# ERCOT data center power requests: The Queue

> How much power data centers are asking ERCOT for: about 474 GW of large load requests as of June 2026. Every figure with its definition, date and source.

Source: https://siscto.si/queue/ercot/
Updated: 2026-11-26

1. [Home](https://siscto.si/)
2. [The Queue](https://siscto.si/queue/)
3. ERCOT

The Queue · ERCOT

# The queue at ERCOT

ERCOT counts every request from a load of 75 MW or more at one point of interconnection. Its count grew from 63 GW in December 2024 to about 474 GW in June 2026, most of it data centers. In July 2026 the old process closed and a one time batch study took over, with a narrower count of its own.

Figures on file
:   [12](https://siscto.si/queue/ercot/#figures)

Newest figure
:   [Nov 5, 2026](https://siscto.si/queue/ercot/#figures)

Power Map sites inside
:   [14](https://siscto.si/queue/ercot/#sites)

Live on Grid Watch
:   [Yes](https://siscto.si/grid-watch/#ercot)

Over time

## Where the source repeats

Each line joins one measure from one source at the dates the source gave, and nothing else. Every number keeps its own definition, date and source. Figures with different definitions are never added together, and a chart joins only the same measure from the same source.

Every figure

## ERCOT, figure by figure

Newest first. Each card opens its source document.

