1. Home
  2. Gigawatt Ledger
  3. Stargate Shackelford County

Gigawatt Ledger · Under construction

Stargate Shackelford County, announced against built

Stargate Shackelford County (Frontier) is an SI compute project in Shackelford County, Texas, by OpenAI, Oracle and Vantage Data Centers. The announced figure is 1.4 GW of critical IT capacity, from Vantage Data Centers (Nov 11, 2026 (undated page, read on this date)). Epoch AI tracks the site as under construction, with no building operating as of September 4, 2026. Its state today: under construction.

Announced
1.4 GW
Energized
NoneSep 4, 2026
State
Under construction
Source links
3

Announced

What was said, and when

Each row is one public announcement about Stargate Shackelford County: who said it, the power or capacity it states in its own unit, the promised date, and the link. Company claims are quoted as claims.

  1. Company statement

    OpenAI, Oracle and SoftBank

    OpenAI, Oracle, and SoftBank expand Stargate with five new AI data center sites

    OpenAI names Shackelford County, Texas as one of three new sites built with Oracle. The power figure covers the three Oracle sites and an Abilene expansion together.

    “can deliver over 5.5 gigawatts of capacity”
    Power or capacity stated
    Over 5.5 GW for three Oracle sites and an Abilene expansion together
    Promised
    None stated
  2. Undated page, read on this dateCompany statement

    Vantage Data Centers

    Shackelford County (Frontier)

    The developer's campus page states the capacity, the number of buildings and the date of the first one.

    “deliver 1.4GW of critical IT capacity across 10 single-story data centers”
    “The first data center is scheduled for delivery in the second half of 2026.”
    Power or capacity stated
    1.4 GW of critical IT capacity across 10 data centers
    Promised
    First data center delivered in the second half of 2026

Built

What public evidence confirms

What is on the ground today, from the Power Map data and from any statement or filing that states live power.

Under construction

Epoch AI tracks the site as under construction, with no building operating as of September 4, 2026.

  1. Epoch AI estimate

    Epoch AI · Power Map

    OpenAI Stargate Shackelford on the Power Map

    Epoch AI tracks OpenAI Stargate Shackelford as under construction: no building is operating as of September 4, 2026.

    Buildings 1-5 shells complete and fully roofed. Buildings 1-3 appear to be actively installing cooling and backup generators nearby. The pads for Buildings 6-10 to the north have also been visibly cleared, with foundations for Buildings 6 and 7 underway.
    IT power running
    None
    Whole facility
    None

    Epoch AI projects 1,400 MW of IT power by November 11, 2028. A projection, not a fact yet.

Heat Watch

OpenAI Stargate Shackelford: heat seen from space

Over the last three summers NASA's MODIS read the ground here +0.7 °C against the land 5 to 10 km around it by day.

Timeline

Announcements and evidence, by date

What was promised and what was seen, in the order it became public. The full dated record of each site is on its Power Map page.

  1. OpenAI Stargate Shackelford: 0 buildings operating, no IT power yet.Evidence · Epoch AI, on the Power Map

  2. OpenAI, Oracle and SoftBank: Over 5.5 GW for three Oracle sites and an Abilene expansion together.Announcement · OpenAI

  3. OpenAI Stargate Shackelford: 0 buildings operating, no IT power yet.Evidence · Epoch AI, on the Power Map

  4. OpenAI Stargate Shackelford: 0 buildings operating, no IT power yet.Evidence · Epoch AI, on the Power Map

  5. OpenAI Stargate Shackelford: 0 buildings operating, no IT power yet.Evidence · Epoch AI, on the Power Map

  6. Vantage Data Centers: 1.4 GW of critical IT capacity across 10 data centers. Promised: first data center delivered in the second half of 2026.Announcement · Vantage Data Centers, undated page read on this date

Corrections

See something wrong? File a correction

Sign in with your SI Passport and say what is wrong, with a link to a public source. The team reads the source before anything changes, and approved corrections stay on this page.

File a correction

Sign in with your SI Passport to file a correction. It is a free message signature and never moves tokens.

A correction needs a link. Nothing shows until the team approves it. If your Passport carries an Org check it shows here, and an organization correcting its own project is labeled as such.

Corrections on file · 0

  • Loading the corrections on file.

Sources

Every link behind this page

Read on November 11, 2026. An undated page carries the date it was read.