The Gigawatt Ledger · announced against built
What was announced, and what is built
The Gigawatt Ledger sets what was announced for each SI compute project against what public evidence confirms as built. Today the 18 projects with a stated power figure add up to 14.8 GW announced, and 3.3 to 4.25 GW is confirmed energized: 22% to 29%. It follows 24 projects in 5 countries through 44 public announcements, each quoted in its own words with its date and its link.
- Projects
- 24
- Announced
- 14.8 GW
- Confirmed, max
- 4.25 GW
- Source links
- 37
The headline
Announced against confirmed energized
One pair of numbers for the whole Ledger, with the method beside it. Both totals rest on stated power figures and dated public evidence, as of November 11, 2026.
Announced
14.8 GW
against
Confirmed energized
3.3 to 4.25 GW
22% to 29% confirmed energized18 projects with a stated power figure, as of November 11, 2026
How this is counted
- Announced is the sum of one figure for each project: the power or capacity its operator, a partner, a regulator, a utility or a filing states for it.
- Not counted: "up to" and "can scale to" figures (6.54 GW more across 5 projects), figures shared between sites, and figures only the press reports.
- Confirmed energized is the power public evidence shows running at those same projects, never more than the project's own announced figure.
- Like for like: IT load is set against IT load and total power against the whole facility. Where an announcement does not say which it means, both ends are shown as a range.
By operator
Who announced what, and what runs
Each bar is the announced power of one operator's projects in the Ledger. The green part is what public evidence confirms as energized.
- Announced
- Confirmed energized, low end
- Up to the high end
Operators with a stated power figure. A project is filed under the company the compute is built for, or the company that runs the campus.
The Ledger
All 24 projects
Filter by operator, by country or US state, and by state of the build. The totals follow what is shown. Open a project for its announcements, its evidence and its sources.
- Projects shown
- 24
- Announced
- 14.8 GW
- Energized
- 3.3 to 4.25 GW
- Share energized
- 22% to 29%
All 24 projects, largest announcement first.
- Colossus (Memphis and Southaven)Memphis, TennesseeSpaceXAI2 GWannounced1 to 1.7 GWconfirmed, Jun 15, 2026Partly energized
- Meta HyperionRichland Parish, LouisianaMeta2 GWannouncedNot confirmedas of Apr 19, 2026Under construction
- Stargate Shackelford County (Frontier)Shackelford County, TexasOpenAI, Oracle, Vantage Data Centers1.4 GWannouncedNot confirmedas of Sep 4, 2026Under construction
- Stargate Michigan (Saline Township)Saline Township, MichiganOpenAI, Oracle, Related Digital1.38 GWannouncedNot confirmedas of Mar 12, 2026Under construction
- Stargate AbileneAbilene, TexasOpenAI, Oracle, Crusoe1.2 GWannounced1.15 GWconfirmed, Nov 1, 2026Energized
- Stargate Milam CountyMilam County, TexasOpenAI, SoftBank, SB Energy1.2 GWannouncedNot confirmedas of Mar 23, 2026Under construction
- Meta PrometheusNew Albany, OhioMeta1 GWannounced471 to 612 MWconfirmed, Aug 31, 2026Partly energized
- Stargate UAEAbu Dhabi, United Arab EmiratesOpenAI, G42, Oracle1 GWannouncedNot confirmedas of Nov 16, 2025Under construction
- Stargate Wisconsin (Port Washington, Lighthouse)Port Washington, WisconsinOpenAI, Oracle, Vantage Data Centers902 MWannouncedNot confirmedas of Jul 24, 2026Under construction
- Abilene campus for MicrosoftAbilene, TexasMicrosoft, Crusoe900 MWannouncedNot confirmedas of Jan 15, 2026Under construction
- Lake MarinerBarker, New YorkFluidstack, TeraWulf, Core42, Anthropic440 MWannounced268 MWconfirmed, Oct 31, 2026Partly energized
- Polaris Forge 1Ellendale, North DakotaCoreWeave, Applied Digital400 MWannounced68 to 175 MWconfirmed, Jun 30, 2026Partly energized
- DentonDenton, TexasCoreWeave, Core Scientific260 MWannounced262 MWconfirmed, Sep 1, 2026Energized
- Stargate Norway (Narvik)Narvik, Nordland, NorwayNscale, Aker, OpenAI, Microsoft230 MWannouncedNot confirmedas of Jul 5, 2026Under construction
- Barber LakeColorado City, TexasFluidstack, Cipher Mining, Anthropic207 MWannouncedNot confirmedas of Jul 30, 2026Delayed
- LancasterLancaster, PennsylvaniaCoreWeave, Chirisa Technology Parks, Machine Investment Group100 MWannouncedNot confirmedas of Jul 13, 2026Under construction
- MuskogeeMuskogee, OklahomaCoreWeave, Core Scientific100 MWannouncedNot confirmedas of Jun 13, 2026Under construction
- Nebius MäntsäläMäntsälä, Uusimaa, FinlandNebius75 MWannounced75 to 90 MWconfirmed, Jun 29, 2026Energized
- Project Rainier, New CarlisleNew Carlisle, IndianaAmazon, AnthropicNot statedannounced1,037 MW ITconfirmed, Oct 19, 2026Partly energized
- Microsoft Fairwater AtlantaFayetteville, GeorgiaMicrosoftNot statedannounced636 MW ITconfirmed, Jun 14, 2026Energized
- Microsoft Fairwater WisconsinMount Pleasant, WisconsinMicrosoftNot statedannounced369 MW ITconfirmed, May 15, 2026Partly energized
- EcoDataCenter 2, BorlängeBorlänge, Dalarna County, SwedenMistral AI, EcoDataCenterNot statedannouncedNot confirmedas of Aug 17, 2026Under construction
- Stargate Doña Ana County (Project Jupiter)Doña Ana County, New MexicoOpenAI, Oracle, BorderPlex Digital Assets, STACK InfrastructureNot statedannouncedNot confirmedas of Jun 22, 2026Under construction
- Stargate LordstownLordstown, OhioOpenAI, SoftBankNot statedannouncedNot confirmedas of Jul 30, 2026Under construction
No project matches. Clear the filters to see them all.