- **Requested by the 245 large loads in the community impact survey**: about 166 GW, as of November 5, 2026 (asked for). Requested interconnection capacity of the 245 large loads (75 MW or more) that answered ERCOT's data center state and community impact survey. Preliminary as of November 5, 2026. Source: [ERCOT, Data Center State and Community Impact RFI: Preliminary Summary, PUC Open Meeting](https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf), Nov 5, 2026.
- **Batch Zero, conditional studied load**: 127.9 GW, as of September 3, 2026 (in study). 158 projects that met the qualifications to be conditionally included as studied load, as of September 3, 2026. Final inclusion follows ERCOT's verification and audit, due by December 10, 2026. Source: [ERCOT, Item 14: Batch Zero Update, Board of Directors, September 14 to 15, 2026](https://www.ercot.com/files/docs/2026/09/11/14-Batch-Zero-Update.pdf), Sep 11, 2026.
- **Batch Zero, conditional base load**: 66.4 GW, as of September 3, 2026 (in study). 204 projects that met the qualifications to be conditionally included as base load, in the classification ERCOT sent on September 3, 2026. A different group from the studied load below: the two are never added here. Source: [ERCOT, Item 14: Batch Zero Update, Board of Directors, September 14 to 15, 2026](https://www.ercot.com/files/docs/2026/09/11/14-Batch-Zero-Update.pdf), Sep 11, 2026.
- **Eligible for the Batch Zero study**: about 205 GW, as of July 28, 2026 (in study). Large load eligible for inclusion in Batch Zero, ERCOT's one time study under Senate Bill 6, based on existing studies. Preliminary, as of July 28, 2026. Source: [ERCOT, ERCOT update to the Texas House Committee on State Affairs, August 19, 2026](https://www.ercot.com/files/docs/2026/08/19/ERCOTPanel1DataCenters.pdf), Aug 19, 2026.
- **Large load interconnection requests**: about 474 GW, as of June 2026 (asked for). Large loads seeking interconnection, as of June 2026. ERCOT says about 90% are data centers. This is the last count of the old process, which ended on July 10, 2026. Source: [ERCOT, ERCOT update to the Texas Senate, July 29, 2026: Assessing the grid](https://www.ercot.com/files/docs/2026/07/29/ERCOT-Senate-July-29-Panel-1-Assessing-The-Grid.pdf), Jul 29, 2026.
- **Large load interconnection requests**: 438 GW, as of the board deck of May 24, 2026 (asked for). Requests tracked through the PGRR 115 based process, as stated in the deck for the June 1 to 2, 2026 board meeting. The deck gives no separate as of date. ERCOT notes the vast majority have no studies submitted. Source: [ERCOT, Item 8: Interconnection and Grid Analysis Update, Board of Directors, June 1 to 2, 2026](https://www.ercot.com/files/docs/2026/05/24/8-Interconnection-and-Grid-Analysis-Update.pdf), May 24, 2026.
- **Large load interconnection requests**: about 410 GW, as of March 26, 2026 (asked for). Large loads seeking interconnection, as of March 26, 2026. ERCOT says about 87% are data centers and that the count rose 178 GW since the end of 2025. Source: [ERCOT, Item 9: Interconnection and Grid Analysis Update, Board of Directors](https://www.ercot.com/files/docs/2026/04/13/9-Interconnection-and-Grid-Analysis-Update.pdf), Apr 13, 2026.
- **Approved to energize**: 8,876 MW, as of February 25, 2026 (approved). Megawatts that had received approval to energize, in ERCOT's status update of February 25, 2026. Source: [ERCOT, Large Load Interconnection Status Update to the Technical Advisory Committee](https://www.ercot.com/files/docs/2026/03/05/February-TAC-Report.pdf), Feb 25, 2026.
- **Large load interconnection requests**: about 226 GW, as of November 18, 2025 (asked for). Large loads seeking interconnection, as of November 18, 2025. ERCOT adds that about 128,000 MW of these had not yet submitted planning studies for review. Source: [ERCOT, ERCOT Monthly, November 2025: Large Load Interconnection Requests Update](https://www.ercot.com/files/docs/2025/12/19/ERCOT-Monthly-November-2025-FINAL.pdf), Dec 19, 2025.
- **Observed energized**: about 5.3 GW, as of November 18, 2025 (running). Large loads approved to energize that ERCOT observed operating, as of November 18, 2025. Source: [ERCOT, ERCOT Monthly, November 2025: Large Load Interconnection Requests Update](https://www.ercot.com/files/docs/2025/12/19/ERCOT-Monthly-November-2025-FINAL.pdf), Dec 19, 2025.
- **Approved to energize**: about 7.5 GW, as of November 18, 2025 (approved). Large loads ERCOT had approved to energize, as of November 18, 2025: about 5,300 MW observed energized plus about 2,200 MW approved but not yet operating, in ERCOT's own split. Source: [ERCOT, ERCOT Monthly, November 2025: Large Load Interconnection Requests Update](https://www.ercot.com/files/docs/2025/12/19/ERCOT-Monthly-November-2025-FINAL.pdf), Dec 19, 2025.
- **Large load interconnection requests**: 63 GW, as of December 2024 (asked for). Loads of 75 MW or more seeking interconnection to the ERCOT system, as ERCOT tracks them. ERCOT gives this December 2024 figure for reference in its November 2025 update. Source: [ERCOT, ERCOT Monthly, November 2025: Large Load Interconnection Requests Update](https://www.ercot.com/files/docs/2025/12/19/ERCOT-Monthly-November-2025-FINAL.pdf), Dec 19, 2025.

On August 3, 2026, after a directive from the Governor, ERCOT paused approvals to energize data centers and crypto facilities of 75 MW or more while it verifies and audits the loads in Batch Zero (ERCOT, Item 14, September 2026).

Utilities

## The utilities in this grid

A utility's own count of the load it has agreed to serve, from its own filings.

### American Electric Power (AEP)

AEP reports, each quarter, the new load backed by signed customer agreements across its companies in PJM, SPP and ERCOT. The count went from 24 GW in July 2025 to 69 GW through 2030 in July 2026, and to 84 GW by 2031 in October 2026.

