australia

Address
:   Not public

Coordinates
:   37.8172° S, 144.8433° E

Owner
:   Firmus

Chips
:   B300

Compute
:   About 46,488 H100 equivalents (Epoch AI estimate, Aug 9, 2026)

Timeline

### Heat Watch

Over the last three summers NASA's MODIS read the ground here +0.1 °C against the land 5 to 10 km around it by day.

[Open Heat Watch](https://siscto.si/heat-watch/southgate-melbourne/)

### Lights On

NASA's night imagery read 96.9 of 100 over this site in October 2026, against 76.0 in October 2018, the first month read. Against a year before: 0.0 points. The place was already bright at the first reading, so growth is harder to see. Light is not proof of what runs inside.

[Open Lights On](https://siscto.si/lights-on/?site=southgate-melbourne#view)

## Dated, from the public record

Epoch AI's dated notes on Southgate Melbourne, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.

**Dec 26, 2022**

> Building 1 site is cleared/vacant land; no construction visible yet (based on Google Earth historical imagery).

No IT power yet (0 operating)

**Oct 28, 2025**

> Satellite imagery shows 30 fully installed air-cooled chillers (20 fans each) on the roof, with room for many more. In the same month, Firmus [reported](https://firmus.co/newsroom/southgate-expansion) that Project Southgate's "first stages are under construction in Tasmania and Melbourne". So we don't think the Southgate part of the building is operational yet.

No IT power yet (0 operating)

**May 11, 2026**

> Building 1's cooling capacity increased to 53 air-cooled chillers (20 fans each), up from 30 in Oct 2025. This is more than enough for the announced 18,400 GB300 GPUs, but construction does not quite look complete, so we expect another 3 months until it's operational.

No IT power yet (0 operating)

**Aug 9, 2026**

> Building 1 is operational (estimate). No additional chip deployment beyond the 18,400 GB300 GPUs has been publicly confirmed, so we continue to report the disclosed capacity allocated to Project Southgate, rather than speculate on further buildout.

41 MW (1 operating)

Adopt a site

## Watch Southgate Melbourne

One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.

### The watcher

Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.

Approved updates · 0

- Approved updates show here with their date.

Sources

## Where the facts come from

The sources Epoch AI lists for this site, and the record itself.

- [Firmus Expands Project Southgate Across Australia](https://firmus.co/newsroom/southgate-expansion)

- [Firmus Signs Multi-Year Agreement with Global Hyperscale Customer at Project Southgate](https://firmus.co/newsroom/firmus-signs-multi-year-agreement-with-global-hyperscale-customer-at-project-southgate)

- [CDC Melbourne](https://cdc.com/locations/melbourne/)

- [Epoch AI](https://epoch.ai/data/ai-data-centers), "AI data centers", the record for Southgate Melbourne (CC BY 4.0), retrieved November 10, 2026

Nearby

## The nearest SI data centers

The four closest sites on the Power Map, as the crow flies.

6,021 km away

### Oracle Batam

Batam, Riau Islands, Indonesia

72 MW IT power

6,077 km away

### DayOne Nusajaya

Johor Bahru, Johor, Malaysia

473 MW IT power

6,080 km away

### DayOne Kempas

Kempas, Johor, Malaysia

421.7 MW IT power

6,099 km away

### YTL Johor

Kulai, Johor, Malaysia

113 MW IT power

Questions

## Southgate Melbourne, answered

Where it is, who owns it and how much power it uses, from the public record.

### Where is Southgate Melbourne?

Southgate Melbourne is in Melbourne, Victoria, Australia. Epoch AI publishes its coordinates as -37.8172, 144.8433.

### Who owns Southgate Melbourne?

Epoch AI lists Firmus as its owner.

### How much power does Southgate Melbourne use?

Epoch AI estimates its IT power at 41 MW as of August 9, 2026, and its total facility power at 57 MW.

### Is Southgate Melbourne operating?

Yes. Epoch AI counts 1 building operating as of August 9, 2026.

Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).