# VNET Bayin Ulanqab SI Data Center, Ulanqab, China | $SIS

> VNET Bayin Ulanqab is an SI data center in Ulanqab, Inner Mongolia, China, owned by ByteDance. Epoch AI puts its IT power at 221 MW (May 6, 2026).

Source: https://siscto.si/power-map/vnet-bayin-ulanqab/
Updated: 2026-11-10

1. [Home](https://siscto.si/)
2. [Power Map](https://siscto.si/power-map/)
3. VNET Bayin Ulanqab

Power Map · Operating, expanding

# VNET Bayin Ulanqab, Ulanqab

VNET Bayin Ulanqab is an SI data center in Ulanqab, Inner Mongolia, China, owned by ByteDance (Epoch AI rates this speculative) and used by ByteDance (Epoch AI rates this speculative). [Epoch AI](https://epoch.ai/data/ai-data-centers) estimates its IT power at 221 MW as of May 6, 2026, with 4 buildings operating, and projects 700 MW by September 1, 2027. Its public timeline starts on March 15, 2024.

IT power
:   221 MW (May 6, 2026)

Facility power
:   252 MW

Status
:   Operating, expanding

Buildings operating
:   4

Where it is

## The site and its facts

VNET Bayin Ulanqab on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.

Place
:   Ulanqab, Inner Mongolia, China

Address
:   Bayin, Ulanqab, China

Coordinates
:   40.9811° N, 113.3143° E

Owner
:   ByteDance (Epoch AI rates this speculative)

Users
:   ByteDance (Epoch AI rates this speculative)

Project
:   10 GW Hyperscale 2.0

Chips
:   Ascend 910C

Compute
:   About 122,789 H100 equivalents (Epoch AI estimate, May 6, 2026)

Projected
:   700 MW IT power by September 1, 2027 (Epoch AI projection, not a fact yet)

Timeline

### Heat Watch

Over the last three summers NASA's MODIS read the ground here +0.7 °C against the land 5 to 10 km around it by day.

[Open Heat Watch](https://siscto.si/heat-watch/vnet-bayin-ulanqab/)

### Lights On

NASA's night imagery read 36.5 of 100 over this site in October 2026, against 1.4 in October 2018, the first month read. Against a year before: -1.3 points. Light is not proof of what runs inside.

[Open Lights On](https://siscto.si/lights-on/?site=vnet-bayin-ulanqab#view)

## Dated, from the public record

Epoch AI's dated notes on VNET Bayin Ulanqab, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.

**Mar 15, 2024**

> Land clearing begins late March, as can be seen in satellite images (eastern part: buildings 1 & 2). VNET officially [announces](https://web.archive.org/web/20250620154431/https://www.vnet.com/portal/article/index/cid/14/id/876.html) its signing ceremony with the Ulanqab municipal government and Shandong Hi-Speed Holdings.

No IT power yet (0 operating)

**Feb 5, 2025**

> Satellite imagery shows five buildings (1, 2, 3, 4, 5) under construction. Chillers are in place, but no roof is complete for any building.

No IT power yet (0 operating)

**Jul 1, 2025**

> Building 1 is operational, based on a 3-month fit-out period after structural completion in April, as can be seen from satellite imagery.

38 MW (1 operating)

**Aug 1, 2025**

> Satellite imagery shows that in total nine buildings have started construction, with building 1 being the only one operational. Buildings 2 and 5 are structurally complete, and the final roofs for buildings 3 and 4 have begun.

38 MW (1 operating)

**Nov 1, 2025**

> Buildings 2 and 5 are operational, based on a 3-month fit-out period after structural completion in August, as can be seen from satellite imagery. Land clearing for the northern part of campus (buildings 10 and 11) has started.

171 MW (3 operating)

**Dec 1, 2025**

> Building 4 is operational, similarly based on a 3-month fit-out period after structural completion in September, as seen from satellite imagery.

221 MW (4 operating)

**Mar 5, 2026**

> Satellite imagery shows four operational buildings (1, 2, 4, 5), and the western part of campus (6, 7, 8, 9) has made significant construction progress. The foundation for the northern part of campus (10, 11) has started.

221 MW (4 operating)

**May 6, 2026**

> Satellite imagery shows building 9 has completed all its chillers, with only its roof remaining. Previous building completion timelines would imply this building will be operational by the end of 2026.

221 MW (4 operating)

**Sep 1, 2027 (Projection)**

> Estimated: the nine-building section of the campus is projected to be fully operational by late 2027 or early 2028. VNET's eastern cluster (buildings 1-5) took roughly a year each from clearing to operational based on satellite imagery. The western cluster (buildings 6-9) was cleared in late 2024 but as of mid-2026 is not yet structurally complete, putting each on track for ~2 years from clearing to operational. Buildings 10 and 11 are projected to be completed sometime later. Comparable data centers in Ulanqab are expected to take at least 6 months per phase ([China Unicom](https://archive.ph/bJDHl)).

700 MW (9 operating)

Adopt a site

## Watch VNET Bayin Ulanqab

One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.

### The watcher

Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.

Approved updates · 0

- Approved updates show here with their date.

Sources

## Where the facts come from

The sources Epoch AI lists for this site, and the record itself.

- [Epoch AI](https://epoch.ai/data/ai-data-centers), "AI data centers", the record for VNET Bayin Ulanqab (CC BY 4.0), retrieved November 10, 2026

Nearby

## The nearest SI data centers

The four closest sites on the Power Map, as the crow flies.

7 km away

### Envision Galaxy Ulanqab

Ulanqab, Inner Mongolia, China

118 MW IT power

121 km away

### Alibaba Zhangbei

Zhangbei, Hebei, China

169 MW IT power

134 km away

### Huawei Horinger

Hohhot, Inner Mongolia, China

169.9 MW IT power

1,166 km away

### Huawei Wuhu

Wuhu, Anhui, China

197 MW IT power

Questions

## VNET Bayin Ulanqab, answered

Where it is, who owns it and how much power it uses, from the public record.

### Where is VNET Bayin Ulanqab?

VNET Bayin Ulanqab is in Ulanqab, Inner Mongolia, China, at Bayin, Ulanqab, China. Epoch AI publishes its coordinates as 40.9811, 113.3143.

### Who owns VNET Bayin Ulanqab?

Epoch AI lists ByteDance (Epoch AI rates this speculative) as its owner and ByteDance (Epoch AI rates this speculative) as its user.

### How much power does VNET Bayin Ulanqab use?

Epoch AI estimates its IT power at 221 MW as of May 6, 2026, and its total facility power at 252 MW. It projects 700 MW of IT power by September 1, 2027.

### Is VNET Bayin Ulanqab operating?

Yes, and it is growing. Epoch AI counts 4 buildings operating as of May 6, 2026, with more capacity on its timeline.

Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).