- **Contracted load by 2031**: 84 GW, as of October 28, 2026 (under contract). After 15 GW of new load commitments in the third quarter of 2026. AEP moved the horizon to 2031, so this figure is kept off the 2030 line. Source: [AEP, Third-quarter 2026 earnings release (SEC Form 8-K, exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/4904/000000490426000069/a3q20268kpressreleaseex991.htm), Oct 28, 2026.
- **Contracted load growth through 2030**: 69 GW, as of July 30, 2026 (under contract). After 6 GW more of signed load agreements in the second quarter of 2026, mainly in Texas. Source: [AEP, Second-quarter 2026 earnings release (SEC Form 8-K, exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/4904/000000490426000055/a2q20268kpressreleaseex991.htm), Jul 30, 2026.
- **New load by 2030 under signed agreements**: 63 GW, as of May 5, 2026 (under contract). After 7 GW of new load agreements signed in the first quarter of 2026. AEP Texas accounts for 41 GW of the commitments. Source: [AEP, First-quarter 2026 earnings release (SEC Form 8-K, exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/4904/000000490426000031/a1q20268kpressreleaseex991.htm), May 5, 2026.
- **New load by 2030 under signed agreements**: 56 GW, as of February 12, 2026 (under contract). Incremental load by 2030, all backed by signed agreements. AEP Texas alone rose from 13 GW to 36 GW, backed by signed letters of agreement. Source: [AEP, Fourth-quarter and full-year 2025 earnings release (SEC Form 8-K, exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/4904/000000490426000011/a4q20258kpressreleaseex991.htm), Feb 12, 2026.
- **New load by 2030 under customer agreements**: 28 GW, as of October 29, 2025 (under contract). Load additions by 2030 backed by electric service agreements or letters of agreement, supported by an additional 190 GW of load requests. Source: [AEP, Third-quarter 2025 earnings release (SEC Form 8-K, exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/4904/000000490425000169/a3q20258kpressreleaseex991.htm), Oct 29, 2025.
- **New load by 2030 under customer agreements**: 24 GW, as of July 30, 2025 (under contract). Incremental load by 2030 under customer agreements with firm financial commitments, mainly in Indiana, Ohio and Texas. AEP also cited more than 190 GW of load requests at various stages. Source: [AEP, Second-quarter 2025 earnings release (SEC Form 8-K, exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/4904/000000490425000139/a2q20258kpressreleaseex991.htm), Jul 30, 2025.

On the Power Map

## SI data centers inside ERCOT

Each card opens the site on the Power Map. Status and power are Epoch AI's, read November 10, 2026.

- [OpenAI Stargate Abilene](https://siscto.si/power-map/openai-stargate-abilene/): Abilene, Texas. 824 MW of IT power (Epoch AI, as of Nov 1, 2026).
- [CoreWeave Denton TX](https://siscto.si/power-map/coreweave-denton-tx/): Denton, Texas. 262 MW of IT power (Epoch AI, as of Sep 1, 2026).
- [Meta Temple](https://siscto.si/power-map/meta-temple/): Temple, Texas. 178 MW of IT power (Epoch AI, as of Sep 30, 2026).
- [Coreweave Helios](https://siscto.si/power-map/coreweave-helios/): Afton, Texas. 132 MW of IT power (Epoch AI, as of Aug 30, 2026).
- [Google Midlothian](https://siscto.si/power-map/google-midlothian/): Midlothian, Texas. 103 MW of IT power (Epoch AI, as of Jul 1, 2026).
- [Google Red Oak](https://siscto.si/power-map/google-red-oak/): Red Oak, Texas. 77 MW of IT power (Epoch AI, as of Feb 6, 2026).
- [Microsoft SAT40](https://siscto.si/power-map/microsoft-sat40/): San Antonio, Texas. 75 MW of IT power (Epoch AI, as of Feb 4, 2026).
- [Microsoft SAT14](https://siscto.si/power-map/microsoft-sat14/): San Antonio, Texas. 47 MW of IT power (Epoch AI, as of Mar 31, 2026).
- [Vantage TX1](https://siscto.si/power-map/vantage-tx1/): San Antonio, Texas. 32 MW of IT power (Epoch AI, as of Feb 15, 2026).
- [Anthropic Barber Lake](https://siscto.si/power-map/anthropic-barber-lake/): Colorado City, Texas. No building running yet (Epoch AI, as of Jul 30, 2026).
- [Crusoe Abilene Expansion](https://siscto.si/power-map/crusoe-abilene-expansion/): Abilene, Texas. No building running yet (Epoch AI, as of Jan 15, 2026).
- [Goodnight](https://siscto.si/power-map/goodnight/): Claude, Texas. No building running yet (Epoch AI, as of Apr 16, 2026).
- [OpenAI Stargate Milam](https://siscto.si/power-map/openai-stargate-milam/): Burlington, Texas. No building running yet (Epoch AI, as of Mar 23, 2026).
- [OpenAI Stargate Shackelford](https://siscto.si/power-map/openai-stargate-shackelford/): Abilene, Texas. No building running yet (Epoch AI, as of Sep 4, 2026).

