1. Home
  2. Power Map
  3. AWS Berwick

Power Map · Operating, expanding

AWS Berwick, Berwick

AWS Berwick is an SI data center in Berwick, Pennsylvania, United States, owned by Amazon and used by Anthropic (Epoch AI rates this speculative). Epoch AI estimates its IT power at 108 MW as of August 1, 2026, with 3 buildings operating, and projects 169 MW by August 1, 2027. Its public timeline starts on July 1, 2021.

IT power
108 MWAug 1, 2026
Facility power
139 MW
Status
Operating, expanding
Buildings operating
3

Where it is

The site and its facts

AWS Berwick on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.

Berwick, Pennsylvania, United StatesOpen in OpenStreetMap
Place
Berwick, Pennsylvania, United States
Address
1125 Electron Ave, Berwick, PA 18603
Coordinates
41.0851° N, 76.1488° W
Owner
Amazon
Users
Anthropic (Epoch AI rates this speculative)
Project
Project Rainier
Chips
Trainium2
Compute
About 81,354 H100 equivalentsEpoch AI estimate, Aug 1, 2026
Projected
169 MW IT power by August 1, 2027Epoch AI projection, not a fact yet

Heat Watch

AWS Berwick: heat seen from space

Over the last three summers NASA's MODIS read the ground here -0.0 °C against the land 5 to 10 km around it by day.

Lights On

AWS Berwick: light at night

NASA's night imagery read 29.3 of 100 over this site in October 2026, against 20.9 in October 2018, the first month read. Against a year before: -0.1 points. Light is not proof of what runs inside.

Timeline

Dated, from the public record

Epoch AI's dated notes on AWS Berwick, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.

  1. Land clearing begins. Talen Energy reported on July 12, 2021 that site-preparation permits had already been obtained and site work was underway, while permits for construction of the first building were still being pursued. We model land clearing as starting from the beginning of the month.

    No IT power yet0 operating

  2. Cumulus completes a 48 MW, 300,000 sq ft powered shell for the first data center at the Susquehanna campus. The shell is available for lease, with the campus still awaiting its first tenant and commercial operations.

    No IT power yet0 operating

  3. AWS acquires the Cumulus/Talen building campus for $650M.

    No IT power yet0 operating

  4. Building 1 fit out and related construction begins under Amazon, based on the Susquehanna River Basin Commission (SRBC) schedule.

    No IT power yet0 operating

  5. Building 1 operational estimate. According to Google Earth Satellite Imagery from this date, Building 1 appears structurally complete and likely operational, while Building 2 is still missing two generators.

    47 MW1 operating

  6. Building 2 operational estimate. This is based on the progress visible in the September 2025 image. The DEP also issues an air plan approval to add 48 more emergency generators on this date.

    77 MW2 operating

  7. The SRBC increases approved water use from 0.060 MGD to 0.129 MGD. This supports that some expansion is happening, but does not explicitly prove a third operational building.

    77 MW2 operating

  8. Buildings 1 and 2 visibly complete and operational. Building 3 appears complete and may be commissioning, but it's likely not operational yet given the immediate surrounding construction work. Several additional building shells and pads are still in construction, but none are assumed operational due to all the construction work visible. This is based on satellite imagery from this date.

    77 MW2 operating

  9. Building 3 expected to come online sometime around August 2026, since in the May satellite image it appeared structurally complete with minimal construction surrounding it. Basing MW estimate using Building 2 as a reference.

    108 MW3 operating

  10. Building 4 expected to come online around August 2027, judging from prior satellite imagery. Modeled at twice Building 2's capacity because Building 4 is approximately twice its size.

    169 MW4 operating

Adopt a site

Watch AWS Berwick

One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.

The watcher

Loading the watcher.

Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.

Approved updates · 0

  • Approved updates show here with their date.

Questions

AWS Berwick, answered

Where it is, who owns it and how much power it uses, from the public record.

Where is AWS Berwick?

AWS Berwick is in Berwick, Pennsylvania, United States, at 1125 Electron Ave, Berwick, PA 18603. Epoch AI publishes its coordinates as 41.0851, -76.1488.

Who owns AWS Berwick?

Epoch AI lists Amazon as its owner and Anthropic (Epoch AI rates this speculative) as its user.

How much power does AWS Berwick use?

Epoch AI estimates its IT power at 108 MW as of August 1, 2026, and its total facility power at 139 MW. It projects 169 MW of IT power by August 1, 2027.

Is AWS Berwick operating?

Yes, and it is growing. Epoch AI counts 3 buildings operating as of August 1, 2026, with more capacity on its timeline.

Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).