# The queue at PJM

PJM has no single queue of loads. Utilities send it large load adjustments for its load forecast, and PJM accepts or trims them. Its own read in November 2025 supported data center growth of up to about 30 GW from 2025 to 2030. Dominion Energy, the largest data center market in PJM, told PJM in September 2026 that about 54 GW of data center capacity is under contract with it.

Figures on file
:   [4](https://siscto.si/queue/pjm/#figures)

Newest figure
:   [Sep 29, 2026](https://siscto.si/queue/pjm/#figures)

Power Map sites inside
:   [19](https://siscto.si/queue/pjm/#sites)

Live on Grid Watch
:   [Yes](https://siscto.si/grid-watch/#pjm)

Over time

## Where the source repeats

This grid has no measure that its source repeats three times yet, so there is no line. Every number keeps its own definition, date and source. Figures with different definitions are never added together, and a chart joins only the same measure from the same source.

The figures below are each a single reading. A line appears here once the same source gives the same measure three times.

Every figure

## PJM, figure by figure

Newest first. Each card opens its source document.

- **Dominion Energy: data center capacity under contract**: about 54 GW, as of September 29, 2026 (under contract). Capacity under contract at three stages (engineering letters of authorization, construction letters of authorization and electric service agreements), as Dominion told PJM. Dominion excludes 19 GW of the engineering stage from its own forecast. Source: [Dominion Energy, to PJM, Dominion Energy LSE 20-Year Data Center Forecast, Load Analysis Subcommittee](https://www.pjm.com/-/media/DotCom/committees-groups/subcommittees/las/2026/20260929/20260929-item-5ai---dominion_energy.pdf), Sep 29, 2026.
- **Dominion Energy: data center billing peak load**: 4.8 GW, as of August 2026 (running). The peak billing load of the data centers Dominion serves, as of August 2026, in the same presentation. Load that runs today, unlike the contracts above. Source: [Dominion Energy, to PJM, Dominion Energy LSE 20-Year Data Center Forecast, Load Analysis Subcommittee](https://www.pjm.com/-/media/DotCom/committees-groups/subcommittees/las/2026/20260929/20260929-item-5ai---dominion_energy.pdf), Sep 29, 2026.
- **Forecast summer peak in 2036**: 222,106 MW, as of January 14, 2026 (forecast). PJM's 2026 load forecast for the whole system's summer peak in 2036, a ten year increase of 65,733 MW. It counts all load, not only data centers. Source: [PJM, 2026 PJM Load Forecast Report](https://www.pjm.com/-/media/DotCom/library/reports-notices/load-forecast/2026-load-report.pdf), Jan 14, 2026.
- **Data center growth PJM's review supports, 2025 to 2030**: about 30 GW, as of November 24, 2025 (forecast). PJM's own reading of utility requests and national projections: "Supports PJM data center growth of up to ~30 GW between 2025 and 2030." A forecast, not requests. Source: [PJM, Load Adjustment Requests Summary for the 2026 Load Forecast, Load Analysis Subcommittee](https://www.pjm.com/-/media/DotCom/committees-groups/subcommittees/las/2025/20251124/20251124-item-03---large-load-adjustment-requests-summary.pdf), Nov 24, 2025.

Utilities

## The utilities in this grid

A utility's own count of the load it has agreed to serve, from its own filings.

### American Electric Power (AEP)

AEP reports, each quarter, the new load backed by signed customer agreements across its companies in PJM, SPP and ERCOT. The count went from 24 GW in July 2025 to 69 GW through 2030 in July 2026, and to 84 GW by 2031 in October 2026.

