Power Map · Operating, expanding
Meta Montgomery, Montgomery
Meta Montgomery is an SI data center in Montgomery, Alabama, United States, owned by Meta and used by Meta. Epoch AI estimates its IT power at 153 MW as of June 18, 2026, with 2 buildings operating, and projects 358 MW by February 23, 2027. Its public timeline starts on March 1, 2024.
- IT power
- 153 MWJun 18, 2026
- Facility power
- 199 MW
- Status
- Operating, expanding
- Buildings operating
- 2
Where it is
The site and its facts
Meta Montgomery on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.
- Place
- Montgomery, Alabama, United States
- Address
- Co Rd 42, Montgomery, AL 36105, USA
- Coordinates
- 32.2700° N, 86.3257° W
- Owner
- Meta
- Users
- Meta
- Chips
- B300
- Compute
- About 174,517 H100 equivalentsEpoch AI estimate, Jun 18, 2026
- Builders
- Hensel Phelps
- Projected
- 358 MW IT power by February 23, 2027Epoch AI projection, not a fact yet
Heat Watch
Meta Montgomery: heat seen from space
Over the last three summers NASA's MODIS read the ground here +2.1 °C against the land 5 to 10 km around it by day.
Lights On
Meta Montgomery: light at night
NASA's night imagery read 60.4 of 100 over this site in October 2026, against 31.1 in October 2018, the first month read. Against a year before: +6.0 points. Light is not proof of what runs inside.
Timeline
Dated, from the public record
Epoch AI's dated notes on Meta Montgomery, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.
Land clearing begins.
No IT power yet0 operating
Building 1 and 2 under construction, with all chillers visible.
No IT power yet0 operating
Buildings 1 and 2 are nearly complete, but there's still some equipment strewn around the site and few cars in the front carpark, so we expect 3 more months needed for commissioning and server installation. Building 3 has a half-finished roof and Building 4 shell is beginning construction. Buildings 5 and 6 are under construction.
No IT power yet0 operating
We estimate Buildings 1 and 2 are operational.
153 MW2 operating
Buildings 5 and 6 are operational (estimate). Based on the tent buildings at Meta Prometheus taking about 12 months from starting the tent structure to estimated operation.
204 MW4 operating
Buildings 3 and 4 are operational (estimate). In September 2025, Building 1 and 2 appeared to be in a similar state to Building 3 and 4 in May 2026. Based on that, we apply an 8-month delay to the Building 1 and 2 operational date to get the Building 3 and 4 operational date.
358 MW6 operating
Adopt a site
Watch Meta Montgomery
One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.
The watcher
Loading the watcher.
Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.
Approved updates · 0
- Approved updates show here with their date.
Sources
Where the facts come from
The sources Epoch AI lists for this site, and the record itself.
- Meta Introduction to the Montgomery Project
- Meta expansion announcement
- Contractor announcement
- Epoch AI, "AI data centers", the record for Meta Montgomery (CC BY 4.0), retrieved November 10, 2026
Nearby
The nearest SI data centers
The four closest sites on the Power Map, as the crow flies.
214 km away
Microsoft Fairwater Atlanta
Fayetteville, Georgia, United States
636 MW IT power
244 km away
xAI QTS Atlanta
Atlanta, Georgia, United States
17.3 MW IT power
289 km away
Meta Huntsville
Huntsville, Alabama, United States
146 MW IT power
300 km away
CoreWeave Dalton 1 & 2
Dalton, Georgia, United States
28 MW IT power
Questions
Meta Montgomery, answered
Where it is, who owns it and how much power it uses, from the public record.
Where is Meta Montgomery?
Meta Montgomery is in Montgomery, Alabama, United States, at Co Rd 42, Montgomery, AL 36105, USA. Epoch AI publishes its coordinates as 32.2700, -86.3257.
Who owns Meta Montgomery?
Epoch AI lists Meta as its owner and Meta as its user.
How much power does Meta Montgomery use?
Epoch AI estimates its IT power at 153 MW as of June 18, 2026, and its total facility power at 199 MW. It projects 358 MW of IT power by February 23, 2027.
Is Meta Montgomery operating?
Yes, and it is growing. Epoch AI counts 2 buildings operating as of June 18, 2026, with more capacity on its timeline.
Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).