Power Map · Operating, expanding
Meta Cheyenne, Cheyenne
Meta Cheyenne is an SI data center in Cheyenne, Wyoming, United States, owned by Meta and used by Meta. Epoch AI estimates its IT power at 152 MW as of July 25, 2026, with 2 buildings operating, and projects 207 MW by February 15, 2027. Its public timeline starts on April 1, 2024.
- IT power
- 152 MWJul 25, 2026
- Facility power
- 182 MW
- Status
- Operating, expanding
- Buildings operating
- 2
Where it is
The site and its facts
Meta Cheyenne on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.
- Place
- Cheyenne, Wyoming, United States
- Address
- Cheyenne, WY 82007, USA
- Coordinates
- 41.0801° N, 104.8241° W
- Owner
- Meta
- Users
- Meta
- Chips
- B300
- Compute
- About 172,815 H100 equivalentsEpoch AI estimate, Jul 25, 2026
- Projected
- 207 MW IT power by February 15, 2027Epoch AI projection, not a fact yet
Heat Watch
Meta Cheyenne: heat seen from space
Over the last three summers NASA's MODIS read the ground here -0.4 °C against the land 5 to 10 km around it by day.
Lights On
Meta Cheyenne: light at night
NASA's night imagery read 32.7 of 100 over this site in October 2026, against 7.1 in October 2018, the first month read. Against a year before: +17.8 points. Light is not proof of what runs inside.
Timeline
Dated, from the public record
Epoch AI's dated notes on Meta Cheyenne, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.
Land clearing begins.
No IT power yet0 operating
Structure for Building 1 and 2 under construction.
No IT power yet0 operating
Building 1 shell and cooling looks complete, Building 2 roof almost complete.
No IT power yet0 operating
Both buildings estimated to be operational.
152 MW2 operating
Buildings 3 and 4 are similar in style and size to the ones seen at the Prometheus site, we estimate their operability based on that timeline.
207 MW4 operating
Adopt a site
Watch Meta Cheyenne
One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.
The watcher
Loading the watcher.
Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.
Approved updates · 0
- Approved updates show here with their date.
Sources
Where the facts come from
The sources Epoch AI lists for this site, and the record itself.
- Meta Introduction to the Cheyenne Project
- Fortis Construction announcement
- Press announcement suggesting a 2027 operational date
- Epoch AI, "AI data centers", the record for Meta Cheyenne (CC BY 4.0), retrieved November 10, 2026
Nearby
The nearest SI data centers
The four closest sites on the Power Map, as the crow flies.
613 km away
Meta Eagle Mountain
Eagle Mountain, Utah, United States
133 MW IT power
614 km away
QTS Eagle Mountain
Eagle Mountain, Utah, United States
IT power not stated
686 km away
Google Lincoln
Lincoln, Nebraska, United States
141 MW IT power
716 km away
Meta Los Lunas
Los Lunas, New Mexico, United States
118 MW IT power
Questions
Meta Cheyenne, answered
Where it is, who owns it and how much power it uses, from the public record.
Where is Meta Cheyenne?
Meta Cheyenne is in Cheyenne, Wyoming, United States, at Cheyenne, WY 82007, USA. Epoch AI publishes its coordinates as 41.0801, -104.8241.
Who owns Meta Cheyenne?
Epoch AI lists Meta as its owner and Meta as its user.
How much power does Meta Cheyenne use?
Epoch AI estimates its IT power at 152 MW as of July 25, 2026, and its total facility power at 182 MW. It projects 207 MW of IT power by February 15, 2027.
Is Meta Cheyenne operating?
Yes, and it is growing. Epoch AI counts 2 buildings operating as of July 25, 2026, with more capacity on its timeline.
Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).