Power Map · Operating, expanding
Huawei Horinger, Hohhot
Huawei Horinger is an SI data center in Hohhot, Inner Mongolia, China, owned by Huawei. Epoch AI estimates its IT power at 169.9 MW as of August 18, 2026, with 3 buildings operating, and projects 351.1 MW by February 17, 2028. Its public timeline starts on October 8, 2023.
- IT power
- 169.9 MWAug 18, 2026
- Facility power
- 212.4 MW
- Status
- Operating, expanding
- Buildings operating
- 3
Where it is
The site and its facts
Huawei Horinger on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.
- Place
- Hohhot, Inner Mongolia, China
- Address
- Huawei, Horinger, China
- Coordinates
- 40.5397° N, 111.8277° E
- Owner
- Huawei
- Chips
- Ascend 910C, Ascend 910B
- Compute
- About 81,044 H100 equivalentsEpoch AI estimate, Aug 18, 2026
- Projected
- 351.1 MW IT power by February 17, 2028Epoch AI projection, not a fact yet
Heat Watch
Huawei Horinger: heat seen from space
Over the last three summers NASA's MODIS read the ground here +0.9 °C against the land 5 to 10 km around it by day.
Lights On
Huawei Horinger: light at night
NASA's night imagery read 49.9 of 100 over this site in October 2026, against 17.3 in October 2018, the first month read. Against a year before: +10.4 points. Light is not proof of what runs inside.
Timeline
Dated, from the public record
Epoch AI's dated notes on Huawei Horinger, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.
Land clearing begins simultaneously for all three zones (West, North, and South) after an official ceremony. The West and South zones later have the cooling capacity indicative of AI workloads, while the North Zone does not.
No IT power yet0 operating
In the West Zone, Building 1 is structurally complete. In the South Zone, Building 4 is structurally complete except for several cooling towers to be installed later. Buildings 2 (West Zone) and 5 (South Zone) have shells under construction.
No IT power yet0 operating
In the South Zone, paving and landscaping around Building 4 is mostly complete, while Building 5 still needs cooling and backup generators to be installed.
No IT power yet0 operating
In the West Zone, Building 1 is operational, based on its structural completion and colored motion artifacts on some of the cooling tower fans.
42.4 MW1 operating
Building 1 appears to have condensed water vapor above some cooling towers, suggesting they are still operating. Cooling towers have been added to Building 4, but we do not see any condensed water vapor, and there is still a crane over the building. So we don't think Building 4 is operational at full capacity yet.
42.4 MW1 operating
Building 4 is operational, based on its structural completion, the colored motion artifacts on some of the cooling tower fans, and cars parked out front (between the main building and the backup generator enclosure). Building 5 is almost structurally complete, but there is still some work to do in front of the backup generator enclosure.
86.8 MW2 operating
In the West Zone, Building 2 is structurally complete but still has some construction equipment around it.
86.8 MW2 operating
In the South Zone, Building 5 is operational, based on its structural completion, and the colored motion artifacts on the some of the cooling tower fans. Building 6 (South Zone) is under construction. In the West Zone, Building 3 has not begun construction.
169.9 MW3 operating
In the West Zone, Building 2 is operational (estimate). A local government announcement said a "completion acceptance filing" was completed for Building 2 around September 23, 2026, "marking a critical step toward the project's entry into operation". We assume this corresponds to structural completion, since there was minimal construction activity by August 18th. We then allow 3 more months for a full fit-out of AI servers.
216.4 MW4 operating
Building 6 (South Zone) is operational (estimate). This was the only new building under construction as of August 2026. We estimate the operational date based on an average of (1) previous buildings taking about 2 years on average from starting the building shell to becoming operational at ~full capacity, (2) a similar building at the Huawei Wuhu campus taking an estimated 550 days to become fully operational. Building 6 can reportedly support 100,000 AI accelerator cards and will deploy Huawei Ascend 950 chips. Based on the timing, we assume it has capacity for 100,000 Ascend 950DT chips (Ascend 950DT is ramping a few months later than 950PR). As with the other buildings, we multiply this capacity by the reported rack occupancy rate for the Horinger New Area (about 76%).
351.1 MW5 operating
Adopt a site
Watch Huawei Horinger
One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.
The watcher
Loading the watcher.
Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.
Approved updates · 0
- Approved updates show here with their date.
Sources
Where the facts come from
The sources Epoch AI lists for this site, and the record itself.
- Epoch AI, "AI data centers", the record for Huawei Horinger (CC BY 4.0), retrieved November 10, 2026
Nearby
The nearest SI data centers
The four closest sites on the Power Map, as the crow flies.
Questions
Huawei Horinger, answered
Where it is, who owns it and how much power it uses, from the public record.
Where is Huawei Horinger?
Huawei Horinger is in Hohhot, Inner Mongolia, China, at Huawei, Horinger, China. Epoch AI publishes its coordinates as 40.5397, 111.8277.
Who owns Huawei Horinger?
Epoch AI lists Huawei as its owner.
How much power does Huawei Horinger use?
Epoch AI estimates its IT power at 169.9 MW as of August 18, 2026, and its total facility power at 212.4 MW. It projects 351.1 MW of IT power by February 17, 2028.
Is Huawei Horinger operating?
Yes, and it is growing. Epoch AI counts 3 buildings operating as of August 18, 2026, with more capacity on its timeline.
Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).