CoreWeave Marble NC is an SI data center in Marble, North Carolina, United States, owned by CoreWeave and used by OpenAI (Epoch AI rates this speculative). Epoch AI estimates its IT power at 65 MW as of May 6, 2026, with 1 building operating. Its public timeline starts on June 25, 2024.
- IT power
- 65 MWMay 6, 2026
- Facility power
- 91 MW
- Status
- Operating
- Buildings operating
- 1
Where it is
The site and its facts
CoreWeave Marble NC on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.
- Place
- Marble, North Carolina, United States
- Address
- 155 Palmer Ln, Marble, NC 28905
- Coordinates
- 35.1875° N, 83.9161° W
- Owner
- CoreWeave
- Users
- OpenAI (Epoch AI rates this speculative)
- Chips
- B200
- Compute
- About 78,828 H100 equivalentsEpoch AI estimate, May 6, 2026
Heat Watch
CoreWeave Marble NC: heat seen from space
Over the last three summers NASA's MODIS read the ground here +1.9 °C against the land 5 to 10 km around it by day.
Lights On
CoreWeave Marble NC: light at night
NASA's night imagery read 8.6 of 100 over this site in October 2026, against 2.0 in October 2018, the first month read. Against a year before: -4.4 points. Light is not proof of what runs inside.
Timeline
Dated, from the public record
Epoch AI's dated notes on CoreWeave Marble NC, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.
Core Scientific announced that CoreWeave would receive about 70 MW of HPC infrastructure from 100 MW of owned infrastructure. Site modifications were expected to begin in H2 2024.
No IT power yet0 operating
The site has been energized. Two of three data halls had been delivered at 37 billable MW, supporting about 15000 Grace Blackwell GPUs. The third hall was still in commissioning.
36 MW1 operating
Satellite imagery shows the main data hall and southern utility yard substantially complete. No new public MW disclosure, so this keeps the March 2026 public 36 MW state.
36 MW1 operating
Core Scientific said Marble was fully handed over to CoreWeave with about 65 MW of billable customer power online.
65 MW1 operating
Adopt a site
Watch CoreWeave Marble NC
One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.
The watcher
Loading the watcher.
Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.
Approved updates · 0
- Approved updates show here with their date.
Sources
Where the facts come from
The sources Epoch AI lists for this site, and the record itself.
- Core Scientific - Q1 2026 Fiscal Earnings Call
- Core Scientific - Official Marble, NC Datacenter page
- Core Scientific - Q1 2025 Earnings Presentation
- Core Scientific - June 2024 Investor and Analyst Day
- Epoch AI, "AI data centers", the record for CoreWeave Marble NC (CC BY 4.0), retrieved November 10, 2026
Nearby
The nearest SI data centers
The four closest sites on the Power Map, as the crow flies.
108 km away
CoreWeave Dalton 1 & 2
Dalton, Georgia, United States
28 MW IT power
163 km away
xAI QTS Atlanta
Atlanta, Georgia, United States
17.3 MW IT power
200 km away
Microsoft Fairwater Atlanta
Fayetteville, Georgia, United States
636 MW IT power
250 km away
Meta Huntsville
Huntsville, Alabama, United States
146 MW IT power
Questions
CoreWeave Marble NC, answered
Where it is, who owns it and how much power it uses, from the public record.
Where is CoreWeave Marble NC?
CoreWeave Marble NC is in Marble, North Carolina, United States, at 155 Palmer Ln, Marble, NC 28905. Epoch AI publishes its coordinates as 35.1875, -83.9161.
Who owns CoreWeave Marble NC?
Epoch AI lists CoreWeave as its owner and OpenAI (Epoch AI rates this speculative) as its user.
How much power does CoreWeave Marble NC use?
Epoch AI estimates its IT power at 65 MW as of May 6, 2026, and its total facility power at 91 MW.
Is CoreWeave Marble NC operating?
Yes. Epoch AI counts 1 building operating as of May 6, 2026.
Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).