Built evidence: Epoch AI, "AI data centers" (CC BY 4.0), retrieved November 10, 2026, plus the linked statements and filings. Announcements read on November 11, 2026.
The states
Six states, each with its evidence
Every project is in exactly one state, and its page says what evidence put it there.
- Announced
A public announcement exists and no public evidence of construction has been read.
0 projects today
- Under construction
Work on the ground is confirmed and nothing is confirmed as running yet.
13 projects today
- Partly energized
Part of the announced power is confirmed as running.
6 projects today
- Energized
Public evidence puts the running power at 95% or more of the announced figure, or shows every building running where no figure was stated.
4 projects today
- Delayed
Nothing is running, a promised date has passed, and a linked source shows it was not met.
1 project today
- Cancelled
A linked source says the project was dropped.
0 projects today
Use it
Download, embed, cite
The Ledger is made to be quoted. Take the data, put the live headline in an article, or cite it with its date.
The dataset
Every project, announcement and evidence row with its source link and date.
Reuse with credit and a link to siscto.si/ledger/. Epoch AI's figures are theirs under CC BY 4.0.
Embed for reporters
The headline and the chart in a frame that follows the data. Paste this where your article takes HTML.
See the embedReality Check · fourth quarter 2026
The quarter in one page
Each quarter the Ledger is summed up from its own data: the headline, the operators, the widest gaps and the promises that came due. The first one is dated November 11, 2026.
See the sites
On the map, and from orbit
The Ledger counts. The Power Map and Compute Watch show the same sites on the ground.
The Power Map
Every SI data center that public data confirms, on one world map, with the dated timeline behind each Ledger figure.
Open the mapCompute Watch
The newest clear satellite pass over seven of the largest builds, read by SI MIND and sealed on Solana.
See them from orbitHeat Watch
Data center heat, seen from space
Every site's summer land heat from NASA's MODIS satellites against the land 5 to 10 km around it: +0.5 °C on average by day over the last three summers. One public signal, next to what is built.
SI Next Door
The SI data centers near your ZIP code
Enter a ZIP code to see the sites within reach, builds on the way, hearings, your state's home power price and sourced facts on what data center demand adds to costs. 77 US sites.
Lights On
Night lights over every site
NASA's night-light imagery over all 96 sites, month by month since 2018, beside what is announced and what is built. In October 2026, 66 of 96 sites were brighter than a year before. Light is one public signal, never proof a site is running.
Questions
The Gigawatt Ledger, answered
What counts as announced, what counts as built and how to correct a row.
What is the Gigawatt Ledger?
A public ledger of SI compute projects that sets what was announced against what can be verified as built. Each project lists its public announcements, each with who said it, the power or capacity stated, the promised date and a link, and next to them the public evidence of what is running today. It covers 24 projects from 5 countries, and every row has a source.
Where do the announced figures come from?
From the announcement itself: a company page or release, a regulator, a utility or a public filing, quoted in its own words and its own unit. A figure counts toward the total only when the source states it as the project's planned or contracted power or capacity. Figures given as "up to", "potential" or "can scale to" are listed on the project page and left out of the total, and so are figures that only the press reports.
What counts as confirmed energized?
Power that public evidence shows in operation. The main evidence is Epoch AI's public tracker, which dates each building that starts running from satellite images, permits and company statements, the same data the Power Map draws. A company statement, a utility statement or a filing that states live power is used too, with its link. Where Compute Watch follows a site, its newest satellite pass is on the project page.
Why is the confirmed figure a range?
Because announcements do not always say what their number measures. A campus announced at 1 GW may mean the power for the computers or the power for the whole site, cooling included. Where the announcement states IT load, the Ledger compares IT load, and where it states total power it compares the whole facility. Where it says neither, the low end is the IT load in operation and the high end is the whole facility, and both are shown.
What do the six states mean?
Announced: no construction evidence has been read. Under construction: work is confirmed and nothing runs yet. Partly energized: part of the announced power runs. Energized: 95% or more runs. Delayed: nothing runs, a promised date has passed and a linked source shows it was not met. Cancelled: a linked source says the project was dropped. Each project page states the evidence for its state.
Why are some projects not in the total?
A project joins the total only when a source states a power figure for it alone. A project announced with money and dates but no power, or with a figure shared between several sites, is on the Ledger with everything that is known and shows "not stated" where a number would be. Nothing is guessed to fill the gap.
How do I correct a row?
Open the project page, sign in with your SI Passport and file a correction with a link to a public source. The team reads the source before anything changes, and approved corrections show on the page with their date. If your Passport carries an Org check, the page shows it, and an organization correcting its own project is labeled as such.
Can I reuse the data?
Yes, with credit and a link to siscto.si/ledger/. The Ledger downloads as JSON and CSV, there is an embed for articles and a line to cite. The figures taken from Epoch AI are Epoch AI's, published under CC BY 4.0, so credit Epoch AI for those.
Is $SIS linked to these companies?
No. $SIS is a community meme token with no affiliation with, or endorsement from, any company named in the Ledger or with Epoch AI. The Ledger quotes public sources and describes what they show.