Gigawatt Ledger · Energized

Stargate Abilene, announced against built

Stargate Abilene is an SI compute project in Abilene, Texas, by OpenAI, Oracle and Crusoe. The announced figure is 1.2 GW total power capacity, from Crusoe (Mar 18, 2025). Public evidence puts 1.15 GW in operation as of November 1, 2026, against 1.2 GW announced: 96%. The announcement states total power, so it is set against the power of the whole facility. Its state today: energized.

Announced
1.2 GW
Energized
1.15 GWNov 1, 2026
State
Energized
Source links
6

Announced

What was said, and when

Each row is one public announcement about Stargate Abilene: who said it, the power or capacity it states in its own unit, the promised date, and the link. Company claims are quoted as claims.

  1. Company statement

    OpenAI

    Announcing The Stargate Project

    OpenAI announces the Stargate Project with SoftBank, Oracle and MGX and says the buildout starts in Texas. No power figure is stated.

    “intends to invest $500 billion over the next four years”
    “The buildout is currently underway, starting in Texas”
    Power or capacity stated
    None stated
    Promised
    $500 billion invested over the next four years
  2. Company statement

    Crusoe

    Crusoe expands Abilene AI campus to 1.2 GW

    Crusoe says the Abilene campus grows to eight buildings and 1.2 GW of total power capacity.

    “a total power capacity of 1.2 gigawatts (GW)”
    “The initial phase, comprising two buildings at 980,000 square feet and 200+ megawatts”
    “expected to be energized in the first half of 2025”
    “expected to be completed in mid-2026”
    Power or capacity stated
    1.2 GW total power capacity (first phase: 200+ MW)
    Promised
    First two buildings energized in the first half of 2025; six more buildings completed in mid-2026
  3. Company statement

    OpenAI, Oracle and SoftBank

    OpenAI, Oracle, and SoftBank expand Stargate with five new AI data center sites

    OpenAI names five more Stargate sites and says a further 600 MW could be added near the Abilene flagship.

    “brings Stargate to nearly 7 gigawatts of planned capacity”
    “an additional potential expansion of 600 megawatts near the flagship Stargate site”
    Power or capacity stated
    Potential expansion of 600 MW near the flagship site
    Promised
    None stated
  4. Company statement

    Crusoe

    Crusoe builds 900 MW Abilene campus for Microsoft

    In a release about a second Abilene campus, Crusoe restates the first campus at 1.2 GW and gives a new date for its second phase.

    “to bring total campus capacity to 1.2 GW”
    “is expected to reach completion by the end of 2026”
    Power or capacity stated
    1.2 GW total campus capacity
    Promised
    Second phase complete by the end of 2026

Built

What public evidence confirms

What is on the ground today, from the Power Map data and from any statement or filing that states live power.

Energized

Public evidence puts 1.15 GW in operation as of November 1, 2026, against 1.2 GW announced: 96%. The announcement states total power, so it is set against the power of the whole facility.

  1. Epoch AI estimate

    Epoch AI · Power Map

    OpenAI Stargate Abilene on the Power Map

    Epoch AI counts 8 buildings operating at OpenAI Stargate Abilene and estimates 824 MW of IT power (1,154 MW for the whole facility) as of November 1, 2026.

    Buildings 7-8 are estimated to be operational. On March 24, Building 8 roughly looked like where Building 3 was in September. Building 3 is estimated to be operational in April, 7 months later. This naively suggests Building 8 will be operational by early November, 7 months after March 24. Oracle gave no date for the last two buildings on its September 10 call.
    IT power running
    824 MW
    Whole facility
    1,154 MW
  2. Undated page, read on this dateContractor statement

    Mortenson

    Abilene AI Data Center & Power Delivery

    The power contractor says the 1 GW, 345 kV substation for the second phase was fully energized by March 10, 2026.

    “construction of a 12.5-acre, 1 GW, 345 kV greenfield substation”
    “fully energized by March 10, 2026”
    Power confirmed
    No figure stated
    Used in the total
    No, shown as history
Schedule

Crusoe first said the six buildings of the second phase were expected to be completed in mid-2026. Its March 27, 2026 release says the second phase is expected to reach completion by the end of 2026.

Loading the newest clear pass

Seen from orbit · Compute Watch

The newest clear pass over the site

The image loads from NASA's public imagery: true color at 30 m per pixel, about 5 km across, north up.

Open Compute Watch

Heat Watch

OpenAI Stargate Abilene: heat seen from space

Over the last three summers NASA's MODIS read the ground here -0.7 °C against the land 5 to 10 km around it by day.

Timeline

Announcements and evidence, by date

What was promised and what was seen, in the order it became public. The full dated record of each site is on its Power Map page.

  1. OpenAI: no power figure stated. Promised: $500 billion invested over the next four years.Announcement · OpenAI

  2. Crusoe: 1.2 GW total power capacity (first phase: 200+ MW). Promised: first two buildings energized in the first half of 2025; six more buildings completed in mid-2026.Announcement · Crusoe

  3. OpenAI, Oracle and SoftBank: Potential expansion of 600 MW near the flagship site.Announcement · OpenAI

  4. Crusoe: 1.2 GW total campus capacity. Promised: second phase complete by the end of 2026.Announcement · Crusoe

  5. OpenAI Stargate Abilene: 4 buildings operating, 412 MW of IT power.Evidence · Epoch AI, on the Power Map

  6. OpenAI Stargate Abilene: 4 buildings operating, 412 MW of IT power.Evidence · Epoch AI, on the Power Map

  7. OpenAI Stargate Abilene: 6 buildings operating, 618 MW of IT power.Evidence · Epoch AI, on the Power Map

  8. OpenAI Stargate Abilene: 8 buildings operating, 824 MW of IT power.Evidence · Epoch AI, on the Power Map

  9. The power contractor says the 1 GW, 345 kV substation for the second phase was fully energized by March 10, 2026.Evidence · Mortenson, undated page read on this date

Corrections

See something wrong? File a correction

Sign in with your SI Passport and say what is wrong, with a link to a public source. The team reads the source before anything changes, and approved corrections stay on this page.

File a correction

Sign in with your SI Passport to file a correction. It is a free message signature and never moves tokens.

A correction needs a link. Nothing shows until the team approves it. If your Passport carries an Org check it shows here, and an organization correcting its own project is labeled as such.

Corrections on file · 0

  • Loading the corrections on file.

Sources

Every link behind this page

Read on November 11, 2026. An undated page carries the date it was read.