Gigawatt Ledger · Under construction
Stargate Wisconsin, announced against built
Stargate Wisconsin (Port Washington, Lighthouse) is an SI compute project in Port Washington, Wisconsin, by OpenAI, Oracle and Vantage Data Centers. The announced figure is 902 MW across four data centers, from Vantage Data Centers (Nov 11, 2026 (undated page, read on this date)). Epoch AI tracks the site as under construction, with no building operating as of July 24, 2026. Its state today: under construction.
- Announced
- 902 MW
- Energized
- NoneJul 24, 2026
- State
- Under construction
- Source links
- 3
Announced
What was said, and when
Each row is one public announcement about Stargate Wisconsin: who said it, the power or capacity it states in its own unit, the promised date, and the link. Company claims are quoted as claims.
- Company statement
OpenAI, Oracle and SoftBank
OpenAI, Oracle, and SoftBank expand Stargate with five new AI data center sites
OpenAI announces a Midwest site with Oracle. An update on the same page dated October 22, 2025 places it in Wisconsin, developed with Vantage.
“can deliver over 5.5 gigawatts of capacity”
“which we expect to announce soon”
- Power or capacity stated
- Over 5.5 GW for three Oracle sites and an Abilene expansion together
- Promised
- None stated
- Undated page, read on this dateCompany statement
Vantage Data Centers
Port Washington (Lighthouse) Data Center Campus
The developer's campus page states the capacity of the four data centers, labeled as critical IT load, and the completion year.
“totaling 902MW across 2.5 million square feet.”
“is scheduled to be completed in 2028.”
- Power or capacity stated
- 902 MW of critical IT load across four data centers
- Promised
- Completed in 2028
Built
What public evidence confirms
What is on the ground today, from the Power Map data and from any statement or filing that states live power.
Epoch AI tracks the site as under construction, with no building operating as of July 24, 2026.
- Epoch AI estimate
Epoch AI · Power Map
OpenAI Stargate Wisconsin on the Power Map
Epoch AI tracks OpenAI Stargate Wisconsin as under construction: no building is operating as of July 24, 2026.
Construction continues, Buildings 1 and 2 appear roughly halfway roofed, and building 3 foundation is halfway done.
- IT power running
- None
- Whole facility
- None
Epoch AI projects 902 MW of IT power by December 31, 2028. A projection, not a fact yet.
Heat Watch
OpenAI Stargate Wisconsin: heat seen from space
Over the last three summers NASA's MODIS read the ground here +2.0 °C against the land 5 to 10 km around it by day.
Timeline
Announcements and evidence, by date
What was promised and what was seen, in the order it became public. The full dated record of each site is on its Power Map page.
OpenAI, Oracle and SoftBank: Over 5.5 GW for three Oracle sites and an Abilene expansion together.Announcement · OpenAI
OpenAI Stargate Wisconsin: 0 buildings operating, no IT power yet.Evidence · Epoch AI, on the Power Map
OpenAI Stargate Wisconsin: 0 buildings operating, no IT power yet.Evidence · Epoch AI, on the Power Map
OpenAI Stargate Wisconsin: 0 buildings operating, no IT power yet.Evidence · Epoch AI, on the Power Map
Vantage Data Centers: 902 MW of critical IT load across four data centers. Promised: completed in 2028.Announcement · Vantage Data Centers, undated page read on this date
Corrections
See something wrong? File a correction
Sign in with your SI Passport and say what is wrong, with a link to a public source. The team reads the source before anything changes, and approved corrections stay on this page.
File a correction
Sign in with your SI Passport to file a correction. It is a free message signature and never moves tokens.
A correction needs a link. Nothing shows until the team approves it. If your Passport carries an Org check it shows here, and an organization correcting its own project is labeled as such.
Corrections on file · 0
- Loading the corrections on file.
Sources
Every link behind this page
Read on November 11, 2026. An undated page carries the date it was read.
- OpenAI, Oracle, and SoftBank expand Stargate with five new AI data center sites, OpenAI, Sep 23, 2025
- Port Washington (Lighthouse) Data Center Campus, Vantage Data Centers, Nov 11, 2026 (undated page, read on this date)
- OpenAI Stargate Wisconsin on the Power Map, from Epoch AI, "AI data centers" (CC BY 4.0), retrieved November 10, 2026
More projects
Keep reading the Ledger
Three more projects, the same operator first.
The whole Ledger- Under construction
Stargate Shackelford County (Frontier)
Shackelford County, Texas
1.4 GW announced · nothing confirmed
Open the project - Under construction
Stargate Michigan (Saline Township)
Saline Township, Michigan
1.38 GW announced · nothing confirmed
Open the project - Energized
Stargate Abilene
Abilene, Texas
1.2 GW announced · 1.15 GW
Open the project