- **Contracted load by 2031**: 84 GW, as of October 28, 2026 (under contract). After 15 GW of new load commitments in the third quarter of 2026. AEP moved the horizon to 2031, so this figure is kept off the 2030 line. Source: [AEP, Third-quarter 2026 earnings release (SEC Form 8-K, exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/4904/000000490426000069/a3q20268kpressreleaseex991.htm), Oct 28, 2026.
- **Contracted load growth through 2030**: 69 GW, as of July 30, 2026 (under contract). After 6 GW more of signed load agreements in the second quarter of 2026, mainly in Texas. Source: [AEP, Second-quarter 2026 earnings release (SEC Form 8-K, exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/4904/000000490426000055/a2q20268kpressreleaseex991.htm), Jul 30, 2026.
- **New load by 2030 under signed agreements**: 63 GW, as of May 5, 2026 (under contract). After 7 GW of new load agreements signed in the first quarter of 2026. AEP Texas accounts for 41 GW of the commitments. Source: [AEP, First-quarter 2026 earnings release (SEC Form 8-K, exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/4904/000000490426000031/a1q20268kpressreleaseex991.htm), May 5, 2026.
- **New load by 2030 under signed agreements**: 56 GW, as of February 12, 2026 (under contract). Incremental load by 2030, all backed by signed agreements. AEP Texas alone rose from 13 GW to 36 GW, backed by signed letters of agreement. Source: [AEP, Fourth-quarter and full-year 2025 earnings release (SEC Form 8-K, exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/4904/000000490426000011/a4q20258kpressreleaseex991.htm), Feb 12, 2026.
- **New load by 2030 under customer agreements**: 28 GW, as of October 29, 2025 (under contract). Load additions by 2030 backed by electric service agreements or letters of agreement, supported by an additional 190 GW of load requests. Source: [AEP, Third-quarter 2025 earnings release (SEC Form 8-K, exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/4904/000000490425000169/a3q20258kpressreleaseex991.htm), Oct 29, 2025.
- **New load by 2030 under customer agreements**: 24 GW, as of July 30, 2025 (under contract). Incremental load by 2030 under customer agreements with firm financial commitments, mainly in Indiana, Ohio and Texas. AEP also cited more than 190 GW of load requests at various stages. Source: [AEP, Second-quarter 2025 earnings release (SEC Form 8-K, exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/4904/000000490425000139/a2q20258kpressreleaseex991.htm), Jul 30, 2025.

On the Power Map

## SI data centers inside PJM

Each card opens the site on the Power Map. Status and power are Epoch AI's, read November 10, 2026.