[The Power Map](https://siscto.si/power-map/)

14 Power Map sites fall inside this grid's area on the federal Control Areas map (HIFLD Open, year 2018 boundaries). 2 of them sit where the map draws two areas over the same spot; they are listed under each. A site's place on that map is a guide, not proof of which utility serves it.

Sources

## Where every figure comes from

Each source was opened and read on November 23, 2026.

validated May 15, 2020, read Nov 23, 2026

### U.S. Department of Homeland Security, HIFLD Open (public copy)

Control Areas (balancing authority areas), sourced from FERC 714, EIA 860 and EIA 861, year 2018

[Open the source](https://services5.arcgis.com/HDRa0B57OVrv2E1q/ArcGIS/rest/services/Control_Areas/FeatureServer/0)

Jul 30, 2025, read Nov 23, 2026

### AEP

Second-quarter 2025 earnings release (SEC Form 8-K, exhibit 99.1)

[Open the source](https://www.sec.gov/Archives/edgar/data/4904/000000490425000139/a2q20258kpressreleaseex991.htm)

Oct 29, 2025, read Nov 23, 2026

### AEP

Third-quarter 2025 earnings release (SEC Form 8-K, exhibit 99.1)

[Open the source](https://www.sec.gov/Archives/edgar/data/4904/000000490425000169/a3q20258kpressreleaseex991.htm)

Dec 19, 2025, read Nov 23, 2026

### ERCOT

ERCOT Monthly, November 2025: Large Load Interconnection Requests Update

[Open the source](https://www.ercot.com/files/docs/2025/12/19/ERCOT-Monthly-November-2025-FINAL.pdf)

Feb 12, 2026, read Nov 23, 2026

### AEP

Fourth-quarter and full-year 2025 earnings release (SEC Form 8-K, exhibit 99.1)

[Open the source](https://www.sec.gov/Archives/edgar/data/4904/000000490426000011/a4q20258kpressreleaseex991.htm)

Feb 25, 2026, read Nov 23, 2026

### ERCOT

Large Load Interconnection Status Update to the Technical Advisory Committee

[Open the source](https://www.ercot.com/files/docs/2026/03/05/February-TAC-Report.pdf)

Apr 13, 2026, read Nov 23, 2026

### ERCOT

Item 9: Interconnection and Grid Analysis Update, Board of Directors

[Open the source](https://www.ercot.com/files/docs/2026/04/13/9-Interconnection-and-Grid-Analysis-Update.pdf)

May 5, 2026, read Nov 23, 2026

### AEP

First-quarter 2026 earnings release (SEC Form 8-K, exhibit 99.1)

[Open the source](https://www.sec.gov/Archives/edgar/data/4904/000000490426000031/a1q20268kpressreleaseex991.htm)

May 24, 2026, read Nov 23, 2026

### ERCOT

Item 8: Interconnection and Grid Analysis Update, Board of Directors, June 1 to 2, 2026

[Open the source](https://www.ercot.com/files/docs/2026/05/24/8-Interconnection-and-Grid-Analysis-Update.pdf)

