# The queue at NYISO

NYISO counts the large load projects in its interconnection queue. Six projects with 1,045 MW were in it in 2022; by May 1, 2026 there were 51 projects that would add nearly 12,670 MW.

Figures on file
:   [3](https://siscto.si/queue/nyiso/#figures)

Newest figure
:   [May 1, 2026](https://siscto.si/queue/nyiso/#figures)

Power Map sites inside
:   [2](https://siscto.si/queue/nyiso/#sites)

Live on Grid Watch
:   [Yes](https://siscto.si/grid-watch/#nyiso)

Over time

## Where the source repeats

Each line joins one measure from one source at the dates the source gave, and nothing else. Every number keeps its own definition, date and source. Figures with different definitions are never added together, and a chart joins only the same measure from the same source.

Every figure

## NYISO, figure by figure

Newest first. Each card opens its source document.

- **Large load projects in the interconnection queue**: about 12.7 GW, as of May 1, 2026 (asked for). 51 large load projects in the queue as of May 1, 2026, which would add nearly 12,670 MW of load. Source: [NYISO, Power Trends 2026](https://www.nyiso.com/documents/d/guest/2026-power-trends), Jun 7, 2026.
- **Large load projects in the interconnection queue**: about 6.1 GW, as of July 2025 (asked for). 29 large load projects in the queue as of July 2025, about 6,055 MW of load. Source: [NYISO, Energy-Intensive Projects in NYISO's Interconnection Queue](https://www.nyiso.com/-/energy-intensive-projects-in-nyiso-s-interconnection-queue), Aug 26, 2025.
- **Large load projects in the interconnection queue**: 1,045 MW, as of 2022 (asked for). Six large load projects in NYISO's interconnection queue in 2022, as NYISO reports in Power Trends 2026. Source: [NYISO, Power Trends 2026](https://www.nyiso.com/documents/d/guest/2026-power-trends), Jun 7, 2026.

On the Power Map

## SI data centers inside NYISO

Each card opens the site on the Power Map. Status and power are Epoch AI's, read November 10, 2026.

- [Anthropic Lake Mariner](https://siscto.si/power-map/anthropic-lake-mariner/): Barker, New York. 210 MW of IT power (Epoch AI, as of Oct 31, 2026).
- [Core42 Lake Mariner](https://siscto.si/power-map/core42-lake-mariner/): Barker, New York. 58 MW of IT power (Epoch AI, as of Jul 23, 2026).

[The Power Map](https://siscto.si/power-map/)

2 Power Map sites fall inside this grid's area on the federal Control Areas map (HIFLD Open, year 2018 boundaries). A site's place on that map is a guide, not proof of which utility serves it.

Sources

## Where every figure comes from

Each source was opened and read on November 23, 2026.

validated May 15, 2020, read Nov 23, 2026

### U.S. Department of Homeland Security, HIFLD Open (public copy)

Control Areas (balancing authority areas), sourced from FERC 714, EIA 860 and EIA 861, year 2018

[Open the source](https://services5.arcgis.com/HDRa0B57OVrv2E1q/ArcGIS/rest/services/Control_Areas/FeatureServer/0)

Aug 26, 2025, read Nov 23, 2026

### NYISO

Energy-Intensive Projects in NYISO's Interconnection Queue

[Open the source](https://www.nyiso.com/-/energy-intensive-projects-in-nyiso-s-interconnection-queue)

Jun 7, 2026, read Nov 23, 2026

### NYISO

Power Trends 2026

[Open the source](https://www.nyiso.com/documents/d/guest/2026-power-trends)

retrieved Nov 10, 2026

### Epoch AI

The Power Map's site list, towns, status and power come from Epoch AI's open data set of data centers, licensed CC BY 4.0.

[Open the source](https://epoch.ai/data/ai-data-centers)

Keep going

## The same grid, other records

Every page of the set reads a different public record.

### Power Map

Every SI data center public data can confirm, with its power.

### Gigawatt Ledger

What was announced against what is confirmed energized.

### Onsite Power Watch

The plants built to run data centers directly.

### Grid Watch

Live demand on the grids that host the most sites.

### Bill Watch

Home power prices in every state with a site.

Questions

## NYISO, answered

The figures, the stages and the limits.

### How much power are data centers asking NYISO for?

NYISO counts the large load projects in its interconnection queue. Six projects with 1,045 MW were in it in 2022; by May 1, 2026 there were 51 projects that would add nearly 12,670 MW. Each figure on this page has its own definition and date; figures with different definitions are never added together.

### Is all of that going to be built?

No figure here says what will be built. Requests are what customers asked for; many requests are speculative, duplicated across grids or withdrawn. The stages on this page (asked for, in study, approved, under contract, running) are the source's own words.

### Which data centers are inside NYISO?

The [Power Map](https://siscto.si/power-map/) lists 2 sites inside NYISO's area on the federal Control Areas map. See the list below; each links to its page.

### Where do the figures come from?

From the grid operator's own board decks, filings and reports, each read on November 23, 2026. The links are on every figure.

### How hard is NYISO running right now?

[Grid Watch](https://siscto.si/grid-watch/#nyiso) shows NYISO's demand hour by hour from the EIA, against its own forecast and its record.

Join the takeover

## Read the queue with us

Open a source, check a figure yourself and bring what you find to the $SIS Telegram.

[Buy $SIS](https://pump.fun/coin/FdKdpz11GsTofLaNiddrhxrsE4APZYSSfLFqQ9YKpump)

[Join the Telegram](https://t.me/sisctotg)

[Follow on X](https://x.com/entersiscto)

[Swap on Jupiter](https://jup.ag/swap/SOL-FdKdpz11GsTofLaNiddrhxrsE4APZYSSfLFqQ9YKpump)