- [Anthropic-Amazon New Carlisle](https://siscto.si/power-map/anthropic-amazon-new-carlisle/): New Carlisle, Indiana. 1,037 MW of IT power (Epoch AI, as of Oct 19, 2026).
- [Meta Prometheus](https://siscto.si/power-map/meta-prometheus/): New Albany, Ohio. 471 MW of IT power (Epoch AI, as of Aug 31, 2026).
- [Google New Albany](https://siscto.si/power-map/google-new-albany/): New Albany, Ohio. 333 MW of IT power (Epoch AI, as of May 18, 2026).
- [Google Columbus](https://siscto.si/power-map/google-columbus/): Columbus, Ohio. 303 MW of IT power (Epoch AI, as of Aug 5, 2026).
- [Google Bristow](https://siscto.si/power-map/google-bristow/): Bristow, Virginia. 238 MW of IT power (Epoch AI, as of May 20, 2026).
- [QTS Richmond 1](https://siscto.si/power-map/qts-richmond-1/): Sandston, Virginia. 238 MW of IT power (Epoch AI, as of Feb 13, 2026).
- [AWS New Albany](https://siscto.si/power-map/aws-new-albany/): New Albany, Ohio. 213 MW of IT power (Epoch AI, as of May 18, 2026).
- [QTS Richmond 2](https://siscto.si/power-map/qts-richmond-2/): Sandston, Virginia. 180 MW of IT power (Epoch AI, as of May 14, 2026).
- [QTS Richmond 3](https://siscto.si/power-map/qts-richmond-3/): Sandston, Virginia. 144 MW of IT power (Epoch AI, as of May 14, 2026).
- [Google Lancaster](https://siscto.si/power-map/google-lancaster/): Lancaster, Ohio. 137 MW of IT power (Epoch AI, as of Mar 12, 2026).
- [AWS Berwick](https://siscto.si/power-map/aws-berwick/): Berwick, Pennsylvania. 108 MW of IT power (Epoch AI, as of Aug 1, 2026).
- [STACK Infrastructure NVA02](https://siscto.si/power-map/stack-infrastructure-nva02/): Manassas, Virginia. 85 MW of IT power (Epoch AI, as of Feb 14, 2026).
- [CoreWeave Chester VA](https://siscto.si/power-map/coreweave-chester-va/): Chester, Virginia. 82 MW of IT power (Epoch AI, as of May 20, 2026).
- [Google Arcola](https://siscto.si/power-map/google-arcola/): Arcola, Virginia. 77 MW of IT power (Epoch AI, as of Jun 16, 2026).
- [Microsoft-Nebius New Jersey](https://siscto.si/power-map/microsoft-nebius-new-jersey/): Vineland, New Jersey. 50 MW of IT power (Epoch AI, as of Jul 12, 2026).
- [CoreWeave Lancaster Greenfield site](https://siscto.si/power-map/coreweave-lancaster-greenfield-site/): Lancaster, Pennsylvania. No building running yet (Epoch AI, as of Jul 13, 2026).
- [Google Fort Wayne](https://siscto.si/power-map/google-fort-wayne/): Fort Wayne, Indiana. No building running yet (Epoch AI, as of Aug 19, 2026).
- [Meta Bowling Green](https://siscto.si/power-map/meta-bowling-green/): Bowling Green, Ohio. No building running yet (Epoch AI, as of Jul 30, 2026).
- [OpenAI Stargate Lordstown](https://siscto.si/power-map/openai-stargate-lordstown/): Lordstown, Ohio. No building running yet (Epoch AI, as of Jul 30, 2026).

[The Power Map](https://siscto.si/power-map/)

19 Power Map sites fall inside this grid's area on the federal Control Areas map (HIFLD Open, year 2018 boundaries). A site's place on that map is a guide, not proof of which utility serves it.

Sources

## Where every figure comes from

Each source was opened and read on November 23, 2026.

validated May 15, 2020, read Nov 23, 2026

### U.S. Department of Homeland Security, HIFLD Open (public copy)

Control Areas (balancing authority areas), sourced from FERC 714, EIA 860 and EIA 861, year 2018

[Open the source](https://services5.arcgis.com/HDRa0B57OVrv2E1q/ArcGIS/rest/services/Control_Areas/FeatureServer/0)

Jul 30, 2025, read Nov 23, 2026

### AEP

Second-quarter 2025 earnings release (SEC Form 8-K, exhibit 99.1)

[Open the source](https://www.sec.gov/Archives/edgar/data/4904/000000490425000139/a2q20258kpressreleaseex991.htm)

Oct 29, 2025, read Nov 23, 2026

### AEP

Third-quarter 2025 earnings release (SEC Form 8-K, exhibit 99.1)

[Open the source](https://www.sec.gov/Archives/edgar/data/4904/000000490425000169/a3q20258kpressreleaseex991.htm)

Nov 24, 2025, read Nov 23, 2026

### PJM

Load Adjustment Requests Summary for the 2026 Load Forecast, Load Analysis Subcommittee

[Open the source](https://www.pjm.com/-/media/DotCom/committees-groups/subcommittees/las/2025/20251124/20251124-item-03---large-load-adjustment-requests-summary.pdf)

Jan 14, 2026, read Nov 23, 2026

### PJM

2026 PJM Load Forecast Report

[Open the source](https://www.pjm.com/-/media/DotCom/library/reports-notices/load-forecast/2026-load-report.pdf)