Jul 29, 2026, read Nov 23, 2026

### ERCOT

ERCOT update to the Texas Senate, July 29, 2026: Assessing the grid

[Open the source](https://www.ercot.com/files/docs/2026/07/29/ERCOT-Senate-July-29-Panel-1-Assessing-The-Grid.pdf)

Jul 30, 2026, read Nov 23, 2026

### AEP

Second-quarter 2026 earnings release (SEC Form 8-K, exhibit 99.1)

[Open the source](https://www.sec.gov/Archives/edgar/data/4904/000000490426000055/a2q20268kpressreleaseex991.htm)

Aug 19, 2026, read Nov 23, 2026

### ERCOT

ERCOT update to the Texas House Committee on State Affairs, August 19, 2026

[Open the source](https://www.ercot.com/files/docs/2026/08/19/ERCOTPanel1DataCenters.pdf)

Sep 11, 2026, read Nov 23, 2026

### ERCOT

Item 14: Batch Zero Update, Board of Directors, September 14 to 15, 2026

[Open the source](https://www.ercot.com/files/docs/2026/09/11/14-Batch-Zero-Update.pdf)

Oct 28, 2026, read Nov 23, 2026

### AEP

Third-quarter 2026 earnings release (SEC Form 8-K, exhibit 99.1)

[Open the source](https://www.sec.gov/Archives/edgar/data/4904/000000490426000069/a3q20268kpressreleaseex991.htm)

Nov 5, 2026, read Nov 23, 2026

### ERCOT

Data Center State and Community Impact RFI: Preliminary Summary, PUC Open Meeting

[Open the source](https://www.ercot.com/files/docs/2026/11/05/Community-Impact-RFI-PUC-Update.pdf)

retrieved Nov 10, 2026

### Epoch AI

The Power Map's site list, towns, status and power come from Epoch AI's open data set of data centers, licensed CC BY 4.0.

[Open the source](https://epoch.ai/data/ai-data-centers)

Keep going

## The same grid, other records

Every page of the set reads a different public record.

### Power Map

Every SI data center public data can confirm, with its power.

### Gigawatt Ledger

What was announced against what is confirmed energized.

### Onsite Power Watch

The plants built to run data centers directly.

### Grid Watch

Live demand on the grids that host the most sites.

### Bill Watch

Home power prices in every state with a site.

Questions

## ERCOT, answered

The figures, the stages and the limits.

### How much power are data centers asking ERCOT for?

ERCOT counts every request from a load of 75 MW or more at one point of interconnection. Its count grew from 63 GW in December 2024 to about 474 GW in June 2026, most of it data centers. In July 2026 the old process closed and a one time batch study took over, with a narrower count of its own. Each figure on this page has its own definition and date; figures with different definitions are never added together.

### Is all of that going to be built?

No figure here says what will be built. Requests are what customers asked for; many requests are speculative, duplicated across grids or withdrawn. The stages on this page (asked for, in study, approved, under contract, running) are the source's own words.

### Which data centers are inside ERCOT?

The [Power Map](https://siscto.si/power-map/) lists 14 sites inside ERCOT's area on the federal Control Areas map. See the list below; each links to its page.

### Where do the figures come from?

From the grid operator's own board decks, filings and reports and the utilities' own filings with the SEC, each read on November 23, 2026. The links are on every figure.

### How hard is ERCOT running right now?

[Grid Watch](https://siscto.si/grid-watch/#ercot) shows ERCOT's demand hour by hour from the EIA, against its own forecast and its record.

Join the takeover

## Read the queue with us

Open a source, check a figure yourself and bring what you find to the $SIS Telegram.

[Buy $SIS](https://pump.fun/coin/FdKdpz11GsTofLaNiddrhxrsE4APZYSSfLFqQ9YKpump)

[Join the Telegram](https://t.me/sisctotg)

[Follow on X](https://x.com/entersiscto)

[Swap on Jupiter](https://jup.ag/swap/SOL-FdKdpz11GsTofLaNiddrhxrsE4APZYSSfLFqQ9YKpump)