VNET Bayin Ulanqab, Ulanqab

VNET Bayin Ulanqab is an SI data center in Ulanqab, Inner Mongolia, China, owned by ByteDance (Epoch AI rates this speculative) and used by ByteDance (Epoch AI rates this speculative). Epoch AI estimates its IT power at 221 MW as of May 6, 2026, with 4 buildings operating, and projects 700 MW by September 1, 2027. Its public timeline starts on March 15, 2024.

IT power
221 MWMay 6, 2026
Facility power
252 MW
Status
Operating, expanding
Buildings operating
4

Where it is

The site and its facts

VNET Bayin Ulanqab on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.

Ulanqab, Inner Mongolia, ChinaOpen in OpenStreetMap
Place
Ulanqab, Inner Mongolia, China
Address
Bayin, Ulanqab, China
Coordinates
40.9811° N, 113.3143° E
Owner
ByteDance (Epoch AI rates this speculative)
Users
ByteDance (Epoch AI rates this speculative)
Project
10 GW Hyperscale 2.0
Chips
Ascend 910C
Compute
About 122,789 H100 equivalentsEpoch AI estimate, May 6, 2026
Projected
700 MW IT power by September 1, 2027Epoch AI projection, not a fact yet

Heat Watch

VNET Bayin Ulanqab: heat seen from space

Over the last three summers NASA's MODIS read the ground here +0.7 °C against the land 5 to 10 km around it by day.

Lights On

VNET Bayin Ulanqab: light at night

NASA's night imagery read 36.5 of 100 over this site in October 2026, against 1.4 in October 2018, the first month read. Against a year before: -1.3 points. Light is not proof of what runs inside.

Timeline

Dated, from the public record

Epoch AI's dated notes on VNET Bayin Ulanqab, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.

  1. Land clearing begins late March, as can be seen in satellite images (eastern part: buildings 1 & 2). VNET officially announces its signing ceremony with the Ulanqab municipal government and Shandong Hi-Speed Holdings.

    No IT power yet0 operating

  2. Satellite imagery shows five buildings (1, 2, 3, 4, 5) under construction. Chillers are in place, but no roof is complete for any building.

    No IT power yet0 operating

  3. Building 1 is operational, based on a 3-month fit-out period after structural completion in April, as can be seen from satellite imagery.

    38 MW1 operating

  4. Satellite imagery shows that in total nine buildings have started construction, with building 1 being the only one operational. Buildings 2 and 5 are structurally complete, and the final roofs for buildings 3 and 4 have begun.

    38 MW1 operating

  5. Buildings 2 and 5 are operational, based on a 3-month fit-out period after structural completion in August, as can be seen from satellite imagery. Land clearing for the northern part of campus (buildings 10 and 11) has started.

    171 MW3 operating

  6. Building 4 is operational, similarly based on a 3-month fit-out period after structural completion in September, as seen from satellite imagery.

    221 MW4 operating

  7. Satellite imagery shows four operational buildings (1, 2, 4, 5), and the western part of campus (6, 7, 8, 9) has made significant construction progress. The foundation for the northern part of campus (10, 11) has started.

    221 MW4 operating

  8. Satellite imagery shows building 9 has completed all its chillers, with only its roof remaining. Previous building completion timelines would imply this building will be operational by the end of 2026.

    221 MW4 operating

  9. Estimated: the nine-building section of the campus is projected to be fully operational by late 2027 or early 2028. VNET's eastern cluster (buildings 1-5) took roughly a year each from clearing to operational based on satellite imagery. The western cluster (buildings 6-9) was cleared in late 2024 but as of mid-2026 is not yet structurally complete, putting each on track for ~2 years from clearing to operational. Buildings 10 and 11 are projected to be completed sometime later. Comparable data centers in Ulanqab are expected to take at least 6 months per phase (China Unicom).

    700 MW9 operating

Adopt a site

Watch VNET Bayin Ulanqab

One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.

The watcher

Loading the watcher.

Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.

Approved updates · 0

  • Approved updates show here with their date.

Sources

Where the facts come from

The sources Epoch AI lists for this site, and the record itself.

  • Epoch AI, "AI data centers", the record for VNET Bayin Ulanqab (CC BY 4.0), retrieved November 10, 2026

Questions

VNET Bayin Ulanqab, answered

Where it is, who owns it and how much power it uses, from the public record.

Where is VNET Bayin Ulanqab?

VNET Bayin Ulanqab is in Ulanqab, Inner Mongolia, China, at Bayin, Ulanqab, China. Epoch AI publishes its coordinates as 40.9811, 113.3143.

Who owns VNET Bayin Ulanqab?

Epoch AI lists ByteDance (Epoch AI rates this speculative) as its owner and ByteDance (Epoch AI rates this speculative) as its user.

How much power does VNET Bayin Ulanqab use?

Epoch AI estimates its IT power at 221 MW as of May 6, 2026, and its total facility power at 252 MW. It projects 700 MW of IT power by September 1, 2027.

Is VNET Bayin Ulanqab operating?

Yes, and it is growing. Epoch AI counts 4 buildings operating as of May 6, 2026, with more capacity on its timeline.

Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).