Feb 12, 2026, read Nov 23, 2026

### AEP

Fourth-quarter and full-year 2025 earnings release (SEC Form 8-K, exhibit 99.1)

[Open the source](https://www.sec.gov/Archives/edgar/data/4904/000000490426000011/a4q20258kpressreleaseex991.htm)

May 5, 2026, read Nov 23, 2026

### AEP

First-quarter 2026 earnings release (SEC Form 8-K, exhibit 99.1)

[Open the source](https://www.sec.gov/Archives/edgar/data/4904/000000490426000031/a1q20268kpressreleaseex991.htm)

Jul 30, 2026, read Nov 23, 2026

### AEP

Second-quarter 2026 earnings release (SEC Form 8-K, exhibit 99.1)

[Open the source](https://www.sec.gov/Archives/edgar/data/4904/000000490426000055/a2q20268kpressreleaseex991.htm)

Sep 29, 2026, read Nov 23, 2026

### Dominion Energy, to PJM

Dominion Energy LSE 20-Year Data Center Forecast, Load Analysis Subcommittee

[Open the source](https://www.pjm.com/-/media/DotCom/committees-groups/subcommittees/las/2026/20260929/20260929-item-5ai---dominion_energy.pdf)

Oct 28, 2026, read Nov 23, 2026

### AEP

Third-quarter 2026 earnings release (SEC Form 8-K, exhibit 99.1)

[Open the source](https://www.sec.gov/Archives/edgar/data/4904/000000490426000069/a3q20268kpressreleaseex991.htm)

retrieved Nov 10, 2026

### Epoch AI

The Power Map's site list, towns, status and power come from Epoch AI's open data set of data centers, licensed CC BY 4.0.

[Open the source](https://epoch.ai/data/ai-data-centers)

Keep going

## The same grid, other records

Every page of the set reads a different public record.

### Power Map

Every SI data center public data can confirm, with its power.

### Gigawatt Ledger

What was announced against what is confirmed energized.

### Onsite Power Watch

The plants built to run data centers directly.

### Grid Watch

Live demand on the grids that host the most sites.

### Bill Watch

Home power prices in every state with a site.

Questions

## PJM, answered

The figures, the stages and the limits.

### How much power are data centers asking PJM for?

PJM has no single queue of loads. Utilities send it large load adjustments for its load forecast, and PJM accepts or trims them. Its own read in November 2025 supported data center growth of up to about 30 GW from 2025 to 2030. Dominion Energy, the largest data center market in PJM, told PJM in September 2026 that about 54 GW of data center capacity is under contract with it. Each figure on this page has its own definition and date; figures with different definitions are never added together.

### Is all of that going to be built?

No figure here says what will be built. Requests are what customers asked for; many requests are speculative, duplicated across grids or withdrawn. The stages on this page (asked for, in study, approved, under contract, running) are the source's own words.

### Which data centers are inside PJM?

The [Power Map](https://siscto.si/power-map/) lists 19 sites inside PJM's area on the federal Control Areas map. See the list below; each links to its page.

### Where do the figures come from?

From the grid operator's own board decks, filings and reports and the utilities' own filings with the SEC, each read on November 23, 2026. The links are on every figure.

### How hard is PJM running right now?

[Grid Watch](https://siscto.si/grid-watch/#pjm) shows PJM's demand hour by hour from the EIA, against its own forecast and its record.

Join the takeover

## Read the queue with us

Open a source, check a figure yourself and bring what you find to the $SIS Telegram.

[Buy $SIS](https://pump.fun/coin/FdKdpz11GsTofLaNiddrhxrsE4APZYSSfLFqQ9YKpump)

[Join the Telegram](https://t.me/sisctotg)

[Follow on X](https://x.com/entersiscto)

[Swap on Jupiter](https://jup.ag/swap/SOL-FdKdpz11GsTofLaNiddrhxrsE4APZYSSfLFqQ9YKpump)