Google Kansas City East, Kansas City
Google Kansas City East is an SI data center in Kansas City, Missouri, United States, owned by Google. Epoch AI estimates its IT power at 105 MW as of August 1, 2026, with 1 building operating. Its public timeline starts on January 1, 2024.
- IT power
- 105 MWAug 1, 2026
- Facility power
- 126 MW
- Status
- Operating
- Buildings operating
- 1
Where it is
The site and its facts
Google Kansas City East on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.
- Place
- Kansas City, Missouri, United States
- Address
- Not public
- Coordinates
- 39.1796° N, 94.4642° W
- Owner
- Compute
- About 202,628 H100 equivalentsEpoch AI estimate, Aug 1, 2026
Heat Watch
Google Kansas City East: heat seen from space
Over the last three summers NASA's MODIS read the ground here +0.8 °C against the land 5 to 10 km around it by day.
Lights On
Google Kansas City East: light at night
NASA's night imagery read 64.6 of 100 over this site in October 2026, against 40.0 in October 2018, the first month read. Against a year before: -1.5 points. The place was already bright at the first reading, so growth is harder to see. Light is not proof of what runs inside.
Timeline
Dated, from the public record
Epoch AI's dated notes on Google Kansas City East, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.
Land clearing has begun for the site
No IT power yet0 operating
Foundation work begins on Building 1
No IT power yet0 operating
Foundation work begins on Building 2. Building 1 roof is fully black.
No IT power yet0 operating
Foundation work begins for Building 3. Building 1 generators seem complete.
No IT power yet0 operating
Foundation work begins for Building 4. Building 2 roof is almost complete, and construction appears to have started on cooling. Building 1 cooling construction continues, and the substation right next to it seems finished as well.
No IT power yet0 operating
Building 1 is almost complete, with only cooling needing 4 more fans. Building 2 backup generator construction has begun, and cooling tower installation is about halfway complete. Building 3's roof is almost complete, and construction has started on generators and cooling. A clear foundation has been cleared for Building 4, though no construction has begun.
No IT power yet0 operating
Building 1 operational. Estimated based on present construction progress and typical timelines.
105 MW1 operating
Adopt a site
Watch Google Kansas City East
One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.
The watcher
Loading the watcher.
Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.
Approved updates · 0
- Approved updates show here with their date.
Sources
Where the facts come from
The sources Epoch AI lists for this site, and the record itself.
- Hunt Midwest Business Center press release linking data center with Google
- DCD article on the site
- Epoch AI, "AI data centers", the record for Google Kansas City East (CC BY 4.0), retrieved November 10, 2026
Nearby
The nearest SI data centers
The four closest sites on the Power Map, as the crow flies.
249 km away
Google Council Bluffs (East)
Council Bluffs, Iowa, United States
237 MW IT power
258 km away
Meta Sarpy
Springfield, Nebraska, United States
80 MW IT power
260 km away
Google Papillion
Papillion, Nebraska, United States
237 MW IT power
264 km away
Microsoft Project Osmium
Cumming, Iowa, United States
190 MW IT power
Questions
Google Kansas City East, answered
Where it is, who owns it and how much power it uses, from the public record.
Where is Google Kansas City East?
Google Kansas City East is in Kansas City, Missouri, United States. Epoch AI publishes its coordinates as 39.1796, -94.4642.
Who owns Google Kansas City East?
Epoch AI lists Google as its owner.
How much power does Google Kansas City East use?
Epoch AI estimates its IT power at 105 MW as of August 1, 2026, and its total facility power at 126 MW.
Is Google Kansas City East operating?
Yes. Epoch AI counts 1 building operating as of August 1, 2026.
Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).