# YTL Johor SI Data Center, Kulai, Malaysia | $SIS

> YTL Johor is an SI data center in Kulai, Johor, Malaysia. Epoch AI puts its IT power at 113 MW (Jul 13, 2026). Map, timeline, sources and its watcher.

Source: https://siscto.si/power-map/ytl-johor/
Updated: 2026-11-10

1. [Home](https://siscto.si/)
2. [Power Map](https://siscto.si/power-map/)
3. YTL Johor

Power Map · Operating, expanding

# YTL Johor, Kulai

YTL Johor is an SI data center in Kulai, Johor, Malaysia. [Epoch AI](https://epoch.ai/data/ai-data-centers) estimates its IT power at 113 MW as of July 13, 2026, with 2 buildings operating, and projects 284 MW by August 1, 2028. Its public timeline starts on November 1, 2023.

IT power
:   113 MW (Jul 13, 2026)

Facility power
:   155 MW

Status
:   Operating, expanding

Buildings operating
:   2

Where it is

## The site and its facts

YTL Johor on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.

Place
:   Kulai, Johor, Malaysia

Address
:   YTL Green Data Centers, Kulai, Johor, Malaysia

Coordinates
:   1.6183° N, 103.5192° E

Owner
:   Not public

Chips
:   B200, B300

Compute
:   About 153,532 H100 equivalents (Epoch AI estimate, Jul 13, 2026)

Projected
:   284 MW IT power by August 1, 2028 (Epoch AI projection, not a fact yet)

Timeline

### Heat Watch

Over the last three summers NASA's MODIS read the ground here +0.5 °C against the land 5 to 10 km around it by day.

[Open Heat Watch](https://siscto.si/heat-watch/ytl-johor/)

### Lights On

NASA's night imagery read 26.3 of 100 over this site in October 2026, against 1.7 in October 2018, the first month read. Against a year before: +9.3 points. Light is not proof of what runs inside.

[Open Lights On](https://siscto.si/lights-on/?site=ytl-johor#view)

## Dated, from the public record

Epoch AI's dated notes on YTL Johor, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.

**Nov 1, 2023**

> Land clearing begins for Building 1.

No IT power yet (0 operating)

**Nov 3, 2025**

> Building 1 is operational with Nvidia GB200s, according to the [local investment development authority](https://www.midf.com.my/sites/corporate/files/2025-11/ytl_power-cu-all_systems_go_for_ai_dc-mbsbr-031125.pdf).

20 MW (1 operating)

**Mar 14, 2026**

> Building 2 is operational, assuming 3 months to structural completion plus 3 months fit-out after this [video](https://youtu.be/HODHjDbFt10?si=749v3V9LD4gkTDE2&t=212). Solar panels are also being installed to the north west of the campus.

100 MW (2 operating)

**May 15, 2026**

> Building 1 added 4 two-fan cooling towers (config 3), installed mid May of 2026. This capacity is not reflected in any disclosure (the building is still reported at 20MW IT load).

113 MW (2 operating)

**Jul 13, 2026**

> Satellite imagery confirms Buildings 1 and 2 are structurally complete. Buildings 3 and 4 are underway, and construction equipment can be seen on the plot for Building 5. Extensive solar panel arrays have been built out.

113 MW (2 operating)

**Aug 1, 2028 (Projection)**

> Estimate: all five AI buildings operational. The mean time from first ground activity to operational across buildings 1 and 2 was 25.6 (25.1 and 26.0 months). Buildings 3 and 4 have been underway since Mar 2026, and building 5's plot only has construction equipment as of Jul 2026, so +25 months gives Aug 2028 as campus completion. Company guidance is faster: capacity "expected to double to 600MW by the end of 2027" per [Kenanga via The Star](https://www.thestar.com.my/business/business-news/2026/06/24/dc-expansion-to-lift-ytl-power); JDC4 phases Sep-25/Sep-26/Sep-27 per [MIDF](https://www.midf.com.my/sites/corporate/files/2025-11/ytl_power-cu-all_systems_go_for_ai_dc-mbsbr-031125.pdf). The resulting ~429MW IT independently matches Kenanga's "expected IT load of 430MW" for the 600MW park ([Kenanga, 9 Dec 2024](https://www.kenanga.com.my/wp-content/uploads/2024/12/YTLPOWR-241209-CU-Kenanga.pdf)).

284 MW (5 operating)

Adopt a site

## Watch YTL Johor

One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.

### The watcher

Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.

Approved updates · 0

- Approved updates show here with their date.

Sources

## Where the facts come from

The sources Epoch AI lists for this site, and the record itself.

- [Official YTL page for the campus](https://ytldatacenters.com/locations/malaysia/)

- [YTL press release on the use of GB200's](https://www.ytlpowerinternational.com/press-releases/ytl-creates-one-of-the-worlds-most-advanced-supercomputers-powered-by-nvidia-grace-blackwell-based-dgx-cloud/)

- [Aerial footage including the campus](https://www.youtube.com/watch?v=HODHjDbFt10)

- [Epoch AI](https://epoch.ai/data/ai-data-centers), "AI data centers", the record for YTL Johor (CC BY 4.0), retrieved November 10, 2026

Nearby

## The nearest SI data centers

The four closest sites on the Power Map, as the crow flies.

14 km away

### Bridge Data Centres MY06

Kulai, Johor, Malaysia

243 MW IT power

23 km away

### DayOne Nusajaya

Johor Bahru, Johor, Malaysia

473 MW IT power

23 km away

### DayOne Kempas

Kempas, Johor, Malaysia

421.7 MW IT power

81 km away

### Oracle Batam

Batam, Riau Islands, Indonesia

72 MW IT power

Questions

## YTL Johor, answered

Where it is, who owns it and how much power it uses, from the public record.

### Where is YTL Johor?

YTL Johor is in Kulai, Johor, Malaysia, at YTL Green Data Centers, Kulai, Johor, Malaysia. Epoch AI publishes its coordinates as 1.6183, 103.5192.

### Who owns YTL Johor?

Epoch AI does not name an owner yet.

### How much power does YTL Johor use?

Epoch AI estimates its IT power at 113 MW as of July 13, 2026, and its total facility power at 155 MW. It projects 284 MW of IT power by August 1, 2028.

### Is YTL Johor operating?

Yes, and it is growing. Epoch AI counts 2 buildings operating as of July 13, 2026, with more capacity on its timeline.

Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).